Construction · State law

Construction prompt payment laws by state: deadlines and interest

A prompt payment act sets two clocks on a construction job: the days an owner (or public agency) has to pay the GC after a pay application, and the days the GC has to pay each sub after the GC is paid. Late payment carries statutory interest, usually stated per month (1% to 2%) or tied to the prime rate.

Private and public jobs run on different statutes in most states, and some states have no private prompt payment law at all. The table below gives each state's two clocks and its interest rate with the statute behind them. Each state page covers what happens when the GC says it hasn't been paid, what to do after the deadline, a worked example and a days-late and interest calculator.

Chart of the 50 US states grouped by private-job GC-to-sub deadline (prompt payment law). 7 days: 16 states (AL, AZ, CA, KS, LA, MD, ME, MT, NC, NM, NY, OR, SC, TX, VA, VT); 10 days: 8 states (GA, HI, MN, NE, NJ, NV, OH, OK); 14 days: 1 state (PA); 15 days: 4 states (DE, IL, KY, MS); 25 days: 1 state (CT); 30 days: 1 state (TN); 45 days: 1 state (MA); Statute sets no day count: 2 states (FL, MO); No private-job statute: 16 states (AK, AR, CO, IA, ID, IN, MI, ND, NH, RI, SD, UT, WA, WI, WV, WY).
16 states give a GC 7 days to pay its subs on private jobs; 16 have no private prompt-pay law. Days a general contractor has to pay a subcontractor after the GC is paid, under each state's private-job prompt payment law. Source: state statutes as cited on each state page, read 2026-10-14.
Data behind the chart
Private-job GC-to-sub deadlineStates
7 days16 statesAlabama, Arizona, California, Kansas, Louisiana, Maryland, Maine, Montana, North Carolina, New Mexico, New York, Oregon, South Carolina, Texas, Virginia, Vermont
10 days8 statesGeorgia, Hawaii, Minnesota, Nebraska, New Jersey, Nevada, Ohio, Oklahoma
14 days1 statePennsylvania
15 days4 statesDelaware, Illinois, Kentucky, Mississippi
25 days1 stateConnecticut
30 days1 stateTennessee
45 days1 stateMassachusetts
Statute sets no day count2 statesFlorida, Missouri
No private-job statute16 statesAlaska, Arkansas, Colorado, Iowa, Idaho, Indiana, Michigan, North Dakota, New Hampshire, Rhode Island, South Dakota, Utah, Washington, Wisconsin, West Virginia, Wyoming

Prompt payment deadlines and interest, state by state

StateOwner → GCGC → subInterestStatute
Alabama30 days7 days12% a yearAla. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7
AlaskaPublic only: 30 days8 days10.5% a yearAlaska Stat. §§36.90.200, 36.90.210, 36.90.230, 36.90.290; AS 45.45.010(a)
Arizona21 days7 days18% a yearA.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188
ArkansasPublic only: 90 daysPer contract10% a yearArk. Code §§22-9-205, 19-4-1411
California30 days7 days24% a yearCal. Civ. Code §8800 (owner to direct contractor); Cal. Bus. & Prof. Code §7108.5 (prime or sub to sub)
ColoradoPublic only: 45 days7 days15% a yearC.R.S. §24-91-103(1)(a), (2); §24-30-202(24)
Connecticut30 days25 days12% a yearConn. Gen. Stat. §§42-158i, 42-158j
Delaware30 days15 daysIndex-linked6 Del. C. §§3506, 3507, 3508, 3509, 2301(a)
FloridaPer contractPer contractIndex-linkedFla. Stat. §715.12
Georgia15 days10 days12% a yearO.C.G.A. §§13-11-2, 13-11-3, 13-11-4, 13-11-5, 13-11-7, 13-11-8, 13-11-10
HawaiiPer contract10 days18% a yearHaw. Rev. Stat. §444-25
IdahoPublic only: 60 daysPer contractSee state pageIdaho Code §67-2302(2), (7)-(9), (16), (18); §63-3045(6)(c)
Illinois40 days15 days10% a year815 ILCS 603/5, 603/10, 603/15
IndianaPublic only: 35 days10 days12% a yearInd. Code §§5-17-5-1 to 5-17-5-4; 4-13.6-7-4; 5-16-5.5-5
IowaPublic only: 14 days7 daysIndex-linkedIowa Code §§573.12(2)-(3), 573.14(2)
Kansas30 days7 days18% a yearK.S.A. 16-1803, 16-1805, 16-1806, 16-1807
Kentucky30 days15 days12% a yearKRS 371.405, 371.415, 371.425
Louisiana35 days7 days18% a yearLa. R.S. 9:2784 (as amended and reenacted by Acts 2026, No. 822, HB 638, eff. Aug. 1, 2026)
Maine20 days7 daysIndex-linked10 M.R.S. §§1111, 1112, 1113, 1114, 1115, 1118
Maryland7 days7 daysSee state pageMd. Code, Real Prop. §§9-301 to 9-305
Massachusetts45 days45 daysSee state pageM.G.L. c.149 §29E
MichiganPublic only: 30 daysPer contractSee state pageMich. Comp. Laws §§125.1561-125.1566 (Act 524 of 1980); §§17.52, 17.54 (Act 279 of 1984)
MinnesotaPer contract10 days18% a yearMinn. Stat. §337.10 subds. 3-4; §337.01 subd. 2
Mississippi60 days15 days12% a yearMiss. Code §§87-7-3, 87-7-5
MissouriPer contractPer contract18% a yearRSMo 431.180, 431.183
Montana28 days7 days18% a yearMCA 28-2-2101, 28-2-2102, 28-2-2103, 28-2-2104, 28-2-2105, 28-2-2107, 28-2-2115, 28-2-2116, 28-2-2117
Nebraska30 days10 days12% a yearNeb. Rev. Stat. 45-1202, 45-1203, 45-1204, 45-1205, 45-1207, 45-1209, 45-1211
Nevada21 days10 daysIndex-linkedNRS 624.609, 624.620, 624.622, 624.624, 624.626, 624.628, 624.630
New HampshireNo statute——N.H. RSA 447:15-18; RSA 21-I:20
New Jersey30 days10 daysIndex-linkedN.J.S.A. 2A:30A-1, 2A:30A-2
New Mexico21 days7 days18% a yearNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11
New York30 days7 days12% a yearN.Y. Gen. Bus. Law 756, 756-a, 756-b, 757
North CarolinaPer contract7 days12% a yearN.C. Gen. Stat. 22C-1 to 22C-6
North DakotaPublic only: 45 days45 days21% a yearN.D.C.C. 13-01.1-01, 13-01.1-02, 13-01.1-03, 13-01.1-05, 13-01.1-06, 48-01.2-13, 48-01.2-14
OhioPer contract10 days18% a yearOhio Rev. Code 4113.61, 4113.62
Oklahoma28 days10 daysSee state page15 O.S. 820, 821
Oregon14 days7 days18% a yearORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645
Pennsylvania20 days14 days12% a year73 P.S. §§501-516 (Contractor and Subcontractor Payment Act, 1994 Act 7, §§2-12)
Rhode IslandPublic only: 30 daysPer contractIndex-linkedR.I. Gen. Laws §§42-11.1-2, 42-11.1-5, 42-11.1-6; 37-13-5
South Carolina21 days7 days12% a yearS.C. Code §§29-6-10, 29-6-30, 29-6-40, 29-6-50, 29-6-60, 29-6-230
South DakotaPublic only: 45 days30 days10% a yearSDCL 5-26-1, 5-26-2, 5-26-3, 5-26-3.1, 5-26-5, 5-26-6; 5-18B-14; 54-3-16
Tennessee30 days30 days18% a yearTenn. Code Ann. §§66-34-201, 66-34-202, 66-34-203, 66-34-301 to 66-34-303, 66-34-601, 66-34-602
Texas35 days7 days18% a yearTex. Prop. Code §§28.002, 28.003, 28.004, 28.005, 28.006, 28.009
UtahPublic only: 60 days30 days15.5% a yearUtah Code §§15-6-2, 15-6-3, 15-6-4, 15-6-5, 15-6-6
Vermont20 days7 daysIndex-linked9 V.S.A. §§4001-4004, 4007, 4009
Virginia60 days7 daysIndex-linkedVa. Code §11-4.6(B)
WashingtonPublic only: 30 days10 days12% a yearRCW 39.76.011, 39.76.020, 39.76.040; RCW 39.04.250
West VirginiaPublic only: 60 daysPer contractIndex-linkedW. Va. Code §§7-5-7 (counties), 8-13-22d (municipalities), 11-10-17a, 12-10-1 to 12-10-3 (state agencies, Prompt Payment Act of 2025, 2025 HB 2152), 14-3-1 (state contracts 1969-1991)
WisconsinPublic only: 30 days7 days12% a yearWis. Stat. §§16.528(2), (2m) (state agencies); 66.0135(2), (3), (6) (local governmental units); 71.82(1)(a)
WyomingPublic only: 45 daysPer contract18% a yearWyo. Stat. §§16-6-601, 16-6-602, 16-6-116, 16-6-117

Key figures only; each state page has the full rule, private and public. Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.