Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Illinois prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Illinois prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

On a private Illinois job, the owner pays within 15 calendar days after approving a pay app, and the app is deemed approved 25 days after receipt unless the owner gives a written statement of what is withheld and why, so the clock runs 40 days in practice (815 ILCS 603/10). A GC or sub pays the next tier within 15 calendar days of receiving each payment or retainage. Late payment bears 10% per annum, and a sub not paid may suspend performance after 7 days' written notice (603/15). On public jobs, local governments approve in 30 days and pay in 30 more with 1% per month interest, state agencies pay in 90 days, and a contractor that holds sub-tier money more than 15 days owes 2% per month.

## Prompt payment on private jobs

| Rule | Illinois law |
|---|---|
| Residential work | Contracts for single-family residences or multiple-family residences with 12 or fewer units in a single building, and contracts that require the expenditure of public funds, are excluded ([815 ILCS 603/5, 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K10)) |
| Owner pays the GC within | 40 days owner pays not more than 15 calendar days after approving the payment application; the application is deemed approved 25 days after the owner receives it unless the owner gives a written statement of the amount withheld and reason before day 25 (25 + 15 = 40 days) ([815 ILCS 603/5, 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K10)) |
| GC pays each sub within | 15 days calendar days after the contractor's receipt from the owner (or the subcontractor's receipt from the contractor) of each periodic payment, final payment, or retainage monies, for work accepted by the owner, the owner's agent or the contractor ([815 ILCS 603/5, 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K10)) |
| Flows down to sub-tiers | Yes ([815 ILCS 603/5, 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K10)) |
| Written notice to withhold | Within 25 days ([815 ILCS 603/5, 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K10)) |
| Interest on late payment | 10% per annum on a late payment; a contractor or sub not paid as required may suspend performance without breach after 7 calendar days' written notice; interest is not duplicative of Mechanics Lien Act interest ([815 ILCS 603/5, 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K10)) |
| Attorney's fees to the prevailing party | No ([815 ILCS 603/5, 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K10)) |

## Prompt payment on public jobs

| Rule | Illinois law |
|---|---|
| Agency pays the prime within | 60 days ([50 ILCS 505/2, 505/3, 505/4, 505/9; 30 ILCS 540/3-2, 540/7](https://law.onecle.com/illinois/50ilcs505/index.html)) |
| Prime pays each sub within | 15 days of receiving payment ([50 ILCS 505/2, 505/3, 505/4, 505/9; 30 ILCS 540/3-2, 540/7](https://law.onecle.com/illinois/50ilcs505/index.html)) |
| Interest on late payment | Local governments: approve or disapprove a bill within 30 days after receipt, then pay within 30 days after approval (60 days in total); interest penalty of 1% per month or fraction after that (50 ILCS 505/3-4). State agencies: pay within 90 days of a proper bill (FY2012 and later), 1% per month after (30 ILCS 540/3-2); construction bill defects must be notified within 30 days. Contractors that fail to pay subs within 15 days of receipt owe 2% per month, throughout the contracting chain (50 ILCS 505/9; 30 ILCS 540/7) ([50 ILCS 505/2, 505/3, 505/4, 505/9; 30 ILCS 540/3-2, 540/7](https://law.onecle.com/illinois/50ilcs505/index.html)) |

## When the GC says it hasn't been paid in Illinois

Illinois' private-job clock starts when the GC receives payment from the owner: the GC must pay its sub within 15 calendar days of receipt of each periodic payment, final payment or retainage monies, for work the owner, the owner's agent or the GC has accepted (815 ILCS 603/10(2)). On public work, when the contractor receives less than the full payment, it must disburse the funds received pro rata among itself, subs and suppliers, and the sub-tier statute applies throughout the chain (50 ILCS 505/9; 30 ILCS 540/7). A State-contract sub with an unpaid claim can file a written notice with the State agency, which then convenes an administrative-law-judge hearing within 15 days. The Contractor Prompt Payment Act does not bar contract language conditioning a sub's pay on owner payment; that is a case-law question.

## After the deadline: what a sub can do in Illinois

An Illinois sub with a late payment (1) confirms its pay app or retainage request was submitted under the contract and is a 'payment application', and counts 25 days to deemed approval plus 15 days to pay; (2) sends written notice of the missed payment; after 7 calendar days' written notice the sub may suspend performance without breach (815 ILCS 603/15(b)); (3) demands 10% per annum interest from the due date; (4) on a public job, claims the 2% per month pass-through interest and, on State contracts, files a written notice with the State agency for an ALJ hearing (30 ILCS 540/7); (5) files a mechanic's lien or bond claim on separate deadlines.

## Illinois quirks to know

Illinois uses a deemed-approval device: silence by the owner for 25 days approves the pay app, and the 15-day payment clock starts on that approval. A sub's 15-day clock includes retainage monies. The private act excludes public-funds contracts and residential projects of 12 or fewer units in a single building. Public retainage limits apply where the Public Construction Bond Act requires a bond: work costing over $150,000 until January 1, 2029 (over $500,000 for IDOT and the Tollway), then over $50,000. From June 1, 2027 (P.A. 104-0168, HB 1224) the 10%/5% limit extends to the State except IDOT, and State agencies may retain on new contracts only for unsatisfactory progress, case by case, with sub retainage limited to what the agency held on that sub's work.

## Worked example: a $48,000 pay app paid late in Illinois

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 30, 2026 ([815 ILCS 603/5, 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K10)) |
| Paid | July 30, 2026 (30 days late) |
| Interest owed | $394.52 ([815 ILCS 603/5, 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K10)) |

In Illinois, a GC paid by the owner has to pay the sub within 15 days: with the clock starting June 15, 2026, payment is due by June 30, 2026. Paid 30 days after that, a $48,000 payment carries $394.52 of interest at 10% a year, simple.

## Illinois prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/illinois/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 15 days (calendar days after the contractor's receipt from the owner (or the subcontractor's receipt from the contractor) of each periodic payment, final payment, or retainage monies, for work accepted by the owner, the owner's agent or the contractor); interest: 10% per annum on a late payment; a contractor or sub not paid as required may suspend performance without breach after 7 calendar days' written notice; interest is not duplicative of Mechanics Lien Act interest.
- **Private job: owner → GC:** 40 days (owner pays not more than 15 calendar days after approving the payment application; the application is deemed approved 25 days after the owner receives it unless the owner gives a written statement of the amount withheld and reason before day 25 (25 + 15 = 40 days)); interest: 10% per annum on a late payment; a contractor or sub not paid as required may suspend performance without breach after 7 calendar days' written notice; interest is not duplicative of Mechanics Lien Act interest.
- **Public job: prime → sub:** 15 days (after the prime is paid); interest: Local governments: approve or disapprove a bill within 30 days after receipt, then pay within 30 days after approval (60 days in total); interest penalty of 1% per month or fraction after that (50 ILCS 505/3-4). State agencies: pay within 90 days of a proper bill (FY2012 and later), 1% per month after (30 ILCS 540/3-2); construction bill defects must be notified within 30 days. Contractors that fail to pay subs within 15 days of receipt owe 2% per month, throughout the contracting chain (50 ILCS 505/9; 30 ILCS 540/7).
- **Public job: agency → prime:** 60 days; interest: Local governments: approve or disapprove a bill within 30 days after receipt, then pay within 30 days after approval (60 days in total); interest penalty of 1% per month or fraction after that (50 ILCS 505/3-4). State agencies: pay within 90 days of a proper bill (FY2012 and later), 1% per month after (30 ILCS 540/3-2); construction bill defects must be notified within 30 days. Contractors that fail to pay subs within 15 days of receipt owe 2% per month, throughout the contracting chain (50 ILCS 505/9; 30 ILCS 540/7).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Illinois prompt payment law: questions

### How long does an Illinois owner have to pay a contractor?

Not more than 15 calendar days after approving the payment application, and the application is deemed approved 25 days after the owner receives it unless the owner gives a written statement of the amount withheld and the reason before day 25 (815 ILCS 603/10(1)).

### How long does an Illinois GC have to pay a subcontractor?

Within 15 calendar days after the GC receives each periodic payment, final payment or retainage monies, for work the owner, owner's agent or GC accepted (815 ILCS 603/10(2)). On public work the same 15-day period applies, with 2% per month interest for a late sub payment (50 ILCS 505/9; 30 ILCS 540/7).

### What interest applies to late payments on a private Illinois job?

10% per annum, and a contractor or sub who is not paid may suspend performance without penalty after 7 calendar days' written notice (815 ILCS 603/15).

## Sources

- [815 ILCS 603/5, 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K10) (mirror; the official site did not load)
- [50 ILCS 505/2, 505/3, 505/4, 505/9; 30 ILCS 540/3-2, 540/7](https://law.onecle.com/illinois/50ilcs505/index.html) (mirror; the official site did not load)

Sources marked "mirror" were read from the linked copy on October 13, 2026 because the state's official code site did not load for us. Check the official code before relying on those figures.

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Illinois retainage law](https://fynex.ai/construction/retainage/illinois/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- Illinois
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)