Construction · Prompt payment law

Arkansas prompt payment law for construction: deadlines and interest

Arkansas has no private prompt-payment statute. On public work, the state and local public authorities owe the prime interest of 10% per annum on a completion claim not paid within 90 days of presentation (Ark. Code §22-9-205), and state construction projects carry 5-working-day processing limits for the design professional, the agency and the Department of Finance and Administration, with an 8% per annum penalty on late requests (§19-4-1411). No Arkansas statute sets a clock for the prime or GC to pay a sub, so subcontract terms decide.

Also in Arkansas: retainage law

Arkansas prompt payment calculator: days late and interest

Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from Arkansas law; change them if your contract or the statute's trigger differs.

Which clock

Statute: Local and state agencies under §22-9-205: 10% per annum on a completion claim unpaid 90 days after presentation, counted for the period after day 90. State construction projects under §19-4-1411: each processing party has 5 working days (subsection (a)(1)(B) reworded by Act 910 of 2019 for the agency rename, 5 working days kept); a late party is assessed an 8% per annum penalty on the request amount

Payment due by
September 13, 2026
Days late
30
Interest owed
$394.52
Total now owed
$48,394.52

30 days late at 10% a year.

Statute: Ark. Code §§22-9-205, 19-4-1411

Calendar days and simple interest (10% a year ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Prompt payment on private jobs

No statute. No Arkansas statute on private-construction payment timing was found: the prompt-payment sections located (Ark. Code §§19-4-1411 and 22-9-205) apply only to state and public-agency contracts, and the subchapter's definition of 'public agency' covers state agencies, political subdivisions and entities spending public funds. On private jobs the contract sets the owner-to-GC and GC-to-sub deadlines and any late-payment interest. Absence was confirmed against the Title 22 subchapter listing and secondary summaries, not a full-text search of the Arkansas Code, which the official host would not serve.

Prompt payment on public jobs

RuleArkansas law
Agency pays the prime within90 daysArk. Code §§22-9-205, 19-4-1411
Prime pays each sub withinNot set by statute
Interest on late paymentLocal and state agencies under §22-9-205: 10% per annum on a completion claim unpaid 90 days after presentation, counted for the period after day 90. State construction projects under §19-4-1411: each processing party has 5 working days (subsection (a)(1)(B) reworded by Act 910 of 2019 for the agency rename, 5 working days kept); a late party is assessed an 8% per annum penalty on the request amountArk. Code §§22-9-205, 19-4-1411

No statute found that sets a prime-to-sub payment clock on public work. The subcontract controls; the only sub-tier public-work rule read is the retainage limit in §22-9-604(b).

When the GC says it hasn't been paid in Arkansas

Arkansas statutes do not regulate when a GC must pay its subs, so the subcontract and the pay-if-paid or pay-when-paid language in it decide. Secondary summaries say Arkansas courts enforce a pay-if-paid clause when it is clear and unambiguous, but this was not checked against case law here. A sub on a public job can sue on the payment bond, and on a private job its statutory tool is the mechanic's lien; neither is covered by the payment sections read.

After the deadline: what a sub can do in Arkansas

An Arkansas sub with unpaid money first reads its subcontract for the payment trigger, because the state sets none. On a public job a sub (1) confirms the agency has paid the prime (agencies have 5 working days per processing party on state projects, or 90 days on a completion claim); (2) checks the retainage deadline of 30 days after completion under §22-9-604(c) for the prime's own recovery; (3) demands payment and any contractual interest from the prime; and (4) preserves payment-bond and lien rights on separate deadlines not covered here.

Arkansas quirks to know

Arkansas is a minimal-statute state: only public-agency contracts carry retainage and payment-timing rules, and the parties cannot waive the retainage subchapter by agreement (Ark. Code §22-9-603). The retainage subchapter excludes State Highway Commission road and highway contracts (§22-9-602). 'Public agency' includes nonprofit corporations that receive public funds, so a grant-funded nonprofit's construction project can fall under the 5% rule. The subcontract-level 5% limit applies only to a sub the prime requires to furnish a performance and payment bond (§22-9-604(b)).

Worked example: a $48,000 pay app paid late in Arkansas

ClockPublic job: agency → prime
Clock startsJune 15, 2026
Payment due bySeptember 13, 2026Ark. Code §§22-9-205, 19-4-1411
PaidOctober 13, 2026 (30 days late)
Interest owed$394.52Ark. Code §§22-9-205, 19-4-1411

In Arkansas, a public agency has to pay the prime within 90 days: with the clock starting June 15, 2026, payment is due by September 13, 2026. Paid 30 days after that, a $48,000 payment carries $394.52 of interest at 10% a year, simple.

Run a payment like this in the split calculator

Arkansas prompt payment law: questions

What interest do Arkansas public agencies owe on late payment?

10% per annum on a completion claim unpaid 90 days after presentation (Ark. Code §22-9-205), and an 8% per annum penalty assessed on parties that exceed the 5-working-day processing limits on state projects (§19-4-1411(a)(3)).

How long does an Arkansas GC have to pay a subcontractor?

No statute sets a deadline in the sections read. The subcontract controls, and secondary sources say pay-if-paid clauses are enforceable in Arkansas when clearly stated.

Sources

Sources marked "mirror" were read from the linked copy on October 13, 2026 because the state's official code site did not load for us. Check the official code before relying on those figures.

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.