Florida's private Construction Contract Prompt Payment Law (§715.12) does not fix a number of days; the contract does. What the statute adds is interest: any payment past due bears the §55.03 judgment rate plus 12% per annum starting on the 14th day after it is due. A GC or sub owes the next tier once it has itself been paid for that work, if the sub has sent a written pay request and the lien waivers the owner needs. On public jobs the clocks are fixed: the agency pays within 20 business days (25 if an agent must approve first, for local governments), the prime pays subs within 10 days of receipt, and a sub pays its tier within 7 days. Late public payments bear 2% per month.

Also in Florida: retainage law

Florida prompt payment calculator: days late and interest

Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from Florida law; change them if your contract or the statute's trigger differs.

Which clock

Clock starts: after the prime is paid

Statute: 2% per month on any payment not made within the statutory time limits (state agencies: s. 255.073(4); local governments: 2% per month or the contract rate, whichever is greater: s. 218.735(9)). Agency pay period is 20 business days for state work if the contract sets none earlier; local governments pay 20 business days after receipt (25 if an agent must first approve). Prime pays subs in 10 days, sub pays sub-tier in 7 days

Payment due by
June 25, 2026
Days late
30
Interest owed
$946.85
Total now owed
$48,946.85

30 days late at 24% a year.

Statute: Fla. Stat. §§255.073, 218.735, 218.755 (created by ch. 2025-140, HB 683), 215.422

Calendar days and simple interest (24% a year ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Prompt payment on private jobs

RuleFlorida law
Owner pays the GC withinNot set by statute
GC pays each sub withinNot set by statute
Flows down to sub-tiersYesFla. Stat. §715.12
Interest on late paymentStatutory judgment rate in s. 55.03 plus 12% per annum, starting on the 14th day after payment is due; or the contract rate if higherFla. Stat. §715.12
Attorney's fees to the prevailing partyNoFla. Stat. §715.12

Section 715.12 sets no fixed owner-to-GC or GC-to-sub payment period. The contract sets when payment is due; the statute adds the interest penalty, the 14-day cure window for rejected pay apps, and the pay-when-paid trigger for sub-tier obligors. The s. 55.03 rate is reset quarterly by the Chief Financial Officer and its current value was not read.

Prompt payment on public jobs

RuleFlorida law
Agency pays the prime within20 daysFla. Stat. §§255.073, 218.735, 218.755 (created by ch. 2025-140, HB 683), 215.422
Prime pays each sub within10 days of receiving paymentFla. Stat. §§255.073, 218.735, 218.755 (created by ch. 2025-140, HB 683), 215.422
Interest on late payment2% per month on any payment not made within the statutory time limits (state agencies: s. 255.073(4); local governments: 2% per month or the contract rate, whichever is greater: s. 218.735(9)). Agency pay period is 20 business days for state work if the contract sets none earlier; local governments pay 20 business days after receipt (25 if an agent must first approve). Prime pays subs in 10 days, sub pays sub-tier in 7 daysFla. Stat. §§255.073, 218.735, 218.755 (created by ch. 2025-140, HB 683), 215.422

When the GC says it hasn't been paid in Florida

Florida writes pay-when-paid into the statute for private jobs. A GC or sub is obliged to pay the next tier only once it has been paid by the person above it for the work in the sub's request (§715.12(4)(b)). The statute does not void a contract clause making payment conditional on the owner paying; it controls the timing and the interest once the money arrives. If the GC has been paid and still withholds, the 12% over the judgment rate starts to run on the 14th day after payment was due. An obligor cannot withhold payment for unrelated labor, services, or materials just because it disputes a different item (§715.12(6)(e)). On public jobs, §255.073(3) starts the sub's 10-day clock when the prime receives payment from the agency.

After the deadline: what a sub can do in Florida

For a private pay app that is late, a Florida sub (1) confirms its written request for payment and required waivers were delivered, because those are conditions in §715.12(4); (2) checks whether the GC returned the request within 14 days with written reasons (§715.12(5)(b)); if not, interest runs; (3) sends a written demand for the unpaid amount and statutory interest; (4) serves its notice to owner and records a claim of lien within the Chapter 713 deadlines, which are separate from this statute. §715.12 creates no separate cause of action except to collect the interest (§715.12(6)(b)) and no attorney's fee right. On a public job, send a written demand citing §255.073 or §218.735 and the 2% per month rate.

Florida quirks to know

Section 715.12 applies only to written contracts that carry construction lien rights under Chapter 713 Part I. The rate is the §55.03 judgment rate (reset quarterly by the CFO) plus 12%, not a fixed percentage, so interest calculators need a rate input. On public jobs the 5% cap does not apply to contracts of $200,000 or less, or to federally funded work with contrary federal requirements (§255.078(5)-(6)). Retainage cannot be held to secure insurance premiums under a wrap-up program, and warranty items cannot delay the final retainage release (§255.077(7)-(8)). Private retainage can be swapped for deposited Treasury securities, State of Florida bonds, or insured CDs (§715.12(7)(c)). On local-government contracts from July 1, 2025, a conforming change-order quote not approved or denied in writing within 35 days is deemed approved at the quoted price (§218.755).

Worked example: a $48,000 pay app paid late in Florida

ClockPublic job: prime → sub
Clock startsJune 15, 2026
Payment due byJune 25, 2026Fla. Stat. §§255.073, 218.735, 218.755 (created by ch. 2025-140, HB 683), 215.422
PaidJuly 25, 2026 (30 days late)
Interest owed$946.85Fla. Stat. §§255.073, 218.735, 218.755 (created by ch. 2025-140, HB 683), 215.422

In Florida, a prime paid by the agency has to pay the sub within 10 days: with the clock starting June 15, 2026, payment is due by June 25, 2026. Paid 30 days after that, a $48,000 payment carries $946.85 of interest at 24% a year, simple.

Run a payment like this in the split calculator

Florida prompt payment law: questions

What interest can a Florida subcontractor charge on late payment?

The s. 55.03 statutory judgment rate plus 12% per annum, or the contract rate if higher, starting on the 14th day after payment is due (Fla. Stat. §715.12(5)(a), (6)(a)).

How fast must a Florida GC pay a sub on a public project?

Within 10 days after the contractor receives payment from the public entity; a sub then has 7 days to pay its own subs and suppliers (Fla. Stat. §255.073(3); §218.735(6) for local governments). Late amounts bear 2% per month.

Sources

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.