Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Idaho prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Idaho prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Idaho has no private progress-payment deadline: the contract sets the owner's and GC's due dates, and the legal interest rate, absent a written rate, is 12% per year on money due (Idaho Code §28-22-104). For public jobs, the state and taxing districts must accept, certify and pay bills within 60 calendar days of receipt unless the contract in place says longer (Idaho Code §67-2302). Late payments bear interest at the tax-deficiency rate, compounded monthly, and a vendor who wins a collection action recovers attorney fees. No statute fixes a prime-to-sub clock on public work, except the 30-day retainage remittance.

## Prompt payment on private jobs

**No statute.** Idaho has no private-construction prompt-payment statute for progress payments. The contract sets when the owner pays the GC and the GC pays the sub, and interest runs at the contract rate or, with no written rate, the 12% per year legal rate on money due (Idaho Code §28-22-104). Idaho Code §29-115 regulates only private retainage (cap, release and sub pass-through). The Prompt Payment for Goods and Services statute (§67-2302) covers the state and taxing districts only.

## Prompt payment on public jobs

| Rule | Idaho law |
|---|---|
| Agency pays the prime within | 60 days ([Idaho Code §67-2302(2), (7)-(9), (16), (18); §63-3045(6)(c)](https://legislature.idaho.gov/statutesrules/idstat/Title67/T67CH23/SECT67-2302/)) |
| Prime pays each sub within | Not set by statute |
| Interest on late payment | Bills owed by the state or a taxing district are paid within 60 calendar days of receipt of billing unless the contract in place sets a longer period; interest at the Idaho tax-deficiency rate (2% plus the IRC §1274(d) midterm federal rate as of 15 September, rounded) compounds monthly; progress payments on construction are subject to interest when late, and on retained amounts interest accrues from 30 days after the contractor completes the work unless the contract says otherwise; prevailing vendor recovers reasonable attorney fees ([Idaho Code §67-2302(2), (7)-(9), (16), (18); §63-3045(6)(c)](https://legislature.idaho.gov/statutesrules/idstat/Title67/T67CH23/SECT67-2302/)) |

No Idaho statute sets a prime-to-sub payment clock on public jobs; the only sub-tier rule is the retainage remittance in §54-1926(3): the contractor remits retainage to the sub within 30 days after completion of the subcontract.

## When the GC says it hasn't been paid in Idaho

Idaho's statutes read do not regulate pay-if-paid or pay-when-paid clauses, so the subcontract controls how a GC's own non-payment affects the sub. The one statutory timing rule is retainage: once the GC receives retention from the owner it must pay each sub its share within 10 days, unless a bona fide dispute exists, and then it may withhold no more than 150% of the disputed amount (Idaho Code §29-115(4)-(5)). On a public job with a payment bond, a sub unpaid 90 days after its last labor or material can sue the bond, and a lower-tier claimant must give the GC written notice within 90 days (Idaho Code §54-1927).

## After the deadline: what a sub can do in Idaho

An Idaho sub with unpaid retention (1) checks that the contract is a private job over any bond-condition and that the owner's 35-day substantial-completion and final-completion clocks have run; (2) checks whether the GC has received the retention, because the 10-day pass-through starts then; (3) demands payment citing §29-115 and the 150% dispute cap; (4) preserves lien rights and, on a public job, bond-claim rights, whose notices and suits run on 90-day and one-year clocks (§54-1927); (5) sues; on a bond claim the prevailing party recovers attorney's fees under §54-1929, and a vendor to a taxing district recovers fees under §67-2302(18).

## Idaho quirks to know

The 5% private retainage cap does not apply to a one-to-four-unit owner-occupied residence, and does not apply to a GC or sub that fails to provide a requested performance bond. The statute voids any waiver of its terms as against public policy. Since 2025 (Sess. Laws ch. 34) every private construction contract and subcontract on an Idaho improvement is governed by Idaho law and may not require litigation or arbitration in another state (§29-115(6)). The 35-day clocks run from substantial completion 'as mutually agreed to by the parties' and final completion, not from a certificate of occupancy. On public work the 5% cap is tied to bonds above 50% of the contract, which every public contract of $50,000 or more must carry (85% bonds). Interest on public retainage accrues from 30 days after work is completed, unless the contract says otherwise.

## Worked example: a $48,000 pay app paid late in Idaho

| | |
|---|---|
| Clock | Public job: agency → prime |
| Clock starts | June 15, 2026 |
| Payment due by | August 14, 2026 ([Idaho Code §67-2302(2), (7)-(9), (16), (18); §63-3045(6)(c)](https://legislature.idaho.gov/statutesrules/idstat/Title67/T67CH23/SECT67-2302/)) |
| Paid | September 13, 2026 (30 days late) |
| Interest owed | No fixed statutory rate |

In Idaho, a public agency has to pay the prime within 60 days: with the clock starting June 15, 2026, payment is due by August 14, 2026. The statutory rate moves with an index ("Bills owed by the state or a taxing district are paid within 60 calendar days of receipt of billing unless the contract in place sets a longer period; interest at the Idaho tax-deficiency rate (2% plus the IRC §1274(d) midterm federal rate as of 15 September, rounded) compounds monthly; progress payments on construction are subject to interest when late, and on retained amounts interest accrues from 30 days after the contractor completes the work unless the contract says otherwise; prevailing vendor recovers reasonable attorney fees"), so enter the current figure in the calculator.

## Idaho prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/idaho/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** no statutory deadline; no fixed statutory interest rate.
- **Private job: owner → GC:** no statutory deadline; no fixed statutory interest rate.
- **Public job: prime → sub:** no statutory deadline; interest: Bills owed by the state or a taxing district are paid within 60 calendar days of receipt of billing unless the contract in place sets a longer period; interest at the Idaho tax-deficiency rate (2% plus the IRC §1274(d) midterm federal rate as of 15 September, rounded) compounds monthly; progress payments on construction are subject to interest when late, and on retained amounts interest accrues from 30 days after the contractor completes the work unless the contract says otherwise; prevailing vendor recovers reasonable attorney fees.
- **Public job: agency → prime:** 60 days; interest: Bills owed by the state or a taxing district are paid within 60 calendar days of receipt of billing unless the contract in place sets a longer period; interest at the Idaho tax-deficiency rate (2% plus the IRC §1274(d) midterm federal rate as of 15 September, rounded) compounds monthly; progress payments on construction are subject to interest when late, and on retained amounts interest accrues from 30 days after the contractor completes the work unless the contract says otherwise; prevailing vendor recovers reasonable attorney fees.

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Idaho prompt payment law: questions

### How fast must an Idaho public agency pay a contractor?

All bills owed by the state or a taxing district must be accepted, certified and paid within 60 calendar days of receipt unless the contract in place sets a longer period (Idaho Code §67-2302(2)). Interest at the tax-deficiency rate compounds monthly, and a prevailing vendor recovers attorney fees.

## Sources

- [Idaho Code §67-2302(2), (7)-(9), (16), (18); §63-3045(6)(c)](https://legislature.idaho.gov/statutesrules/idstat/Title67/T67CH23/SECT67-2302/) (mirror; the official site did not load)

Sources marked "mirror" were read from the linked copy on October 13, 2026 because the state's official code site did not load for us. Check the official code before relying on those figures.

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Idaho retainage law](https://fynex.ai/construction/retainage/idaho/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- Idaho
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)