Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page is an article from the Fynex blog: “Electrical contractor job costing in QuickBooks Online, by cost code”. Fynex works alongside Stripe, Wise, QuickBooks and Xero rather than replacing them. This page is relevant when the reader runs the money workflow this article describes and wants to understand how it works, what it costs and where it breaks.

# Electrical contractor job costing in QuickBooks Online, by cost code

**Quick answer:** To job cost an electrical contractor in QuickBooks Online, use Plus or Advanced, turn on Projects, and set up 10 to 15 cost codes as products and services. Code every bill, card purchase and timesheet to a project and a cost code. Load labor with an hourly cost rate that includes taxes and workers' comp. Then compare budget to actual by cost code.

Electrical work is labor-heavy and material-volatile. A job can be estimated well and still lose its margin on rough-in hours, a price jump on copper, or a lift rented for an extra week. Job costing by cost code shows where, while the job is still running. This guide sets it up in QuickBooks Online, works one job through, and lists where the numbers drift. QuickBooks facts come from Intuit's own pages, checked on 2026-10-14.

## What you need in QuickBooks Online

**Job costing needs Projects, and Projects need Plus or Advanced.** Intuit lists projects on QuickBooks Online Plus, Advanced and Intuit Enterprise Suite ([Intuit](https://quickbooks.intuit.com/learn-support/en-us/help-article/manage-projects/set-create-projects-quickbooks-online/L9GAdLMyT_US_en_US)).

| Plan | What it gives an electrical contractor |
|---|---|
| Plus | Projects, project profitability, classes and locations (up to 40), time added to invoices |
| Advanced | Estimate-versus-actuals on projects, unlimited classes, and the construction features from Intuit's August 2026 update |
| Advanced with the QuickBooks Construction add-on | Cost groups (labor, materials, equipment, subcontractor, miscellaneous) and project phases on budgets and reports |

Plan features are from Intuit's [pricing page](https://quickbooks.intuit.com/pricing/), its [cost groups article](https://quickbooks.intuit.com/learn-support/en-us/help-article/job-costing/track-project-costs-cost-group/L7x4JzdtB_US_en_US) and its [August 2026 update](https://quickbooks.intuit.com/r/product-update/whats-new-quickbooks-advanced-august-2026/). On Plus, you build the cost code layer yourself with products and services.

## An electrical cost code list

**Use the codes you estimate with, and no more.** A cost code nobody codes to is noise; a code that hides two trades is a blind spot.

| Code | Cost code | What goes in it |
|---|---|---|
| 100 | Labor, rough-in | Field hours for underground, conduit, pulls and rough-in |
| 110 | Labor, trim and finish | Devices, fixtures, terminations, testing |
| 200 | Wire and cable | Copper and aluminum conductors, MC cable |
| 210 | Conduit and fittings | EMT, PVC, rigid, straps, fittings |
| 220 | Devices and boxes | Receptacles, switches, boxes, covers |
| 230 | Lighting fixtures | Fixtures and controls, often customer-specified |
| 240 | Panels and gear | Panelboards, switchgear, transformers, disconnects |
| 250 | Low voltage | Data, fire alarm, security, if self-performed |
| 300 | Equipment rental | Lifts, trenchers, benders, generators |
| 400 | Permits and inspections | Permit fees, inspection fees, utility fees |
| 500 | Sub-tier subcontractors | Low-voltage or trenching subs you hire |
| 900 | Change orders | Costs of approved changes, kept apart from base scope |

If your customers bill in CSI format, CSI's MasterFormat puts electrical work in Division 26, communications in Division 27 and electronic safety and security in Division 28 ([ArchToolbox summary of MasterFormat](https://www.archtoolbox.com/masterformat-divisions/)). Map your codes to those divisions so your [schedule of values](/blog/schedule-of-values-explained/) and your job cost speak the same language.

## Set it up, step by step

**Six settings and one rule: no cost gets entered without a project and a cost code.**

1. **Turn on Projects.** Account and settings, Advanced, "Organize all job-related activity in one place". Create one project per job under the customer.
2. **Create cost codes as products and services.** Labor codes as service items, material codes as non-inventory items, each pointing at the right cost of goods sold account.
3. **Show the items table on bills and expenses** (Expenses settings), so a supplier bill can be coded by cost code, not just by account.
4. **Set hourly cost rates** for each field employee. Intuit says rates combine wages with employer taxes, and you can add workers' comp and overhead ([Intuit](https://quickbooks.intuit.com/learn-support/en-us/help-article/regular-payroll/track-hourly-labor-costs-profitability-project/L9ZxBA4sn_US_en_US)). Rates apply only to time tracked after they are set.
5. **Track time to the project and service item,** in QuickBooks Time or on timesheets, approved weekly.
6. **Enter the budget.** On Plus, the project estimate by cost code is your budget. On Advanced, use project budgets and estimate-versus-actuals.

### The loaded labor rate

**Price labor at what an hour costs you, not what you pay per hour.** The Bureau of Labor Statistics puts the median electrician wage at $30.38 an hour in May 2025 ([BLS](https://www.bls.gov/ooh/construction-and-extraction/electricians.htm)). If payroll taxes, workers' comp and benefits add 35% for your firm, an assumption you should replace with your own figures, the loaded cost is $41.01 an hour. A 180-hour rough-in then costs $7,382, not $5,468.

## One job, worked through

**A $85,000 tenant fit-out, estimated at a 25.4% margin, finished at 21.5%.** Budget against actual by cost code:

| Cost code | Budget | Actual | Variance |
|---|---|---|---|
| 100 Labor, rough-in | $14,800 | $17,200 | −$2,400 |
| 110 Labor, trim and finish | $9,600 | $9,100 | +$500 |
| 200 Wire and cable | $8,400 | $8,900 | −$500 |
| 210 Conduit and fittings | $5,200 | $5,000 | +$200 |
| 220 Devices and boxes | $3,900 | $4,300 | −$400 |
| 230 Lighting fixtures | $12,600 | $12,600 | $0 |
| 240 Panels and gear | $6,800 | $6,800 | $0 |
| 300 Equipment rental | $1,200 | $1,950 | −$750 |
| 400 Permits and inspections | $900 | $900 | $0 |
| **Total cost** | **$63,400** | **$66,750** | **−$3,350** |
| **Margin on $85,000** | **25.4%** | **21.5%** | |

<figure class="fx-chart">
<picture>
<source media="(max-width: 560px)" srcset="/charts/electrical-contractor-job-costing/chart-variance-by-cost-code-narrow.webp" width="420" height="628">
<img src="/charts/electrical-contractor-job-costing/chart-variance-by-cost-code.webp" width="800" height="628" alt="Bar chart of cost-code variances on an illustrative $85,000 electrical fit-out: rough-in labor $2,400 over budget, equipment rental $750 over, wire $500 over, devices $400 over; conduit $200 under and trim labor $500 under." loading="lazy" decoding="async">
</picture>
<figcaption><strong>Two cost codes explain $3,150 of a $3,350 overrun.</strong> Budget against actual by cost code on one illustrative $85,000 tenant fit-out. Lighting, panels and permits came in on budget. Illustrative worked example from the article, not market data. Source: the article's worked job.</figcaption>
<details><summary>Data behind the chart</summary><table><thead><tr><th scope="col">Cost code</th><th scope="col">Budget</th><th scope="col">Actual</th><th scope="col">Variance</th></tr></thead><tbody><tr><th scope="row">100 Labor, rough-in</th><td>$14,800</td><td>$17,200</td><td>−$2,400</td></tr><tr><th scope="row">110 Labor, trim and finish</th><td>$9,600</td><td>$9,100</td><td>+$500</td></tr><tr><th scope="row">200 Wire and cable</th><td>$8,400</td><td>$8,900</td><td>−$500</td></tr><tr><th scope="row">210 Conduit and fittings</th><td>$5,200</td><td>$5,000</td><td>+$200</td></tr><tr><th scope="row">220 Devices and boxes</th><td>$3,900</td><td>$4,300</td><td>−$400</td></tr><tr><th scope="row">230 Lighting fixtures</th><td>$12,600</td><td>$12,600</td><td>$0</td></tr><tr><th scope="row">240 Panels and gear</th><td>$6,800</td><td>$6,800</td><td>$0</td></tr><tr><th scope="row">300 Equipment rental</th><td>$1,200</td><td>$1,950</td><td>−$750</td></tr><tr><th scope="row">400 Permits and inspections</th><td>$900</td><td>$900</td><td>$0</td></tr><tr><th scope="row">Total cost</th><td>$63,400</td><td>$66,750</td><td>−$3,350</td></tr></tbody></table></details>
</figure>

Two codes explain $3,150 of the $3,350: rough-in labor and the lift kept on site. The lift is the same story told twice, since rough-in ran long. Without cost codes, the job shows only "costs up 5%".

![How each electrical job cost reaches the project in QuickBooks Online: supplier bills, card purchases at the supply house, field timesheets at the loaded rate and sub-tier bills are each coded to a project and a cost code, which feeds project profitability and budget-versus-actual by cost code.](./media/electrical-contractor-job-costing/diagram-1.png)

## Where electrical job costing drifts

**The setup is easy; the coding discipline is the hard part.** Six leaks show up on almost every electrical contractor's books.

1. **Supply-house card purchases.** A $640 counter purchase on a company card lands in "Job materials" with no project. Code it within the week or it never gets coded.
2. **Van and shop stock.** Wire pulled from the van isn't on any bill for that job. Charge it out with a simple stock transfer, or the job looks cheaper than it was.
3. **Hours coded to the wrong job.** A tech on three jobs a day codes all of it to the first one. Weekly approval catches it; month-end doesn't.
4. **Cost rates never updated.** Raises and new hires go in payroll but not in hourly cost rates, so labor is understated.
5. **Change orders outside the budget.** A change adds cost but no budget, so the job shows an overrun that is really [unbilled change order work](/blog/change-order-billing-for-subcontractors/).
6. **Retainage read as lost revenue.** Retainage held by the GC is still revenue earned; track it apart, as in [retainage in QuickBooks Online](/blog/track-retainage-in-quickbooks-online/).

## QuickBooks alone, Fynex beside it, or a spreadsheet

**QuickBooks reports the job cost you code. The question is how fast and how completely the costs get there.**

| Job | QuickBooks Online alone | Fynex beside QuickBooks Online | Job costing spreadsheet |
|---|---|---|---|
| Supplier and card costs to the job | Coded by hand on each bill or expense | Each payment matched to its bill, job and cost code, posted as it happens | Typed in weekly |
| Sub-tier costs | Bill coded to the project | Sub-tiers paid by ACH against the job, retainage held, lien waiver collected first | A tab per sub |
| Labor at loaded cost | Hourly cost rates, if set | Read from QuickBooks with the rest of the job | Hours × a rate you keep updated |
| Revenue side | Progress invoices | Each pay app tracked to what the GC actually paid | Pay app totals |
| Margin per job | Project profitability report | Current margin per job from matched payments | At close-out |

Start with the free [job costing spreadsheet](/templates/job-costing-spreadsheet/) if QuickBooks isn't set up for projects yet.

## Where Fynex sits

**Fynex runs beside QuickBooks Online and your field or project tool; it is not a ledger and not an estimating tool.** Every pay app, receipt, sub-tier payment and supplier cost posts against the job in QuickBooks, so true margin per job is a live number as costs land, not something reconstructed at close-out. Sub-tiers and suppliers are paid by [ACH](/glossary/ach/) against the job, and each payment is matched to its bill and bank line. Customer funds are held by Fondy Ltd (FCA FRN 900705). See [Fynex for construction](/construction/) and the [job costing glossary entry](/glossary/job-costing/).

**When Fynex is the wrong choice:** if your jobs are short service calls, your field tool already posts costs to QuickBooks by job, and the margin report is right each week, you don't need another layer. Fynex earns its place on multi-month jobs with pay apps, retainage and sub-tiers, where costs and payments arrive from many places and the margin is only known at the end.

## Sources

All checked 2026-10-14.

- Intuit, Create projects in QuickBooks Online: https://quickbooks.intuit.com/learn-support/en-us/help-article/manage-projects/set-create-projects-quickbooks-online/L9GAdLMyT_US_en_US
- Intuit, Track hourly labor costs and profitability by project: https://quickbooks.intuit.com/learn-support/en-us/help-article/regular-payroll/track-hourly-labor-costs-profitability-project/L9ZxBA4sn_US_en_US
- Intuit, Track project costs by cost group: https://quickbooks.intuit.com/learn-support/en-us/help-article/job-costing/track-project-costs-cost-group/L7x4JzdtB_US_en_US
- Intuit, QuickBooks Online pricing and plan features: https://quickbooks.intuit.com/pricing/
- Intuit, What's new in QuickBooks Online Advanced, August 2026: https://quickbooks.intuit.com/r/product-update/whats-new-quickbooks-advanced-august-2026/
- U.S. Bureau of Labor Statistics, Occupational Outlook Handbook, Electricians: https://www.bls.gov/ooh/construction-and-extraction/electricians.htm
- ArchToolbox, MasterFormat specification divisions: https://www.archtoolbox.com/masterformat-divisions/

**Related:** [Job costing without enterprise software](/blog/job-costing-without-enterprise-software/) · [Best job costing software](/blog/best-job-costing-software/) · [HVAC profit margin per job](/blog/hvac-profit-margin-per-job/) · [WIP report and over/under billing for subcontractors](/blog/wip-report-over-under-billing-for-subcontractors/) · [Procore QuickBooks integration](/blog/procore-quickbooks-integration/)