Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Indiana prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Indiana prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

There is no private prompt-payment act in Indiana. On public jobs, IC 5-17-5 makes every state agency and political subdivision pay a 1% per month late payment penalty when a payment is not made by the contract date, or within 35 days of receiving the goods or a properly completed claim if the contract names no date. A GC that is paid late must pay its sub 1% per month on the sub's share once it is paid. State GCs must pay subs within 10 days of receiving payment (IC 4-13.6-7-4).

## Prompt payment on private jobs

**No statute.** Indiana has no prompt-payment act for private construction. The 2026 Indiana Code Title 32 (Property, which holds the mechanic's lien chapter IC 32-28-3) contains no payment-deadline or interest rule between owner, GC and sub, so the contract's own payment terms and the lien deadlines govern. The only statutory interest on late construction pay is the public-works penalty in IC 5-17-5.

## Prompt payment on public jobs

| Rule | Indiana law |
|---|---|
| Agency pays the prime within | 35 days ([Ind. Code §§5-17-5-1 to 5-17-5-4; 4-13.6-7-4; 5-16-5.5-5](https://iga.in.gov/ic/2026/Title_5.pdf)) |
| Prime pays each sub within | 10 days of receiving payment ([Ind. Code §§5-17-5-1 to 5-17-5-4; 4-13.6-7-4; 5-16-5.5-5](https://iga.in.gov/ic/2026/Title_5.pdf)) |
| Interest on late payment | 1% per month late payment penalty on amounts due on written public works contracts; payment is timely if made on the contract date or, if none, within 35 days of receipt of goods/services or a properly completed claim (political subdivisions needing board approval: 35 days after the first regular meeting held at least 10 days after receipt); unpaid penalty compounds every 30 days (IC 5-17-5-1, 5-17-5-3). Good-faith disputes noticed before the due date are exempt (IC 5-17-5-2). A contractor paid late owes its sub 1% per month after it is paid (IC 5-17-5-4). State works: contractor pays subs within 10 days of receiving payment (IC 4-13.6-7-4; IC 5-16-5.5-5) ([Ind. Code §§5-17-5-1 to 5-17-5-4; 4-13.6-7-4; 5-16-5.5-5](https://iga.in.gov/ic/2026/Title_5.pdf)) |

## When the GC says it hasn't been paid in Indiana

On a private Indiana job, a pay-if-paid or pay-when-paid clause is a contract question: no Indiana prompt-pay statute in Title 32 overrides it, so read the clause and the sub's lien rights. On a public job the GC must pay a state sub within 10 days of receiving its payment, and the sub can file a verified claim with the division within 60 days after its last work (IC 4-13.6-7-10); local sub claims go to the board within 60 days (IC 36-1-12-12(b)).

## After the deadline: what a sub can do in Indiana

Private job: send written demand citing the contract, then protect the mechanic's lien deadlines under IC 32-28-3. State job: file the verified claim with the division and send the GC a copy within 60 days after your last labor, material or service; you may sue on the GC's payment bond 30 days after that filing (IC 4-13.6-7-10(c)). Local job: file the claim with the board within 60 days (IC 36-1-12-12) and sue the payment bond surety within the IC 36-1-12-13.1 windows.

## Indiana quirks to know

State Department of Administration retainage rules start at $1,000,000, but the director may apply them below that (IC 4-13.6-7-1). Local and state agency rules start above $200,000 and exclude highways, roads, streets, alleys and bridges. Escrow differs by owner: state agency retainage must be escrowed (IC 5-16-5.5-3), on local jobs the contractor chooses whether the board or an escrow agent holds it (IC 36-1-12-14(b)), and on Department of Administration jobs escrow is optional by agreement (IC 4-13.6-7-2(b)). A board need not pay interest on retainage it holds. HEA 1033 (P.L.28-2025, effective July 1, 2025) lowered local and state agency maximums from 10% and 5% to 6% and 3% and removed the old 6%/3% minimums.

## Worked example: a $48,000 pay app paid late in Indiana

| | |
|---|---|
| Clock | Public job: prime → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 25, 2026 ([Ind. Code §§5-17-5-1 to 5-17-5-4; 4-13.6-7-4; 5-16-5.5-5](https://iga.in.gov/ic/2026/Title_5.pdf)) |
| Paid | July 25, 2026 (30 days late) |
| Interest owed | $473.42 ([Ind. Code §§5-17-5-1 to 5-17-5-4; 4-13.6-7-4; 5-16-5.5-5](https://iga.in.gov/ic/2026/Title_5.pdf)) |

In Indiana, a prime paid by the agency has to pay the sub within 10 days: with the clock starting June 15, 2026, payment is due by June 25, 2026. Paid 30 days after that, a $48,000 payment carries $473.42 of interest at 12% a year, simple.

## Indiana prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/indiana/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** no statutory deadline; no fixed statutory interest rate.
- **Private job: owner → GC:** no statutory deadline; no fixed statutory interest rate.
- **Public job: prime → sub:** 10 days (after the prime is paid); interest: 1% per month late payment penalty on amounts due on written public works contracts; payment is timely if made on the contract date or, if none, within 35 days of receipt of goods/services or a properly completed claim (political subdivisions needing board approval: 35 days after the first regular meeting held at least 10 days after receipt); unpaid penalty compounds every 30 days (IC 5-17-5-1, 5-17-5-3). Good-faith disputes noticed before the due date are exempt (IC 5-17-5-2). A contractor paid late owes its sub 1% per month after it is paid (IC 5-17-5-4). State works: contractor pays subs within 10 days of receiving payment (IC 4-13.6-7-4; IC 5-16-5.5-5).
- **Public job: agency → prime:** 35 days; interest: 1% per month late payment penalty on amounts due on written public works contracts; payment is timely if made on the contract date or, if none, within 35 days of receipt of goods/services or a properly completed claim (political subdivisions needing board approval: 35 days after the first regular meeting held at least 10 days after receipt); unpaid penalty compounds every 30 days (IC 5-17-5-1, 5-17-5-3). Good-faith disputes noticed before the due date are exempt (IC 5-17-5-2). A contractor paid late owes its sub 1% per month after it is paid (IC 5-17-5-4). State works: contractor pays subs within 10 days of receiving payment (IC 4-13.6-7-4; IC 5-16-5.5-5).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Indiana prompt payment law: questions

### Does an Indiana public owner owe interest on late payment?

Yes: 1% per month on amounts due under written public contracts when payment is late, with 35 days from a properly completed claim as the default if the contract names no date (IC 5-17-5-1). Good-faith disputes noticed before the due date are exempt (IC 5-17-5-2).

### How fast must a GC pay a sub on an Indiana state job?

Within 10 days of receiving payment from the state or the escrow agent (IC 4-13.6-7-4(a)).

## Sources

- [Ind. Code §§5-17-5-1 to 5-17-5-4; 4-13.6-7-4; 5-16-5.5-5](https://iga.in.gov/ic/2026/Title_5.pdf)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Indiana retainage law](https://fynex.ai/construction/retainage/indiana/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- Indiana
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)