Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page is an article from the Fynex blog: “The UK retention ban: what it changes for a subcontractor's cash”. Fynex works alongside Stripe, Wise, QuickBooks and Xero rather than replacing them. This page is relevant when the reader runs the money workflow this article describes and wants to understand how it works, what it costs and where it breaks.

# The UK retention ban: what it changes for a subcontractor's cash

*This article explains a Bill going through Parliament. It is not legal advice. Status checked on 13 October 2026.*

**Quick answer:** The UK Government is banning cash retentions in construction contracts, but the ban is not law yet. It sits in the Commercial Payments Bill [HL], which passed Lords report stage on 15 September 2026. Once in force, a two-year transition runs, then new retention clauses are void. Retention held under transition-era clauses is paid out after three years.

For a subcontractor, retention is cash earned and not paid. The Government's own impact assessment puts the average retention at around 5% of contract value, and the total held across UK construction in 2025 at £6.0 billion to £11.0 billion, with a central estimate of £8.4 billion. The ban moves that money back to the people who did the work. It also changes what a main contractor can withhold from you, and what you can withhold from your own subcontractors.

## Where the ban stands in October 2026

**The ban is a Government Bill in the House of Lords.** The Department for Business and Trade consulted on late payments from 31 July to 23 October 2025, including two options for retentions: a ban, or compulsory protection of retained sums. Its response on 24 March 2026 chose the ban.

| Date | Stage | Primary source |
|---|---|---|
| 31 Jul – 23 Oct 2025 | Late payments consultation, incl. retentions | GOV.UK consultation |
| 24 Mar 2026 | Government response: ban retentions, consult on timing | GOV.UK, *Time to pay up* |
| 19 May 2026 | Bill introduced in the Lords (HL Bill 4) | bills.parliament.uk |
| 9 Jun 2026 | Second reading, Lords | Hansard |
| 21 Jul 2026 | Committee stage finished (HL Bill 45) | bills.parliament.uk |
| 15 Sep 2026 | Report stage, Lords (HL Bill 55) | Hansard, bills.parliament.uk |
| 20 Oct 2026 | Third reading, Lords (scheduled) | bills.parliament.uk |
| Next | House of Commons, then Royal Assent | Pending |

The Bill's short title is the Commercial Payments Act 2026. It was announced in the King's Speech as the Small Business Protections Bill, so you will see both names. Clause numbers below follow HL Bill 55, the version as amended on report.

## What the Bill does to retentions

**It inserts new sections 113A to 113F into the Housing Grants, Construction and Regeneration Act 1996**, the Act that already governs payment notices and pay less notices. The retention clauses are 12 to 17 of the Bill.

- **What counts as retention (s113A).** Any practice of holding back a percentage of an interim payment, of the amount payable for work, or of the contract total, until a release condition is met. Conditions include finishing the contract or the end of a defects period.
- **The transition (s113B).** The ban runs in two steps from the day the section starts. Retention clauses agreed during the first two years still work for now. They become ineffective after the "last retention day", three years after the start.
- **Money still held at that point** must be paid out. The payment due date is 30 days after the last retention day. The final date for payment is 60 days after that, or 30 days if the payer is a public authority.
- **The ban (s113C).** A retention clause agreed after the two-year transition is void, along with any release mechanism tied to it.
- **No re-papering (s113D).** After the transition, parties may not vary an older retention clause, unless the change makes it more favourable to the payee.
- **A penalty for holding it anyway (s113E).** After the transition, if a sum due under section 111 is held back as retention instead of paid, the payee can recover a fixed sum: the higher of £40 or 50% of the "retention debt". Statutory interest and late-payment compensation are added on top.

The retention sections extend to England and Wales and Scotland. The Secretary of State can adjust the definitions by regulations, after consultation, with both Houses' approval.

## The timeline, if it starts on day one

No commencement date is set. The Bill leaves it to regulations, and GOV.UK says the Government "will consult further on the timing for implementation". So the timeline below is counted from whatever day the retention sections start.

| From the start date | What happens |
|---|---|
| Day one | Transition begins. New retention clauses still work, under s113B. |
| + 2 years | Transition ends. New retention clauses are void. Varying old ones is void unless it helps the payee. Fixed-sum penalty applies. |
| + 3 years | Last retention day. Transition-era clauses stop working. |
| + 3 years, 30 days | Payment due date for any transition-era retention still held. |
| + 3 years, 90 days | Final date for payment (private payer). |

Contracts signed before the transition keep their retention terms. The Government's overview says the measures "will not be applied retrospectively". A five-year framework signed before the start date can run its retention to the end.

## What else in the Bill moves your cash

Three other changes in the same Bill land on a subcontractor's bank balance.

1. **A 60-day ceiling on payment terms.** For construction payments, the final date for payment can be no later than 60 days after the payment due date, or 30 days for a public authority. The consultation response proposes "starting with 60 days, no earlier than 2027".
2. **Pay less notices with a hard deadline.** A pay less notice will be void if issued later than seven days before the final date for payment. The parties can no longer agree their own period. A late notice means the notified sum is due in full.
3. **Interest you don't have to argue for.** The Government's overview says the Bill mandates interest on late payments at 8% above the Bank of England base rate. Small businesses also get an adjudication scheme run by the Small Business Commissioner.

The seven-day rule matters more than it looks. A main contractor that issues a pay less notice two days before the final date for payment will no longer get to pay less.

## What the ban changes for a subcontractor's cash

**Take one application.** A specialist subcontractor applies for £186,000. The main contractor holds 5% retention, so £9,300 stays back and £176,700 is paid. Commonly half the retention comes back at practical completion and half at the end of the defects period, a year or more later.

| | Today | After the ban |
|---|---|---|
| Application | £186,000 | £186,000 |
| Retention held (5%) | £9,300 | £0 |
| Paid on the final date for payment | £176,700 | £186,000 |
| Still owed after completion | £9,300, split over two release dates | Nothing |
| If the main contractor goes insolvent | You are an unsecured creditor for £9,300 | No retention at risk |

<figure class="fx-chart">
<picture>
<source media="(max-width: 560px)" srcset="/charts/retention-ban-uk-subcontractor-cash/chart-retention-today-vs-ban-narrow.webp" width="420" height="461">
<img src="/charts/retention-ban-uk-subcontractor-cash/chart-retention-today-vs-ban.webp" width="800" height="440" alt="Stacked bars of an illustrative £186,000 application: today £176,700 is paid on the final date for payment and £9,300 is held as 5% retention; after the ban the full £186,000 is paid." loading="lazy" decoding="async">
</picture>
<figcaption><strong>A 5% retention holds back £9,300 of a £186,000 application.</strong> What a subcontractor is paid on the final date for payment today, and after the Commercial Payments Bill's retention ban takes effect. Illustrative worked example from the article, not market data. Source: <a href="https://bills.parliament.uk/bills/4128">UK Parliament, Commercial Payments Bill [HL]</a>.</figcaption>
<details><summary>Data behind the chart</summary><table><thead><tr><th scope="col">Scenario</th><th scope="col">Paid on the final date for payment</th><th scope="col">Retention held (5%)</th></tr></thead><tbody><tr><th scope="row">Today</th><td>£176,700</td><td>£9,300</td></tr><tr><th scope="row">After the ban</th><td>£186,000</td><td>£0</td></tr></tbody></table></details>
</figure>

Across a year of applications, that is 5% of turnover arriving on time instead of up to two years late. The Government's 2018 research, quoted in the impact assessment, found that 71% of contractors with retentions held had been paid them late. 44% had lost retention to an insolvency further up the chain, on average around £27,000 a year for an affected contractor, in 2016 prices.

Two effects run the other way:

- **You lose the retention you hold.** If you hold 5% from your own subcontractors, that cash buffer goes too. Plan the working capital for both sides.
- **Something replaces it.** Clients still want protection against defects. The impact assessment prices the ban mostly as the cost of insurance bonds, so expect retention bonds, performance bonds and tighter defect clauses in new contracts.

## What to do before it starts

The transition is years away from ending. The cash you are owed under today's contracts isn't. Four things are worth doing now:

1. **List every retention held against you,** per contract, with the amount, the percentage and both release dates.
2. **Diarise practical completion and the end of each defects period,** and apply for the release the day it falls due. Retention is lost most often by being forgotten.
3. **Check every pay less notice against the payment timetable** in your contract today. From commencement, a late one will be void.
4. **Read new contracts for retention substitutes:** bonds, extended defect periods, or a higher percentage dressed as something else.

The [US equivalent of retention is retainage](/construction/retainage/), which works the same way state by state.

## How Fynex tracks retention

**Fynex keeps retention visible, job by job.** Retention owed to you and retention you hold from your own subcontractors sit against each job, with practical completion and end-of-defects dates chased, not forgotten. Each application is matched to the payment notice and to what actually landed, and a pay less notice is flagged the day it arrives. When you pay subcontractors, Fynex deducts CIS, pays the net by Faster Payments and issues the payment and deduction statement. The job cost posts to Sage or Xero as it happens.

Fynex runs beside your accounts package and your commercial team. It doesn't replace a solicitor's reading of your contract. The construction overview is on [Fynex for construction](/construction/), and the payment side is in the [subcontractor payouts guide](/construction/subcontractor-payouts/).

## Sources

Primary sources, checked 13 October 2026.

- UK Parliament, [Commercial Payments Bill [HL]](https://bills.parliament.uk/bills/4128): stages and [HL Bill 55, as amended on report](https://bills.parliament.uk/publications/67832/documents/8809) (15 September 2026), clauses 12 to 17, 31 and 32
- Commercial Payments Bill [HL], [Explanatory Notes](https://publications.parliament.uk/pa/bills/lbill/59-02/004/en/5902004en01.htm) (19 May 2026)
- Hansard, [Lords second reading, 9 June 2026](https://hansard.parliament.uk/Lords/2026-06-09/debates/F2258E73-D3EC-4992-9513-E210C19149BF/CommercialPaymentsBill(HL)) and [Lords report stage, 15 September 2026](https://hansard.parliament.uk/Lords/2026-09-15/debates/28521FE1-B5A3-46D9-8B86-9C0D005E4826/CommercialPaymentsBill(HL))
- Department for Business and Trade, [Late payment consultation: time to pay up, Government response](https://www.gov.uk/government/consultations/late-payments-tackling-poor-payment-practices/outcome/late-payment-consultation-time-to-pay-up-government-response-web-version) (24 March 2026; [PDF](https://assets.publishing.service.gov.uk/media/69c2c7c413f1436476e443a2/late-payments-consultation-response.pdf))
- Department for Business and Trade, [Commercial Payments Bill: overview](https://www.gov.uk/government/publications/commercial-payments-bill-factsheets/commercial-payments-bill-overview) (19 May 2026)
- Department for Business and Trade, Commercial Payments Bill final stage impact assessment (28 May 2026), published with the Bill on bills.parliament.uk
- [Housing Grants, Construction and Regeneration Act 1996](https://www.legislation.gov.uk/ukpga/1996/53/contents), Part 2

**Related:** [Best CIS software for UK contractors](/blog/best-cis-software-uk/) · [CIS payment and deduction statements in Xero](/blog/cis-payment-and-deduction-statement-xero/) · [Late payment letters that work](/blog/late-payment-letters-that-work/) · [Net 30, but paid in 90](/blog/net-30-but-paid-in-90/)