Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Connecticut prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Connecticut prompt payment law for construction: deadlines and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

On a private Connecticut job the owner must pay within 30 days of a written pay request, and the GC must pay each sub within 25 days after the GC receives payment (Conn. Gen. Stat. §42-158j(a)); each sub must flow the same 25-day term to its own subs. Interest is 1% per month, running from 10 days after the unpaid party sends a certified-mail notice, with a possible escrow of the claim and 10% damages for bad-faith withholding. A sub can also demand payment directly from the owner, up to what the owner still owes the GC. On public work, a GC pays its subs within 15 days after the State pays it on a State contract (§49-41c, cut from 30 days by P.A. 25-168 from October 1, 2025) and within 30 days on a municipal job (§49-41a), and state agencies pay within 45 days of a complete claim when the contract is silent (§4a-71).

## Prompt payment on private jobs

| Rule | Connecticut law |
|---|---|
| Applies to | Contracts of $25,000 or more ([Conn. Gen. Stat. §§42-158i, 42-158j](https://www.cga.ct.gov/current/pub/chap_742b.htm)) |
| Residential work | Contracts for residential buildings of four or fewer units are excluded; so are public contracts, HUD-funded or insured contracts, and subcontracts under owner-contractor contracts of $25,000 or less ([Conn. Gen. Stat. §§42-158i, 42-158j](https://www.cga.ct.gov/current/pub/chap_742b.htm)) |
| Owner pays the GC within | 30 days after a written request for payment is made to the owner by the contractor, subcontractor or supplier ([Conn. Gen. Stat. §§42-158i, 42-158j](https://www.cga.ct.gov/current/pub/chap_742b.htm)) |
| GC pays each sub within | 25 days after the contractor receives payment from the owner that includes the sub's labor or materials ([Conn. Gen. Stat. §§42-158i, 42-158j](https://www.cga.ct.gov/current/pub/chap_742b.htm)) |
| Flows down to sub-tiers | Yes ([Conn. Gen. Stat. §§42-158i, 42-158j](https://www.cga.ct.gov/current/pub/chap_742b.htm)) |
| Interest on late payment | 1% per month beginning on the date notice (registered or certified mail) is received, owed from 10 days after receipt; party may be required to escrow the claim plus interest; 10% damages for bad-faith withholding ([Conn. Gen. Stat. §§42-158i, 42-158j](https://www.cga.ct.gov/current/pub/chap_742b.htm)) |
| Attorney's fees to the prevailing party | Yes ([Conn. Gen. Stat. §§42-158i, 42-158j](https://www.cga.ct.gov/current/pub/chap_742b.htm)) |

## Prompt payment on public jobs

| Rule | Connecticut law |
|---|---|
| Agency pays the prime within | 45 days ([Conn. Gen. Stat. §§4a-71, 4a-72, 49-41a, 49-41c (as amended by P.A. 25-168, §214, eff. Oct. 1, 2025)](https://www.cga.ct.gov/current/pub/chap_058.htm)) |
| Prime pays each sub within | 30 days of receiving payment ([Conn. Gen. Stat. §§4a-71, 4a-72, 49-41a, 49-41c (as amended by P.A. 25-168, §214, eff. Oct. 1, 2025)](https://www.cga.ct.gov/current/pub/chap_058.htm)) |
| Interest on late payment | State agencies owe interest at the monthly effective yield of the Treasurer's Short Term Investment Fund when late (45 days from a complete claim if the contract names no date; highway work and federal-only funded work excluded). A GC or sub that pays late owes 1% per month starting 10 days after certified-mail notice. Prime-to-sub clock: 15 days after the State pays the prime on State contracts (§49-41c as amended by P.A. 25-168, §214, from 2025-10-01; was 30), 30 days after a municipality pays (§49-41a(a)(1)) ([Conn. Gen. Stat. §§4a-71, 4a-72, 49-41a, 49-41c (as amended by P.A. 25-168, §214, eff. Oct. 1, 2025)](https://www.cga.ct.gov/current/pub/chap_058.htm)) |

## When the GC says it hasn't been paid in Connecticut

Connecticut's private-job statute keys the GC's 25-day clock to the GC receiving owner payment, so a GC that has been paid cannot sit on the sub's share. If the owner has not paid the GC, a sub with an unpaid claim can send a registered or certified mail notice and, after serving demand on the owner (with a copy to the GC), sue the owner directly in superior court, limited to the amount the owner still owes the GC when notice is given (§42-158j(e)). The GC also cannot withhold from one sub because of a dispute with a different sub or supplier (§42-158j(d)). The statutes fetched here do not discuss pay-if-paid clauses; that is decided by the contract and case law.

## After the deadline: what a sub can do in Connecticut

A Connecticut sub whose payment is late (1) sends a notice of its claim by registered or certified mail to the party that owes it (owner, GC or higher-tier sub); (2) calculates 1% per month interest starting 10 days after that notice is received (§42-158j(c)(4)); (3) demands in writing that the debtor place the claim plus interest in an interest-bearing Connecticut escrow account; (4) for an unpaid owner-level obligation, serves a demand on the owner with a copy to the GC to trigger the direct right of action (§42-158j(e)); (5) on a public job with a payment bond, files the bond claim under §49-42. For unreleased retainage, an action under §42-158k or §42-158p can recover costs and attorney's fees (§42-158r).

## Connecticut quirks to know

Connecticut is one of the few states with mandatory private-job retainage escrow, but only for contracts over $25,000 and not for homes of four or fewer units (§42-158q). Interest does not accrue while a party has a good-faith contractual right to dispute the amount (annotation to §42-158j, 158 Conn. App. 27). Waiving lien or bond rights in advance is void (§42-158l). The payment requisition must include a statement of pending change orders (§42-158j(b)). Since October 1, 2025 (P.A. 25-168) a late payment to a sub on a State contract is also a discriminatory practice CHRO can enforce, and on public works of $1M or more the awarding agency holds 2% a month until CHRO compliance reports are approved, counted inside the §49-41b cap.

## Worked example: a $48,000 pay app paid late in Connecticut

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | July 10, 2026 ([Conn. Gen. Stat. §§42-158i, 42-158j](https://www.cga.ct.gov/current/pub/chap_742b.htm)) |
| Paid | August 9, 2026 (30 days late) |
| Interest owed | $473.42 ([Conn. Gen. Stat. §§42-158i, 42-158j](https://www.cga.ct.gov/current/pub/chap_742b.htm)) |

In Connecticut, a GC paid by the owner has to pay the sub within 25 days: with the clock starting June 15, 2026, payment is due by July 10, 2026. Paid 30 days after that, a $48,000 payment carries $473.42 of interest at 12% a year, simple.

## Connecticut prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/connecticut/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 25 days (after the contractor receives payment from the owner that includes the sub's labor or materials); interest: 1% per month beginning on the date notice (registered or certified mail) is received, owed from 10 days after receipt; party may be required to escrow the claim plus interest; 10% damages for bad-faith withholding.
- **Private job: owner → GC:** 30 days (after a written request for payment is made to the owner by the contractor, subcontractor or supplier); interest: 1% per month beginning on the date notice (registered or certified mail) is received, owed from 10 days after receipt; party may be required to escrow the claim plus interest; 10% damages for bad-faith withholding.
- **Public job: prime → sub:** 30 days (after the prime is paid); interest: State agencies owe interest at the monthly effective yield of the Treasurer's Short Term Investment Fund when late (45 days from a complete claim if the contract names no date; highway work and federal-only funded work excluded). A GC or sub that pays late owes 1% per month starting 10 days after certified-mail notice. Prime-to-sub clock: 15 days after the State pays the prime on State contracts (§49-41c as amended by P.A. 25-168, §214, from 2025-10-01; was 30), 30 days after a municipality pays (§49-41a(a)(1)).
- **Public job: agency → prime:** 45 days; interest: State agencies owe interest at the monthly effective yield of the Treasurer's Short Term Investment Fund when late (45 days from a complete claim if the contract names no date; highway work and federal-only funded work excluded). A GC or sub that pays late owes 1% per month starting 10 days after certified-mail notice. Prime-to-sub clock: 15 days after the State pays the prime on State contracts (§49-41c as amended by P.A. 25-168, §214, from 2025-10-01; was 30), 30 days after a municipality pays (§49-41a(a)(1)).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Connecticut prompt payment law: questions

### How many days does a Connecticut GC have to pay a subcontractor?

25 days after the GC receives payment from the owner that covers the sub's work (§42-158j(a)(2)). On public work it is 15 days after the State pays the GC on a State contract (§49-41c, as amended by P.A. 25-168 from October 1, 2025; previously 30) and 30 days after a municipality pays the GC (§49-41a(a)(1)).

### What interest does a Connecticut sub get on a late payment?

1% per month on the amount due, owed beginning 10 days after the debtor receives the sub's certified-mail notice, with a possible escrow demand and 10% damages if the withholding was in bad faith (§42-158j(c)(4)).

## Sources

- [Conn. Gen. Stat. §§42-158i, 42-158j](https://www.cga.ct.gov/current/pub/chap_742b.htm)
- [Conn. Gen. Stat. §§4a-71, 4a-72, 49-41a, 49-41c (as amended by P.A. 25-168, §214, eff. Oct. 1, 2025)](https://www.cga.ct.gov/current/pub/chap_058.htm)

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [Connecticut retainage law](https://fynex.ai/construction/retainage/connecticut/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- Connecticut
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)