Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Kentucky prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Kentucky prompt payment law for construction: deadlines and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

The owner (or public body) pays the GC within 30 business days of a timely, properly completed, undisputed pay application; postsecondary institutions and boards of education get 45 business days. The GC pays each sub within 15 business days of receiving that payment, and subs pay their subs on the same clock. Late amounts bear 12% per annum interest. The statute does not apply to residential construction.

## Prompt payment on private jobs

| Rule | Kentucky law |
|---|---|
| Residential work | Residential construction is excluded (KRS 371.425(1)); also excluded: Rural Utilities Service financed contracts and facilities under KRS Chapter 278 (utilities) ([KRS 371.405, 371.415, 371.425](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548)) |
| Owner pays the GC within | 30 days business days after the contracting entity receives a timely, properly completed, undisputed request for payment (retainage excepted); the contractor must send certified-mail notice on business day 25 if unpaid ([KRS 371.405, 371.415, 371.425](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548)) |
| GC pays each sub within | 15 days business days after the contractor receives payment from the contracting entity, including retainage if released, for a timely, properly completed, undisputed request from the sub; same rule for each tier ([KRS 371.405, 371.415, 371.425](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548)) |
| Flows down to sub-tiers | Yes ([KRS 371.405, 371.415, 371.425](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548)) |
| Interest on late payment | 12% per annum on the unpaid amount, from the 31st business day (owner) or the 16th business day after the contractor is paid (GC to sub) ([KRS 371.405, 371.415, 371.425](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548)) |
| Attorney's fees to the prevailing party | Yes ([KRS 371.405, 371.415, 371.425](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548)) |

## Prompt payment on public jobs

| Rule | Kentucky law |
|---|---|
| Agency pays the prime within | 30 days ([KRS 371.405, 371.425(1); 45.453, 45.454; 65.140; new KRS 45A section and KRS 45A.035 (2026 Ky. Acts ch. 147, HB 480, eff. July 15, 2026)](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548)) |
| Prime pays each sub within | 15 days of receiving payment ([KRS 371.405, 371.425(1); 45.453, 45.454; 65.140; new KRS 45A section and KRS 45A.035 (2026 Ky. Acts ch. 147, HB 480, eff. July 15, 2026)](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548)) |
| Interest on late payment | KRS 371.405 applies to public construction: 12% per annum after 30 business days (45 business days for postsecondary institutions and boards of education). Separately, state agencies owe a 1% per month penalty after 30 working days (KRS 45.453-45.454) and city/county/urban-county governments owe 1% per month after 30 working days (KRS 65.140). From 2026-07-15, 2026 Ky. Acts ch. 147 (HB 480) requires every state contract to state payment terms and sets 30 business days and a 1% per month penalty for undisputed amounts 'except as provided in KRS 371.405', so the construction rule above still controls ([KRS 371.405, 371.425(1); 45.453, 45.454; 65.140; new KRS 45A section and KRS 45A.035 (2026 Ky. Acts ch. 147, HB 480, eff. July 15, 2026)](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548)) |

## When the GC says it hasn't been paid in Kentucky

The sub-payment clock starts when the GC receives payment: 15 business days, including any retainage the owner releases (KRS 371.405(8)). Only undisputed amounts are covered, and a 'disputed amount' means a good-faith question about the validity of the request (KRS 371.400(5)). KRS 371.405(2)(b) voids contract terms waiving mechanic's lien rights under KRS Chapter 376, except partial progress-payment lien waivers. The act does not itself void pay-if-paid clauses.

## After the deadline: what a sub can do in Kentucky

On business day 25 after the pay application, if unpaid, the GC must notify the owner by certified mail with the date interest will start (KRS 371.405(6)); subs should follow the same practice. Send written demand for the amount plus 12% per annum. Attorney fees go to the prevailing party only if the loser acted in bad faith (KRS 371.415); venue is in Kentucky. Preserve mechanic's lien rights under KRS Chapter 376.

## Kentucky quirks to know

All periods in KRS 371.405 are business days; KRS 45.453 and 65.140 count working days. Retainage escrow ($2M+) is a private-contract rule only; waivers of it have been void since June 27, 2025 (2025 Ky. Acts ch. 15, ch. 156). The act excludes residential construction, RUS-financed borrower contracts and KRS Chapter 278 facilities. A 'substantial completion' certificate must come in writing from the contracting entity, and partial use or occupancy alone is not evidence of it (KRS 371.410(2)). Since 2025 (Ky. Acts ch. 15), KRS 367.620 to 367.628 control where they conflict with the Fairness in Construction Act (KRS 371.425(5)); those sections were not read.

## Worked example: a $48,000 pay app paid late in Kentucky

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 30, 2026 ([KRS 371.405, 371.415, 371.425](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548)) |
| Paid | July 30, 2026 (30 days late) |
| Interest owed | $473.42 ([KRS 371.405, 371.415, 371.425](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548)) |

In Kentucky, a GC paid by the owner has to pay the sub within 15 days: with the clock starting June 15, 2026, payment is due by June 30, 2026. Paid 30 days after that, a $48,000 payment carries $473.42 of interest at 12% a year, simple.

## Kentucky prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/kentucky/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 15 days (business days after the contractor receives payment from the contracting entity, including retainage if released, for a timely, properly completed, undisputed request from the sub; same rule for each tier); interest: 12% per annum on the unpaid amount, from the 31st business day (owner) or the 16th business day after the contractor is paid (GC to sub).
- **Private job: owner → GC:** 30 days (business days after the contracting entity receives a timely, properly completed, undisputed request for payment (retainage excepted); the contractor must send certified-mail notice on business day 25 if unpaid); interest: 12% per annum on the unpaid amount, from the 31st business day (owner) or the 16th business day after the contractor is paid (GC to sub).
- **Public job: prime → sub:** 15 days (after the prime is paid); interest: KRS 371.405 applies to public construction: 12% per annum after 30 business days (45 business days for postsecondary institutions and boards of education). Separately, state agencies owe a 1% per month penalty after 30 working days (KRS 45.453-45.454) and city/county/urban-county governments owe 1% per month after 30 working days (KRS 65.140). From 2026-07-15, 2026 Ky. Acts ch. 147 (HB 480) requires every state contract to state payment terms and sets 30 business days and a 1% per month penalty for undisputed amounts 'except as provided in KRS 371.405', so the construction rule above still controls.
- **Public job: agency → prime:** 30 days; interest: KRS 371.405 applies to public construction: 12% per annum after 30 business days (45 business days for postsecondary institutions and boards of education). Separately, state agencies owe a 1% per month penalty after 30 working days (KRS 45.453-45.454) and city/county/urban-county governments owe 1% per month after 30 working days (KRS 65.140). From 2026-07-15, 2026 Ky. Acts ch. 147 (HB 480) requires every state contract to state payment terms and sets 30 business days and a 1% per month penalty for undisputed amounts 'except as provided in KRS 371.405', so the construction rule above still controls.

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Kentucky prompt payment law: questions

### How long does a Kentucky GC have to pay a sub?

15 business days after the GC receives payment from the owner, including any released retainage (KRS 371.405(8)); interest is 12% per annum from the 16th business day (371.405(9)).

### Does Kentucky's prompt payment law cover public jobs?

Yes. KRS 371.425(1) applies the Fairness in Construction Act to public construction; state agencies also owe 1% per month after 30 working days (KRS 45.454) and cities, counties and urban-county governments the same under KRS 65.140.

## Sources

- [KRS 371.405, 371.415, 371.425](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548) (mirror; the official site did not load)
- [KRS 371.405, 371.425(1); 45.453, 45.454; 65.140; new KRS 45A section and KRS 45A.035 (2026 Ky. Acts ch. 147, HB 480, eff. July 15, 2026)](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=56548) (mirror; the official site did not load)

Sources marked "mirror" were read from the linked copy on October 14, 2026 because the state's official code site did not load for us. Check the official code before relying on those figures.

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [Kentucky retainage law](https://fynex.ai/construction/retainage/kentucky/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- Kentucky
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)