Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Hawaii prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Hawaii prompt payment law for construction: deadlines and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

On private Hawaii jobs the only statutory clock is the GC-to-sub clock in HRS §444-25: 10 days after the sub's invoice and the GC's receipt of the owner's payment, whichever is later, with 1.5% per month interest unless a bona fide dispute delays payment. The owner-to-GC date is set by the contract. On public jobs, the State or a county pays within 30 calendar days of a proper statement, with interest at the WSJ prime rate plus 2%, and the prime must pay each sub within 10 days after receipt of the money (HRS §§103-10, 103-10.5).

## Prompt payment on private jobs

| Rule | Hawaii law |
|---|---|
| Owner pays the GC within | Not set by statute |
| GC pays each sub within | 10 days after the sub's invoice (with supporting documents the subcontract requires) is received AND the contractor has received payment from the owner for the sub's work, whichever occurs later ([Haw. Rev. Stat. §444-25](https://law.onecle.com/hawaii/title-25/444-25.html)) |
| Interest on late payment | 1.5% per month on the unpaid amount from the date payment is due; the section does not apply if the delay is due to a bona fide dispute between contractor and sub; if bids state that payment is contingent on funds in escrow or trust, interest starts only after the tenth day following the invoice and receipt of the escrow or trust funds ([Haw. Rev. Stat. §444-25](https://law.onecle.com/hawaii/title-25/444-25.html)) |
| Attorney's fees to the prevailing party | No ([Haw. Rev. Stat. §444-25](https://law.onecle.com/hawaii/title-25/444-25.html)) |

Hawaii has no statute fixing an owner-to-GC payment deadline on private jobs; the owner's date is whatever the prime contract says. Section 444-25 binds a licensed contractor's payment to its subcontractor only and says nothing on lower tiers or on attorney's fees.

## Prompt payment on public jobs

| Rule | Hawaii law |
|---|---|
| Agency pays the prime within | 30 days ([Haw. Rev. Stat. §§103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-10.html)) |
| Prime pays each sub within | 10 days of receiving payment ([Haw. Rev. Stat. §§103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-10.html)) |
| Interest on late payment | State agency or county pays within 30 calendar days of a proper statement or satisfactory delivery or performance, or owes interest at the Wall Street Journal prime rate for the quarter plus 2%; a prime or higher-tier party that fails to pay a sub within 10 days of receipt owes a penalty of 1.5% per month on the late amount ([Haw. Rev. Stat. §§103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-10.html)) |

## When the GC says it hasn't been paid in Hawaii

Hawaii's private-job statute starts the GC's 10 days at the later of the sub's invoice or the GC's receipt of the owner's payment, so a GC need not pay a sub before it is paid for that work (HRS §444-25). If the bid solicitation states that payment is contingent on funds held in escrow or trust, interest does not start until the tenth day after the sub's invoice and receipt of those funds. On public jobs a dispute between a contractor and a sub of any tier is not a dispute to which the State or a county is a party, and no right of action lies against them (HRS §103-32.1(b)). The statutes read do not address pay-if-paid clauses directly.

## After the deadline: what a sub can do in Hawaii

A Hawaii sub with a late payment on a private job (1) checks that it sent an invoice with the supporting documents the subcontract requires, and that the GC has been paid for the sub's work, which together start the 10-day clock; (2) confirms there is no bona fide dispute and no escrow-or-trust contingency stated in the bid solicitation; (3) demands payment plus interest at 1.5% per month from the due date; (4) pursues the claim under the subcontract, and its lien and bond rights on separate deadlines. On a public job, a sub whose retainage is not released within 10 days of the prime's receipt can invoke the 1.5% per month penalty under HRS §103-10.5 and the contractor-licensing referral for repeat violations.

## Hawaii quirks to know

Hawaii's public-work rule for subs: a bonded sub's retainage cannot exceed the prime's percentage (§103-32.1(d)); parties may still agree to retain up to 10% of each progress payment from a sub without incurring late-payment interest (§103-32.1(e)(1)). A prime that violates the 10-day retainage rule three or more times within two years is referred to the contractor license board (§103-10.5(c)). The official capitol.hawaii.gov site blocks automated access, so this record was built from a mirror dated 2016, checked against archived copies of the official §§103-10.5 and 444-25 pages (February 2025), which match. Two bills of the 2025-2026 Legislature did not become law: H.B. 274 (a 30-day invoice rule with compounding interest for private subs) and S.B. 1587 (a public retainage rewrite).

## Worked example: a $48,000 pay app paid late in Hawaii

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 25, 2026 ([Haw. Rev. Stat. §444-25](https://law.onecle.com/hawaii/title-25/444-25.html)) |
| Paid | July 25, 2026 (30 days late) |
| Interest owed | $710.14 ([Haw. Rev. Stat. §444-25](https://law.onecle.com/hawaii/title-25/444-25.html)) |

In Hawaii, a GC paid by the owner has to pay the sub within 10 days: with the clock starting June 15, 2026, payment is due by June 25, 2026. Paid 30 days after that, a $48,000 payment carries $710.14 of interest at 18% a year, simple.

## Hawaii prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/hawaii/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 10 days (after the sub's invoice (with supporting documents the subcontract requires) is received AND the contractor has received payment from the owner for the sub's work, whichever occurs later); interest: 1.5% per month on the unpaid amount from the date payment is due; the section does not apply if the delay is due to a bona fide dispute between contractor and sub; if bids state that payment is contingent on funds in escrow or trust, interest starts only after the tenth day following the invoice and receipt of the escrow or trust funds.
- **Private job: owner → GC:** no statutory deadline; interest: 1.5% per month on the unpaid amount from the date payment is due; the section does not apply if the delay is due to a bona fide dispute between contractor and sub; if bids state that payment is contingent on funds in escrow or trust, interest starts only after the tenth day following the invoice and receipt of the escrow or trust funds.
- **Public job: prime → sub:** 10 days (after the prime is paid); interest: State agency or county pays within 30 calendar days of a proper statement or satisfactory delivery or performance, or owes interest at the Wall Street Journal prime rate for the quarter plus 2%; a prime or higher-tier party that fails to pay a sub within 10 days of receipt owes a penalty of 1.5% per month on the late amount.
- **Public job: agency → prime:** 30 days; interest: State agency or county pays within 30 calendar days of a proper statement or satisfactory delivery or performance, or owes interest at the Wall Street Journal prime rate for the quarter plus 2%; a prime or higher-tier party that fails to pay a sub within 10 days of receipt owes a penalty of 1.5% per month on the late amount.

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Hawaii prompt payment law: questions

### How many days does a Hawaii GC have to pay a subcontractor on a private job?

10 days after receiving the sub's invoice (with required supporting documents) and the owner's payment for the sub's work, whichever is later, with interest at 1.5% per month on the unpaid amount (Haw. Rev. Stat. §444-25). A bona fide dispute suspends the interest.

### How long does a Hawaii agency or county have to pay a contractor?

30 calendar days after a proper statement or satisfactory delivery or performance, or interest accrues at the WSJ prime rate plus 2% (HRS §103-10(a)). Bona fide disputes and certain emergencies pause the clock.

## Sources

- [Haw. Rev. Stat. §444-25](https://law.onecle.com/hawaii/title-25/444-25.html) (mirror; the official site did not load)
- [Haw. Rev. Stat. §§103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-10.html) (mirror; the official site did not load)

Sources marked "mirror" were read from the linked copy on October 14, 2026 because the state's official code site did not load for us. Check the official code before relying on those figures.

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [Hawaii retainage law](https://fynex.ai/construction/retainage/hawaii/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- Hawaii
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)