Arizona prompt payment law for construction: deadlines and interest
Under Arizona's Prompt Pay Act, a private owner's pay app is deemed certified and approved 14 days after receipt unless the owner issues a written statement of reasons, and then payment is due in 7 days, so 21 days in practice (A.R.S. §32-1182). The GC and each sub must pay the next tier within 7 days after receiving each progress payment, retention release or final payment (§32-1183(B)). Late payment bears 1.5% per month, and the successful party recovers attorney fees. A dispute lets the owner withhold only its reasonable direct costs, and 150% of cost at retention and final payment. Contracts can lengthen the clock only with a legend on every plan page.
Also in Arizona: retainage law
Arizona prompt payment calculator: days late and interest
Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from Arizona law; change them if your contract or the statute's trigger differs.
Clock starts: of receipt by the contractor or sub of each progress payment, retention release or final payment, when the sub has submitted a billing and a conditional lien waiver
Statute: 1.5% per month or fraction of a month on the unpaid balance, or a higher rate the parties agree; successful party recovers costs and reasonable attorney fees
- Payment due by
- June 22, 2026
- Days late
- 30
- Interest owed
- $710.14
- Total now owed
- $48,710.14
30 days late at 18% a year.
Statute: A.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188
Calendar days and simple interest (18% a year ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.
Prompt payment on private jobs
| Rule | Arizona law |
|---|---|
| Residential work | Section 32-1182 (owner payment rules) does not apply to a dwelling built for an owner-occupant unless the contractor puts the A.R.S. §32-1188 legend on the front page of each billing; construction contracts under 60 days need not use progress payments if the parties agreeA.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188 |
| Owner pays the GC within | 21 days billing is deemed certified and approved 14 days after the owner receives it (unless the owner issues a written statement of reasons), then payment is due within 7 days after certification and approval; the contract may extend these only with a clear legend on every page of the plansA.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188 |
| GC pays each sub within | 7 days of receipt by the contractor or sub of each progress payment, retention release or final payment, when the sub has submitted a billing and a conditional lien waiverA.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188 |
| Flows down to sub-tiers | YesA.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188 |
| Written notice to withhold | Within 14 daysA.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188 |
| Withholding for a dispute | Up to 150% of the disputed amountA.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188 |
| Interest on late payment | 1.5% per month or fraction of a month on the unpaid balance, or a higher rate the parties agree; successful party recovers costs and reasonable attorney feesA.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188 |
| Attorney's fees to the prevailing party | YesA.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188 |
Prompt payment on public jobs
| Rule | Arizona law |
|---|---|
| Agency pays the prime within | 21 daysA.R.S. §34-221(C)(2), (G), (J), (K), (N) |
| Prime pays each sub within | 7 days of receiving paymentA.R.S. §34-221(C)(2), (G), (J), (K), (N) |
| Interest on late payment | 1% per month or fraction of a month on a late payment to the contractor; a contractor or sub that pays a sub-tier more than 7 days after receipt owes 1% per month starting on the eighth day. Local-government timeline: an estimate is deemed approved 7 days after submission and payment is due within 14 days after it is certified and approved (21 days in total); attorney fees to the successful partyA.R.S. §34-221(C)(2), (G), (J), (K), (N) |
When the GC says it hasn't been paid in Arizona
Arizona says performance entitles a contractor, sub or supplier to payment from the party it contracts with (A.R.S. §32-1183(A)). The 7-day clock runs from the GC's receipt of payment, but if the owner declines to approve part of a billing for defective work, the GC must still pay each sub whose work was not the cause within 21 days after the owner's payment would have been due (§32-1183(G)). The GC must send the sub the owner's written refusal within 7 days (§32-1183(F)). A clause barring a sub from suspending performance or terminating after nonpayment is void (§32-1186(A)(2)); the subcontractor may stop work for nonpayment under §32-1185.
After the deadline: what a sub can do in Arizona
An Arizona sub whose pay app or retention is past the 7-day mark (1) confirms it sent a billing and a conditional lien waiver (required before the GC's duty arises); (2) checks whether the GC sent a written statement of reasons within 14 days (§32-1183(E)); (3) demands payment plus 1.5% per month, running from the eighth day; (4) may file a complaint with the Registrar of Contractors, which requires a surety bond or cash deposit of $500 or half the amount due, whichever is less (§32-1183(I)); (5) may suspend performance or terminate under §32-1185 after notice, and (6) sues or arbitrates, where the winner recovers fees under §32-1183(J). Lien and bond rights run on separate deadlines.
Arizona quirks to know
Arizona's prompt-pay act does not apply to the state or its political subdivisions (A.R.S. §32-1187); public jobs follow A.R.S. §34-221, which applies to counties, cities and towns, districts and similar local bodies (A.R.S. §34-101). Owner-occupant dwellings are carved out of the owner-pay rules unless the contractor puts a prescribed notice on the front page of each billing (§32-1188). Contract terms can extend the 14-day approval and 7-day payment periods, but only with a conspicuous 'Notice of Extended Payment Provision' legend on every page of the plans (§32-1182(B), (C), (F)). Public-works retention reverts to 10% if the owner finds progress unsatisfactory after 50% completion (§34-221(C)(3)). Forum clauses moving disputes out of state are void (§32-1186).
Worked example: a $48,000 pay app paid late in Arizona
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 22, 2026A.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188 |
| Paid | July 22, 2026 (30 days late) |
| Interest owed | $710.14A.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188 |
In Arizona, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. Paid 30 days after that, a $48,000 payment carries $710.14 of interest at 18% a year, simple.
Arizona prompt payment law: questions
How long does an Arizona GC have to pay a subcontractor?
Seven days after receiving each progress payment, retention release or final payment, provided the sub has submitted a billing and a conditional lien waiver (A.R.S. §32-1183(B)).
What interest applies to late payments in Arizona?
1.5% per month or fraction of a month on private jobs, or a higher agreed rate, plus attorney fees to the successful party (A.R.S. §§32-1182(Q), 32-1183(H), (J)). On local public works the rate is 1% per month (A.R.S. §34-221(J), (K)).
Sources
- A.R.S. §§32-1181, 32-1182, 32-1183, 32-1186, 32-1187, 32-1188
- A.R.S. §34-221(C)(2), (G), (J), (K), (N)
Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.