Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Iowa prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Iowa prompt payment law for construction: deadlines and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

Iowa's only construction prompt-payment rules are for public improvements. A progress payment approved by the architect or engineer that stays unpaid 14 days after the pay application is received (up to 30 days if the contract documents say so) earns the GC interest. A GC must then pay its sub within 7 days of receiving payment for that sub's work, or a reasonable time after it could have been paid if the delay is not the sub's fault (573.12(2)). Private owners and GCs have no statutory clock.

## Prompt payment on private jobs

**No statute.** Iowa has no prompt-payment act for private construction. Chapter 572 (mechanic's liens) in the Iowa Code 2026 (official PDF, re-read 2026-10-13: the words 'retain', 'retention' and 'prompt' do not appear) has no payment-deadline, retainage or interest rule between owner, GC and sub. The contract's payment terms govern, backed by lien rights under chapter 572. Iowa's prompt-pay rules in chapter 573 apply only to public improvements.

## Prompt payment on public jobs

| Rule | Iowa law |
|---|---|
| Agency pays the prime within | 14 days ([Iowa Code §§573.12(2)-(3), 573.14(2)](https://www.legis.iowa.gov/docs/code/573.12.pdf)) |
| Prime pays each sub within | 7 days of receiving payment ([Iowa Code §§573.12(2)-(3), 573.14(2)](https://www.legis.iowa.gov/docs/code/573.12.pdf)) |
| Interest on late payment | Progress payments: interest from the day after 14 days (up to 30 days if the contract documents say so) at the public-funds deposit rate under Iowa Code 12C.6 for a comparable period (573.14); final payment: interest if unpaid within 40 days (up to 50 if the contract says so) after completion and acceptance; universities under chapter 262: prime rate plus 1% per year ([Iowa Code §§573.12(2)-(3), 573.14(2)](https://www.legis.iowa.gov/docs/code/573.12.pdf)) |

## When the GC says it hasn't been paid in Iowa

On a public job, 573.12(2)(b)(1)(b) lets the GC pay a reasonable time after it could have received payment when the delay is not the sub's fault, so a sub whose own work is accepted is not left waiting on the GC's dispute with others. A GC that receives interest from the public corporation must pass the sub its proportional share (573.12(3)(a)). On a private job, no Iowa statute limits pay-if-paid language, so the contract controls.

## After the deadline: what a sub can do in Iowa

Public job: send written demand to the GC for the progress payment and a proportional share of any interest; if retainage is the issue, a sub can file a claim against the retained fund and bond under 573.15 and 573.16. Private job: demand in writing, then calendar the mechanic's lien and notice deadlines in chapter 572.

## Iowa quirks to know

Iowa cut its public retainage cap from 5% to 3% by 2025 Iowa Acts ch. 29 (S.F. 574), effective July 1, 2025, so older guides show 5%. The Act has no transition clause; statutes are presumed prospective (Iowa Code §4.5) and Master Builders of Iowa applies 3% to contracts signed after July 1, 2025, so earlier contracts are read as keeping 5%. From July 1, 2026 (S.F. 2365) the owner must send the prime, its surety and any claimant written notice of the final-acceptance date within 14 days, since that date starts the 30-day hold and the window to sue on the fund (573.16). A lower-tier claimant must give the prime written notice within 30 days of first furnishing (573.15; not highway, bridge or culvert work). Under 573.28 a contractor can request early release at substantial completion; the entity may hold 200% of unfinished work and must give written reasons within 30 days (not the State Board of Regents).

## Worked example: a $48,000 pay app paid late in Iowa

| | |
|---|---|
| Clock | Public job: prime → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 22, 2026 ([Iowa Code §§573.12(2)-(3), 573.14(2)](https://www.legis.iowa.gov/docs/code/573.12.pdf)) |
| Paid | July 22, 2026 (30 days late) |
| Interest owed | No fixed statutory rate |

In Iowa, a prime paid by the agency has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. The statutory rate moves with an index ("Progress payments: interest from the day after 14 days (up to 30 days if the contract documents say so) at the public-funds deposit rate under Iowa Code 12C.6 for a comparable period (573.14); final payment: interest if unpaid within 40 days (up to 50 if the contract says so) after completion and acceptance; universities under chapter 262: prime rate plus 1% per year"), so enter the current figure in the calculator.

## Iowa prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/iowa/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** no statutory deadline; no fixed statutory interest rate.
- **Private job: owner → GC:** no statutory deadline; no fixed statutory interest rate.
- **Public job: prime → sub:** 7 days (after the prime is paid); interest: Progress payments: interest from the day after 14 days (up to 30 days if the contract documents say so) at the public-funds deposit rate under Iowa Code 12C.6 for a comparable period (573.14); final payment: interest if unpaid within 40 days (up to 50 if the contract says so) after completion and acceptance; universities under chapter 262: prime rate plus 1% per year.
- **Public job: agency → prime:** 14 days; interest: Progress payments: interest from the day after 14 days (up to 30 days if the contract documents say so) at the public-funds deposit rate under Iowa Code 12C.6 for a comparable period (573.14); final payment: interest if unpaid within 40 days (up to 50 if the contract says so) after completion and acceptance; universities under chapter 262: prime rate plus 1% per year.

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Iowa prompt payment law: questions

### How fast must an Iowa GC pay a subcontractor?

On public improvements, within 7 days after the GC receives payment for that sub's work, or a reasonable time after it could have been paid if the delay is not the sub's fault (573.12(2)(b)).

## Sources

- [Iowa Code §§573.12(2)-(3), 573.14(2)](https://www.legis.iowa.gov/docs/code/573.12.pdf)

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [Iowa retainage law](https://fynex.ai/construction/retainage/iowa/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- Iowa
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)