Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page is an article from the Fynex blog: “Pay less notice explained: payment notices and the Construction Act timeline”. Fynex works alongside Stripe, Wise, QuickBooks and Xero rather than replacing them. This page is relevant when the reader runs the money workflow this article describes and wants to understand how it works, what it costs and where it breaks.

# Pay less notice explained: payment notices and the Construction Act timeline

**Quick answer:** A pay less notice is how a payer under a UK construction contract pays less than the notified sum. It must state the sum considered due and how it is calculated, and arrive no later than the agreed period before the final date for payment: seven days under the Scheme for Construction Contracts. Miss it, and the notified sum is due in full. This is not legal advice.

The Construction Act payment rules turn every application for payment into a sequence of dated notices. A specialist contractor sits on both sides: it receives payment notices and pay less notices from the main contractor, and owes them to its own subcontractors. This guide sets out the four dates, works one application through in pounds, and covers what happens when a notice is late or missing. It follows the Housing Grants, Construction and Regeneration Act 1996 as amended in 2011, and the Scheme for Construction Contracts (England and Wales) Regulations 1998, read on legislation.gov.uk on 2026-10-14.

## The four dates that run every payment

**Every interim payment under a construction contract has a due date, a payment notice, a possible pay less notice and a final date for payment.** The contract sets most of them; the Scheme fills any gap.

| Step | Who gives it | Deadline | Where it comes from |
|---|---|---|---|
| Application for payment | Payee | As the contract says | The contract; can count as the payee's notice (s110B(4)) |
| Payment due date | (a date, not a notice) | As the contract says; Scheme default: 7 days after the end of the period, or the claim if later | s110; Scheme para 4 |
| Payment notice | Payer (or a specified person) | Not later than 5 days after the payment due date | s110A; Scheme para 9 |
| Pay less notice | Payer (or a specified person) | Not later than the prescribed period before the final date; Scheme default: 7 days | s111(3)–(5), (7); Scheme para 10 |
| Final date for payment | (a date, not a notice) | As the contract says; Scheme default: 17 days after the due date | s110(1)(b); Scheme para 8 |

The parties are free to agree how long the period is between the due date and the final date (s110(1)). They can also agree the pay less notice period (s111(7)). The Scheme applies only where the contract is silent or non-compliant.

## A worked example in £

**A specialist contractor applies for £48,000 for work in March, under a contract that leaves the dates to the Scheme.** The application goes in on 31 March, the end of the period.

| Date | Event | Amount |
|---|---|---|
| 31 March | Application for payment | £48,000 applied for |
| 7 April | Payment due date (7 days after the period ends) | |
| by 12 April | Main contractor's payment notice: sum considered due, with its basis | £46,500 valued |
| by 17 April | Pay less notice, if any: £5,500 for a damaged ceiling grid, with the calculation | £41,000 now due |
| 24 April | Final date for payment (17 days after the due date) | £41,000 must be paid |

Three outcomes follow from the same application.

1. **Both notices valid:** £41,000 is due on 24 April.
2. **Payment notice valid, pay less notice late** (say, on 20 April): the notified sum of £46,500 is due on 24 April. The £5,500 dispute goes to negotiation or adjudication.
3. **No payment notice:** if the contract lets the application count as the payee's notice, the notified sum is £48,000. A pay less notice can still reduce it, if it is given in time.

![The Construction Act payment timeline for one application under the Scheme defaults: application 31 March, payment due date 7 April, payment notice by 12 April, pay less notice by 17 April, final date for payment 24 April, with the notified sum falling from £48,000 applied for to £46,500 valued and £41,000 after the pay less notice.](./media/pay-less-notice-explained/diagram-1.png)

## What a pay less notice must contain

**Two things: the sum the payer considers due on the date the notice is served, and the basis on which it is calculated** (s111(4)). The sum may be zero.

- **The sum, not just the deduction.** "Less £5,500" is weaker than "£41,000 is due, being £46,500 less £5,500 for…".
- **The basis.** Show the calculation: what was valued, what is deducted and why, and which contract clause allows it.
- **The right sender.** The payer or a specified person named in the contract.
- **The right time.** No later than the prescribed period before the final date, and not before the notice that fixes the notified sum (s111(5)(b)).
- **The right way.** Served as the contract's notice clause requires: address, method, and whether email counts.

## What happens when a notice is missing or late

**The Act's default is that the notified sum gets paid.** Each failure has a defined result.

1. **No payment notice from the payer.** The payee may give its own notice of the sum due (s110B(2)). The final date moves back by the number of days that notice is late (s110B(3)). If the contract lets the payee's application serve as that notice, it already does (s110B(4)).
2. **No valid pay less notice.** The payer must pay the notified sum, to the extent not already paid, on or before the final date for payment (s111(1)).
3. **Notified sum not paid by the final date.** The payee may suspend performance after giving at least seven days' notice of intention to suspend, stating the grounds (s112(2)). It can recover a reasonable amount for costs and expenses caused by suspending (s112(3A)).
4. **A dispute over the amount.** Either party can refer it to adjudication. If an adjudicator decides more should be paid than a valid notice said, the extra is due within seven days of the decision, or by the original final date if later (s111(8)–(9)).

## Who and what the rules cover

**The payment rules apply to construction contracts, with some exclusions.** Check these before relying on the timeline above.

- **Residential occupiers are excluded.** Part II doesn't apply to a contract with someone for work on a dwelling they live in or intend to live in (s106).
- **Contract dates come first.** JCT and NEC contracts set their own periods. The Scheme defaults apply only where the contract is silent or fails the Act's requirements.
- **Which nation.** This guide follows the England and Wales Scheme. Scotland has its own Scheme for Construction Contracts, and Northern Ireland its own legislation. The 2011 amendments took effect on 1 October 2011 in England and Wales and 1 November 2011 in Scotland.
- **Change is coming.** The Commercial Payments Bill would make a pay less notice void if given later than seven days before the final date, with no freedom to agree a different period. Where it stands is covered in [the UK retention ban and a subcontractor's cash](/blog/retention-ban-uk-subcontractor-cash/).

## Checklists for both sides

**A specialist contractor receives notices from above and owes them below.** Run both lists every month.

**When you're paid (main contractor to you):**

1. Diary the due date, the payment notice deadline and the final date for every application.
2. Log each payment notice and pay less notice against the application it answers, with the date it arrived.
3. If no payment notice arrives in time, give your own notice of the sum due.
4. Compare what lands on the final date with the notified sum, not the amount applied for.

**When you pay (you to your subcontractors):**

1. Issue a payment notice within five days of each due date, every time, even for zero.
2. Decide on any deduction before the pay less deadline, and serve the notice with the calculation.
3. Pay the notified sum, less a valid pay less notice, by the final date. For CIS subcontractors, deduct CIS and issue the [payment and deduction statement](/blog/cis-payment-and-deduction-statement-xero/).

## Email and spreadsheets, Fynex, or the accounts package

**The notices are paperwork; the deadlines are a calendar; the payment is money. Most firms keep the three in different places.**

| Job | Email and a spreadsheet | Fynex | Sage or Xero alone |
|---|---|---|---|
| Notices received from the main contractor | In an inbox | Each payment notice and pay less notice logged against the application it answers | Not tracked |
| Deadlines | Calendar reminders | Construction Act dates tracked per application; late notices flagged the day they happen | Not tracked |
| Notices you owe subcontractors | Word templates | Payment notices and pay less notices issued from the same payment records | Not tracked |
| Paying subcontractors | Bank portal | Paid by Faster Payments, CIS deducted, statement issued | Bills, paid outside |
| What landed vs the notified sum | By hand | Each payment matched to the notice it settles | Bank feed matching |

## Where Fynex sits

**Fynex runs beside Sage, Xero or QuickBooks and your commercial team; it is not a ledger and not a solicitor.** On the money coming in, each application is matched to the payment notice and to what actually landed, and a pay less notice is flagged the day it arrives. On the money going out, Fynex issues payment notices and pay less notices to your subcontractors on time, pays them by [Faster Payments](/glossary/faster-payments/) with CIS deducted, and issues the payment and deduction statement. Retention owed to you and held from your subcontractors is tracked job by job. Every receipt and payment posts to the job in your books. Customer funds are held by Fondy Ltd (FCA FRN 900705). See [Fynex for construction](/construction/).

**When Fynex is the wrong choice:** if you work under one or two contracts at a time, notices arrive on time, and your quantity surveyor keeps the dates in hand, a spreadsheet does the job. Fynex earns its place when many applications, notices and subcontractor payments run on different cycles, and a missed date costs real money. It does not replace advice on a disputed notice: take that to a construction solicitor.

*This article summarises the statutory payment rules for England and Wales as published on legislation.gov.uk. It is not legal advice, and your contract may set different periods.*

## Sources

All read 2026-10-14 on legislation.gov.uk.

- Housing Grants, Construction and Regeneration Act 1996, Part II (sections 104–113): https://www.legislation.gov.uk/ukpga/1996/53/part/II
- Section 110 (dates for payment): https://www.legislation.gov.uk/ukpga/1996/53/section/110
- Section 110A (payment notices): https://www.legislation.gov.uk/ukpga/1996/53/section/110A
- Section 110B (payee's notice in default of payer's notice): https://www.legislation.gov.uk/ukpga/1996/53/section/110B
- Section 112 (right to suspend performance): https://www.legislation.gov.uk/ukpga/1996/53/section/112
- Section 106 (residential occupiers): https://www.legislation.gov.uk/ukpga/1996/53/section/106
- Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule Part II (payment): https://www.legislation.gov.uk/uksi/1998/649/schedule/part/II

**Related:** [Best CIS software for UK contractors](/blog/best-cis-software-uk/) · [CIS payment and deduction statements in Xero](/blog/cis-payment-and-deduction-statement-xero/) · [The UK retention ban and a subcontractor's cash](/blog/retention-ban-uk-subcontractor-cash/) · [Subcontractor payouts](/construction/subcontractor-payouts/)