Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Alabama prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Alabama prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Alabama's Timely Payments to Contractors and Subcontractors chapter sets two private clocks: the owner pays the GC within the contract's terms or 30 days after the pay request, and the GC pays each sub within 7 days after receiving the owner's payment (Ala. Code §8-29-3). Late payment bears 1% per month and the prevailing party in a collection suit recovers attorneys' fees (§8-29-6). A bona fide dispute lets the payor withhold up to twice the disputed amount, with written notice within 15 days (owner) or 5 days (GC and subs) (§8-29-4). Public agencies owe progress payments within 35 days of acceptance and interest at the tax-underpayment rate (§39-2-12).

## Prompt payment on private jobs

| Rule | Alabama law |
|---|---|
| Applies to | Contracts of $10,000 or more ([Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Residential work | Residential homebuilders and improvements for residential purposes of 16 or fewer units are exempt; contracts, subcontracts and sub-subcontracts of $10,000 or less are exempt; contracts with the state or local governments are exempt ([Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Owner pays the GC within | 30 days after receipt of the pay request or invoice, unless the contract specifies other payment terms (terms must be in all contract documents) ([Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| GC pays each sub within | 7 days after the contractor receives payment from the owner, unless the contractor and sub agreed other terms; a sub that bills in time for the GC to include it in its own pay request ([Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Flows down to sub-tiers | Yes ([Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Written notice to withhold | Within 15 days ([Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Withholding for a dispute | Up to 200% of the disputed amount ([Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Interest on late payment | 1% per month (12% per annum) on the unpaid balance; prevailing party recovers reasonable attorneys' fees, court costs and expenses ([Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Attorney's fees to the prevailing party | Yes ([Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |

## Prompt payment on public jobs

| Rule | Alabama law |
|---|---|
| Agency pays the prime within | 35 days ([Ala. Code §39-2-12(b), (i)](https://alison.legislature.state.al.us/code-of-alabama?section=39-2-12)) |
| Prime pays each sub within | Not set by statute |
| Interest on late payment | Interest at the rate assessed for underpayment of taxes under Ala. Code §40-1-44(a) on undisputed amounts unpaid after 35 days; payments to the contractor are due in 35 days after acceptance of the estimate (progress) or after final-payment paperwork is complete (final) ([Ala. Code §39-2-12(b), (i)](https://alison.legislature.state.al.us/code-of-alabama?section=39-2-12)) |

Alabama's private Timely Payments chapter (Ala. Code §8-29) expressly does not apply to contracts with the state or local governments (§8-29-7(4)), and §39-2-12 sets no prime-to-sub payment clock. A public-job sub is governed by its subcontract and by its payment-bond rights under Ala. Code §39-1-1.

## When the GC says it hasn't been paid in Alabama

Alabama's 7-day clock starts when the GC receives payment from the owner for the sub's work, so the statute is built on a pay-when-paid timing rule (Ala. Code §8-29-3(b), (e)). The chapter does not say that a pay-if-paid clause is void or enforceable. The sub can sue only the party it contracted with (§8-29-6), so the remedy against a GC that has not been paid sits in the subcontract, a lien, or a payment-bond claim, not in a direct claim against the owner. Whether a pay-if-paid clause is enforceable is a case-law question the statute text does not resolve.

## After the deadline: what a sub can do in Alabama

When an Alabama pay app or retainage is late, a sub (1) checks that the contract exceeds $10,000 and is not a 16-unit-or-smaller residential project; (2) confirms it billed early enough for the GC to include it in the GC's own pay request, the condition for the 7-day clock (§8-29-3(b)); (3) sends a written demand for the balance plus 1% per month interest (12% a year); (4) checks whether the GC gave written notice of a bona fide dispute within 5 days (§8-29-4(c)); (5) sues the party it contracted with, which carries attorneys' fees and costs for the winner (§8-29-6), and preserves its lien and bond rights on separate deadlines.

## Alabama quirks to know

Alabama is one of the few states where private retainage simply stops at 50% completion: the 10% (private) and 5% (public) caps apply to work done up to that point, so on a $480,000 contract the most that can ever be held is 10% of $240,000. The release clock is the earlier of 60 days after the contractor's work or 60 days after substantial completion, and the certificates of occupancy must be in hand. Payment may be conditioned on a full lien release for the amount paid (§8-29-3(n)). Interest cannot be waived before payment is due (§8-29-5). The chapter excludes residential homebuilders and public contracts, so public subs rely on §39-2-12 and bond claims under §39-1-1.

## Worked example: a $48,000 pay app paid late in Alabama

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 22, 2026 ([Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Paid | July 22, 2026 (30 days late) |
| Interest owed | $473.42 ([Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |

In Alabama, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. Paid 30 days after that, a $48,000 payment carries $473.42 of interest at 12% a year, simple.

## Alabama prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/alabama/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 7 days (after the contractor receives payment from the owner, unless the contractor and sub agreed other terms; a sub that bills in time for the GC to include it in its own pay request); interest: 1% per month (12% per annum) on the unpaid balance; prevailing party recovers reasonable attorneys' fees, court costs and expenses.
- **Private job: owner → GC:** 30 days (after receipt of the pay request or invoice, unless the contract specifies other payment terms (terms must be in all contract documents)); interest: 1% per month (12% per annum) on the unpaid balance; prevailing party recovers reasonable attorneys' fees, court costs and expenses.
- **Public job: prime → sub:** no statutory deadline; interest: Interest at the rate assessed for underpayment of taxes under Ala. Code §40-1-44(a) on undisputed amounts unpaid after 35 days; payments to the contractor are due in 35 days after acceptance of the estimate (progress) or after final-payment paperwork is complete (final).
- **Public job: agency → prime:** 35 days; interest: Interest at the rate assessed for underpayment of taxes under Ala. Code §40-1-44(a) on undisputed amounts unpaid after 35 days; payments to the contractor are due in 35 days after acceptance of the estimate (progress) or after final-payment paperwork is complete (final).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Alabama prompt payment law: questions

### How long does an Alabama GC have to pay a sub after getting paid?

Seven days after the GC receives the owner's payment, unless the subcontract sets other terms (Ala. Code §8-29-3(b), (e)). The sub must have billed in time for the GC to include the request in its own pay request.

### What interest can an Alabama subcontractor charge for late payment?

1% per month (12% per annum) on the unpaid balance, plus attorneys' fees, court costs and expenses if the sub wins (Ala. Code §§8-29-3(d), 8-29-6).

## Sources

- [Ala. Code §§8-29-1, 8-29-3, 8-29-4, 8-29-6, 8-29-7](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)
- [Ala. Code §39-2-12(b), (i)](https://alison.legislature.state.al.us/code-of-alabama?section=39-2-12)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Alabama retainage law](https://fynex.ai/construction/retainage/alabama/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- Alabama
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)