title: "Schedule of values explained: how a subcontractor builds and bills one"
description: "What a schedule of values is, the columns of a G703-style continuation sheet, a worked electrical example, how it drives each pay app, and common mistakes."
url: "/blog/schedule-of-values-explained/"
date: "2026-11-11"
author: "Valeria Vahorovska"
tags: ["Guides","Invoicing","Accounting"]
---

Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page is an article from the Fynex blog: “Schedule of values explained: how a subcontractor builds and bills one”. Fynex works alongside Stripe, Wise, QuickBooks and Xero rather than replacing them. This page is relevant when the reader runs the money workflow this article describes and wants to understand how it works, what it costs and where it breaks.

# Schedule of values explained: how a subcontractor builds and bills one

**Quick answer:** A schedule of values (SOV) is your contract sum split into line items of work, each with a dollar value, adding up exactly to the contract. The customer approves it before the first pay app. Every pay app then bills the share of each line completed that period, less retainage. A clean SOV is the difference between pay apps approved first time and pay apps sent back.

For a specialty subcontractor, the SOV is the document every dollar of revenue passes through. It sets how much you can bill each month, how retainage is calculated, and how change orders are added. This guide covers what goes on one, the columns of the continuation sheet, a worked electrical example, and the mistakes that get pay apps rejected.

## What a schedule of values is

**The SOV is the agreed map from "percent complete" to "dollars billed".** Without it, every pay app is a negotiation.

- **Who prepares it.** The contractor doing the billing: the GC for the owner, the sub for the GC.
- **Who approves it.** The customer, or the architect on an owner-GC contract, before the first pay app.
- **What it must do.** Add up exactly to the contract sum, and break the work into lines the customer can verify in the field.
- **Whose form.** AIA's G703 continuation sheet "breaks the contract sum into portions of the work" according to a schedule of values the contractor prepares. AIA says it "does not publish a standard schedule of values form" ([AIA Contract Documents help](https://help.aiacontracts.com/hc/en-us/articles/1500009387861)). Use the layout your contract requires, or build your own.

AIA also publishes a contractor–subcontractor version of its payment application, G702S/G703S-2017 ([AIA Contract Documents help](https://help.aiacontracts.com/hc/en-us/articles/1500009322141-instructions-g702s-2017-application-and-certificate-for-payment-contractor-subcontractor-version)). Many GCs instead require their own portal format. The logic is the same.

## The columns of a continuation sheet

**Each SOV line runs across the same columns on every pay app.** The names vary by form and portal; the arithmetic doesn't.

| Column | What goes in it |
|---|---|
| Item no. and description | The line of work, as approved |
| Scheduled value | The line's dollar value; all lines sum to the contract |
| Work completed, from previous applications | What earlier pay apps billed on this line |
| Work completed, this period | What this pay app bills on this line |
| Materials presently stored | Materials bought and stored but not yet installed, if the contract allows billing them |
| Total completed and stored to date | Previous + this period + stored |
| % complete | Total to date ÷ scheduled value |
| Balance to finish | Scheduled value − total to date |
| Retainage | The held percentage of the total to date, if calculated per line |

The summary page then runs: contract sum, plus net change orders, total completed and stored to date, less retainage, less previous payments certified, equals the current payment due.

## A worked example: an electrical subcontractor

**A $480,000 electrical subcontract on a four-storey building, 10% retainage.** The SOV has eight lines.

| # | Line | Scheduled value |
|---|---|---|
| 1 | Mobilization and general conditions | $24,000 |
| 2 | Underground and slab conduit | $48,000 |
| 3 | Rough-in, levels 1–2 | $96,000 |
| 4 | Rough-in, levels 3–4 | $96,000 |
| 5 | Switchgear and panels | $72,000 |
| 6 | Lighting fixtures | $60,000 |
| 7 | Devices and trim | $48,000 |
| 8 | Testing, closeout and as-builts | $36,000 |
| | **Contract sum** | **$480,000** |

<figure class="fx-chart">
<picture>
<source media="(max-width: 560px)" srcset="/charts/schedule-of-values-explained/chart-sov-lines-narrow.webp" width="420" height="702">
<img src="/charts/schedule-of-values-explained/chart-sov-lines.webp" width="800" height="707" alt="Bar chart of an illustrative $480,000 electrical schedule of values: rough-in levels 1–2 and 3–4 at $96,000 each, switchgear $72,000, lighting $60,000, underground conduit $48,000, devices and trim $48,000, testing and closeout $36,000, mobilization $24,000." loading="lazy" decoding="async">
</picture>
<figcaption><strong>Rough-in is 40% of a $480,000 electrical SOV.</strong> The eight lines of one illustrative schedule of values for a four-storey electrical subcontract. Every pay app bills against these lines. Illustrative worked example from the article, not market data. Source: the article's worked schedule of values.</figcaption>
<details><summary>Data behind the chart</summary><table><thead><tr><th scope="col">Line</th><th scope="col">Scheduled value</th></tr></thead><tbody><tr><th scope="row">Rough-in, levels 1–2</th><td>$96,000</td></tr><tr><th scope="row">Rough-in, levels 3–4</th><td>$96,000</td></tr><tr><th scope="row">Switchgear and panels</th><td>$72,000</td></tr><tr><th scope="row">Lighting fixtures</th><td>$60,000</td></tr><tr><th scope="row">Underground and slab conduit</th><td>$48,000</td></tr><tr><th scope="row">Devices and trim</th><td>$48,000</td></tr><tr><th scope="row">Testing, closeout and as-builts</th><td>$36,000</td></tr><tr><th scope="row">Mobilization and general conditions</th><td>$24,000</td></tr></tbody></table></details>
</figure>

On pay app 3, line 3 reads: scheduled value $96,000, previous $38,400 (40%), this period $28,800 (30%), total to date $67,200 (70%), balance to finish $28,800, retainage $6,720.

Across the whole SOV, say total completed to date is $216,000 and the first two pay apps certified $144,000 of work. The summary works out as:

1. Total completed and stored to date: $216,000
2. Less 10% retainage: $21,600
3. Less previous payments certified ($144,000 less its retainage): $129,600
4. **Current payment due: $64,800**, which is this period's $72,000 of work less 10%.

![One schedule of values line through pay app 3: of a $96,000 scheduled value, $38,400 was billed on earlier pay apps, $28,800 is billed this period, and $28,800 is left to finish; 10% of the $67,200 completed to date, $6,720, is held as retainage.](./media/schedule-of-values-explained/diagram-1.png)

## How the SOV drives every pay app

**Once approved, the SOV fixes what you can bill; the only variable each month is percent complete.** Three things follow.

- **Billing is by line, not by invoice total.** The GC's project manager checks each line against the field. A line billed ahead of the work is the one cut.
- **Retainage follows the lines.** Retainage is calculated on total completed to date, per line or on the summary at a single rate. Track it from pay app 1; see [how to track retainage in QuickBooks Online](/blog/track-retainage-in-quickbooks-online/).
- **Change orders become new lines.** An approved change order is added with its own scheduled value and billed like any other line. The original lines stay as approved.
- **Waivers follow the pay app.** Each pay app goes out with a conditional progress waiver for the amount requested. See [conditional vs unconditional lien waivers](/blog/conditional-vs-unconditional-lien-waivers/).

## How to build an SOV that gets approved

**Make each line something the GC can see and measure on site.** Six habits that help.

1. **Build it from your estimate,** using the same cost codes, so billing and job costing line up.
2. **Split by area or floor** for long phases like rough-in. "Rough-in, levels 1–2" is verifiable; "Rough-in" alone is a guess.
3. **Give mobilization a fair value, not a fat one.** An inflated first line reads as front-loading.
4. **Fund closeout properly.** Testing, as-builts and O&M manuals take real time. A token line means you finish the job unpaid.
5. **Separate major equipment** like switchgear, so you can bill stored materials when the contract allows it.
6. **Match the GC's format early.** If the GC bills the owner on its own SOV, ask which of their lines your work rolls up into.

## Common SOV mistakes

**Most rejected pay apps trace back to the SOV, not the month's work.** Watch for these.

1. **Front-loading.** Early lines overvalued, late lines starved. It gets the SOV rejected, and later shows as overbilling on your [WIP report](/blog/wip-report-over-under-billing-for-subcontractors/).
2. **Lines that don't add up** to the contract sum after a change order.
3. **Editing an approved line** instead of adding a change-order line, so the history no longer matches.
4. **Stored materials billed without the paperwork** the contract asks for, such as invoices or proof of insurance.
5. **Percent complete that only goes up.** If a line was overbilled, the next pay app has to correct it, or the gap compounds.

## Schedule of values in QuickBooks Online

**QuickBooks Online can carry the SOV as an estimate and bill it with progress invoicing.** Intuit's August 2026 update adds AIA-style invoicing tied to project phases to QuickBooks Online Advanced ([Intuit](https://quickbooks.intuit.com/r/product-update/whats-new-quickbooks-advanced-august-2026/)). Its help page lists phases on Advanced with the QuickBooks Construction add-on and Intuit Enterprise Suite ([Intuit](https://quickbooks.intuit.com/learn-support/en-us/help-article/manage-projects/learn-project-phases/L5RLlXSSc_US_en_US)). On Plus, enter each SOV line as an estimate line and bill a percentage of each on progress invoices. Retainage is still a manual line in both.

## Spreadsheet, billing tool, or Fynex

**The SOV gets you to an approved pay app. What happens to the money after approval is a separate job.**

| Job | Spreadsheet | Fynex, beside your billing tool | Billing tool (Siteline, Textura, Procore) |
|---|---|---|---|
| Build the SOV | By hand | Reads the approved SOV and pay apps from your tools | Built in the tool |
| Produce the pay app | Template | Not a pay-app generator | G702/G703-style output or GC portal |
| Track what the GC actually paid | A column, if kept | Each pay app line matched to the payment, net of retainage; short pays flagged the day they land | Tracked in some tools |
| Retainage by job and GC | Formulas | Receivable and payable tracked, release dates chased | Receivable side |
| Into the books | Re-keyed | Posted to the job in QuickBooks or Sage | Via sync |

## Where Fynex sits

**Fynex runs beside your billing tool and your ledger; it does not build G702/G703 forms or submit to GC portals.** It tracks each pay app to what the GC actually paid, so a short pay or a held line shows up on the job the day the deposit lands. It tracks retainage receivable from each GC and retainage payable to each sub-tier, pays sub-tiers and suppliers by [ACH](/glossary/ach/), and posts everything to the job in QuickBooks or Sage. Customer funds are held by Fondy Ltd (FCA FRN 900705). See [Fynex for construction](/construction/).

**When Fynex is the wrong choice:** if your pay apps are paid in full and on time, and one person can tie each deposit to its pay app in minutes, a billing tool or spreadsheet is enough. Fynex earns its place when pay apps across many GCs come back short, late or net of retainage, and the cash has to be matched line by line. For billing tools compared, see [best construction billing software for subcontractors](/blog/best-construction-billing-software-for-subcontractors/).

## Sources

All checked 2026-10-14.

- AIA Contract Documents, G703–1992 Continuation Sheet: https://help.aiacontracts.com/hc/en-us/articles/1500009387861
- AIA Contract Documents, instructions for G702–1992: https://help.aiacontracts.com/hc/en-us/articles/1500009308242-instructions-g702-1992-application-and-certificate-for-payment
- AIA Contract Documents, instructions for G702S–2017 (contractor–subcontractor version): https://help.aiacontracts.com/hc/en-us/articles/1500009322141-instructions-g702s-2017-application-and-certificate-for-payment-contractor-subcontractor-version
- Intuit, What's new in QuickBooks Online Advanced, August 2026: https://quickbooks.intuit.com/r/product-update/whats-new-quickbooks-advanced-august-2026/
- Intuit, Learn about project phases: https://quickbooks.intuit.com/learn-support/en-us/help-article/manage-projects/learn-project-phases/L5RLlXSSc_US_en_US

AIA, G702 and G703 are trademarks of the American Institute of Architects. This article describes the general layout and does not reproduce AIA forms.

**Related:** [How to track retainage in QuickBooks Online](/blog/track-retainage-in-quickbooks-online/) · [Conditional vs unconditional lien waivers](/blog/conditional-vs-unconditional-lien-waivers/) · [Procore QuickBooks integration](/blog/procore-quickbooks-integration/) · [Job costing without enterprise software](/blog/job-costing-without-enterprise-software/) · [Retainage by state](/construction/retainage/)