Delaware prompt payment law for construction: deadlines and interest

On private Delaware jobs the owner pays within 30 days after the end of the billing period (or after invoice delivery, whichever is later, when the contract is silent), and a GC or sub pays the next tier within 15 days after receiving payment for that work when the contract has no term (6 Del. C. §§3506, 3507). Every contract must also include an interest-penalty clause at the legal rate, 5% over the Federal Reserve discount rate. A disputed invoice must be contested in writing within 7 days or it is deemed accepted (§3508). State public works run on a 7-day approval and 21-day payment cycle with sub-tier pay in 21 days (29 Del. C. §6516(f)).

Also in Delaware: retainage law

Delaware prompt payment calculator: days late and interest

Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from Delaware law; change them if your contract or the statute's trigger differs.

Which clock

Clock starts: after the GC or sub receives each payment for the sub's work, where no payment term is specified in the contract; contracts must also include a clause paying subs within 30 days out of amounts paid to the contractor

Statute: Interest penalty at the legal rate in effect when the obligation accrues (6 Del. C. §2301(a): 5% over the Federal Reserve discount rate, including surcharges); unpaid interest after each 30 days is added to principal; arbitrator or court awards the wrongfully withheld amount plus fees to the substantially prevailing party

Payment due by
June 30, 2026
Days late
30
Interest owed
—
Total now owed
$48,000.00

No fixed statutory rate: enter the rate from the statute or your contract.

Statute: 6 Del. C. §§3506, 3507, 3508, 3509, 2301(a)

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Prompt payment on private jobs

RuleDelaware law
Residential workSections 3507-3509 do not apply to contracts for the erection of 6 or fewer residential units under construction at the same time, to the alteration or repair of any single residential unit, to public works contracts under 29 Del. C. ch. 69, or to purchases of materials by a person building on its own real property6 Del. C. §§3506, 3507, 3508, 3509, 2301(a)
Owner pays the GC within30 days after the end of the billing period (the contract's cycle or the calendar month); where the contract has no payment term, the owner pays undisputed amounts within 30 days after the end of the billing period or 30 days after delivery of the invoice, whichever is later6 Del. C. §§3506, 3507, 3508, 3509, 2301(a)
GC pays each sub within15 days after the GC or sub receives each payment for the sub's work, where no payment term is specified in the contract; contracts must also include a clause paying subs within 30 days out of amounts paid to the contractor6 Del. C. §§3506, 3507, 3508, 3509, 2301(a)
Flows down to sub-tiersYes6 Del. C. §§3506, 3507, 3508, 3509, 2301(a)
Written notice to withholdWithin 7 days6 Del. C. §§3506, 3507, 3508, 3509, 2301(a)
Interest on late paymentInterest penalty at the legal rate in effect when the obligation accrues (6 Del. C. §2301(a): 5% over the Federal Reserve discount rate, including surcharges); unpaid interest after each 30 days is added to principal; arbitrator or court awards the wrongfully withheld amount plus fees to the substantially prevailing party6 Del. C. §§3506, 3507, 3508, 3509, 2301(a)
Attorney's fees to the prevailing partyYes6 Del. C. §§3506, 3507, 3508, 3509, 2301(a)

Prompt payment on public jobs

RuleDelaware law
Agency pays the prime within28 days29 Del. C. §6516(f)
Prime pays each sub within21 days of receiving payment29 Del. C. §6516(f)
Interest on late paymentInterest up to 2% above the Federal Reserve prime rate: on state progress payments delayed more than 21 days after approval (from day 22), on final payment delayed more than 60 days after final submission (from day 61), and on a sub-tier payment delayed more than 21 days after receipt (from day 22). Agency approves an estimate within 7 days of submission, then pays within 21 days after certification (28 days in total)29 Del. C. §6516(f)

When the GC says it hasn't been paid in Delaware

Delaware voids pay-if-paid on private jobs. A contract term stating that a contractor assumes the risk of the owner's nonpayment, or that makes a bond claimant's payment subject to owner payment, is against public policy and unenforceable (6 Del. C. §3507(e)(1), (3)). Money a contractor receives is held in trust and must first pay every person who furnished labor or material, and failure to pay within 30 days of receipt is prima facie evidence of misuse (§§3502-3504), a crime with a fine up to $1,000 or up to 3 years in prison (§3505). Section 3507 does not apply to Delaware public works, where §6516(f)(7) sets a 21-day sub-tier clock.

After the deadline: what a sub can do in Delaware

A Delaware sub with a late payment (1) checks its invoice was disputed or not within 7 days: an invoice with no written dispute in 7 days is deemed accepted (§3508(b)); (2) demands payment and the contract interest penalty at the legal rate; (3) pursues arbitration or suit under §3509, where the tribunal awards damages equal to the wrongfully withheld amount and fees to the substantially prevailing party (arbitration) or the court may award fees if the payment was withheld without good-faith reasonable cause (§3506(e)); (4) on a public job, claims interest from day 22 after the prime's receipt of payment (29 Del. C. §6516(f)(7)). Lien and bond rights run on separate deadlines.

Delaware quirks to know

Delaware's private prompt-pay chapter is also a construction trust-fund statute: money received by a contractor on a building job is a trust fund (6 Del. C. §3502). The payment sections exclude residential projects of 6 or fewer units under simultaneous construction and any single-unit alteration or repair. The 15-day GC-to-sub default applies only where no term is set, while §3506(b) requires a contract clause allowing up to 30 days; parties can opt out of §3508 dispute and §3509 fee rules by contract between GC and sub. Payment to a sub bars later claims against the GC and its surety by the sub's own suppliers (§3506(f)). State public works extend the sub-tier clock to 21 days.

Worked example: a $48,000 pay app paid late in Delaware

ClockPrivate job: GC → sub
Clock startsJune 15, 2026
Payment due byJune 30, 20266 Del. C. §§3506, 3507, 3508, 3509, 2301(a)
PaidJuly 30, 2026 (30 days late)
Interest owedNo fixed statutory rate

In Delaware, a GC paid by the owner has to pay the sub within 15 days: with the clock starting June 15, 2026, payment is due by June 30, 2026. The statutory rate moves with an index ("Interest penalty at the legal rate in effect when the obligation accrues (6 Del. C. §2301(a): 5% over the Federal Reserve discount rate, including surcharges); unpaid interest after each 30 days is added to principal; arbitrator or court awards the wrongfully withheld amount plus fees to the substantially prevailing party"), so enter the current figure in the calculator.

Run a payment like this in the split calculator

Delaware prompt payment law: questions

How many days does a Delaware GC have to pay a sub after getting paid?

15 days after receipt of each payment for the sub's work if the contract is silent (6 Del. C. §3507(d)); contracts must include a payment clause of no more than 30 days (§3506(b)(1)). On state public works the period is 21 days (29 Del. C. §6516(f)(7)).

Is a pay-if-paid clause enforceable in Delaware?

Not on private jobs covered by §3507: a provision stating that a contractor assumes the risk of the owner's nonpayment is void and unenforceable (§3507(e)(1)). The statute carves out public works under 29 Del. C. ch. 69, where it does not apply.

What interest applies to late payments in Delaware?

On private jobs, the legal rate at the time the obligation accrues, which is 5% over the Federal Reserve discount rate where there is no contract rate (6 Del. C. §§3506(c), 2301(a)). On state public works, up to 2% above the Federal Reserve prime rate (29 Del. C. §6516(f)(4), (7)).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.