Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Louisiana prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Louisiana prompt payment law for construction: deadlines and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

On private work, the owner has 35 days from a written pay request to pay the GC, and the GC and every sub tier have 7 consecutive days from receiving payment to pay the next tier. Late amounts carry a 1.5% per month penalty from the day after due, plus court costs and reasonable attorney fees to the prevailing party (R.S. 9:2784, rewritten by Act 822 of 2026 from August 1, 2026; before that there was no owner clock, the GC had 14 days, and the penalty was 0.5% a day capped at 15%). Public entities owe 0.5% per day, capped at 15%, if they miss 45 days on a certified payment request (R.S. 38:2191).

## Prompt payment on private jobs

| Rule | Louisiana law |
|---|---|
| Residential work | Single-family residence contracts may set owner payment at up to 61 days after the owner receives the request; late amounts still carry the 1.5% per month penalty. Oil, gas, mineral, well/mine service and pipeline agreements are excluded entirely (R.S. 9:2784(E), (G)(3)). ([La. R.S. 9:2784 (as amended and reenacted by Acts 2026, No. 822, HB 638, eff. Aug. 1, 2026)](https://legis.la.gov/Legis/Law.aspx?d=107211)) |
| Owner pays the GC within | 35 days after the owner (or its agent) receives a written payment request for properly performed work or suitably stored or specially fabricated materials; if the owner has a construction loan, the later of 35 days or the fifth day after the owner receives the loan proceeds ([La. R.S. 9:2784 (as amended and reenacted by Acts 2026, No. 822, HB 638, eff. Aug. 1, 2026)](https://legis.la.gov/Legis/Law.aspx?d=107211)) |
| GC pays each sub within | 7 days consecutive days after the contractor receives payment from the owner; the same 7 days apply from each subcontractor to the next tier ([La. R.S. 9:2784 (as amended and reenacted by Acts 2026, No. 822, HB 638, eff. Aug. 1, 2026)](https://legis.la.gov/Legis/Law.aspx?d=107211)) |
| Flows down to sub-tiers | Yes ([La. R.S. 9:2784 (as amended and reenacted by Acts 2026, No. 822, HB 638, eff. Aug. 1, 2026)](https://legis.la.gov/Legis/Law.aspx?d=107211)) |
| Interest on late payment | 1.5% of the unpaid amount per month (penalty), starting the day after payment is due, stopping on payment, mailing if delivered in 3 days, or judgment ([La. R.S. 9:2784 (as amended and reenacted by Acts 2026, No. 822, HB 638, eff. Aug. 1, 2026)](https://legis.la.gov/Legis/Law.aspx?d=107211)) |
| Attorney's fees to the prevailing party | Yes ([La. R.S. 9:2784 (as amended and reenacted by Acts 2026, No. 822, HB 638, eff. Aug. 1, 2026)](https://legis.la.gov/Legis/Law.aspx?d=107211)) |

## Prompt payment on public jobs

| Rule | Louisiana law |
|---|---|
| Agency pays the prime within | 45 days ([La. R.S. 38:2191 (as amended by Acts 2026, No. 255, SB 235, eff. May 15, 2026)](https://legis.la.gov/Legis/Law.aspx?d=94906)) |
| Prime pays each sub within | Not set by statute |
| Interest on late payment | 0.5% per day accumulated, capped at 15%, plus reasonable attorney fees, if a progress or final payment is not made within 45 days of a certified payment request (or of a clear lien certificate for final payment); interest received by the contractor is shared pro rata with subcontractors within 10 business days. Since May 15, 2026 (Act 255) a public entity may not withhold liquidated damages the contractor contests from any payment due (except under R.S. 38:2248(C)); it must pay and sue for them separately, and a mandamus for late payment also compels fees and accrued interest ([La. R.S. 38:2191 (as amended by Acts 2026, No. 255, SB 235, eff. May 15, 2026)](https://legis.la.gov/Legis/Law.aspx?d=94906)) |

R.S. 38:2191 sets no number of days for the prime to pay its subs; it only requires the contractor to share interest within 10 business days. Whether the 7-day sub-payment rule in R.S. 9:2784(B) also reaches public contracts is not stated in either section (9:2784(G)(1) only says it does not supersede 38:2191).

## When the GC says it hasn't been paid in Louisiana

Under R.S. 9:2784(B), a GC must pay a sub the sub's share within 7 days after the GC itself is paid, including accrued interest. If the owner has not paid the GC, the 7-day clock has not started, but the GC must still pay any undisputed amount by the applicable date (R.S. 9:2784(C)) and a good-faith dispute only lets the GC withhold the disputed part. A waiver of any provision of the section is absolutely null (R.S. 9:2784(E)).

## After the deadline: what a sub can do in Louisiana

Private job: send written demand on day 8 after the GC was paid, claiming the 1.5% per month penalty, and sue under R.S. 9:2784(F) for the payment, penalty and attorney fees. Preserve the lien: file a statement of claim within 60 days after the notice of termination or substantial completion, or within 30 days / six months if a notice of contract was filed (R.S. 9:4822). Public job: if the entity withholds contested liquidated damages or sits on a payment, seek mandamus under R.S. 38:2191 (fees and interest included since Act 255 of 2026); serve notice and sue on the payment bond under R.S. 38:2242 and 38:2247 (written notice to the GC within 45 days of recorded acceptance for lower-tier claimants).

## Louisiana quirks to know

Act 822 of 2026 rewrote R.S. 9:2784 from August 1, 2026: a new 35-day owner clock, 7 days instead of 14 for each tier to pay the next, an uncapped 1.5% a month instead of 0.5% a day capped at 15%, waivers null, and the blanket residential exclusion dropped (single-family contracts may allow up to 61 days). The public side still runs 0.5% a day, capped at 15%. Since May 15, 2026 (Act 255) a public owner cannot withhold contested liquidated damages from progress or final payments. The 35-day private clock extends to the fifth day after loan proceeds arrive when the owner has a construction loan. The public retainage section does not apply to DOTD and cannot be waived (R.S. 38:2248(B)(3)). Louisiana's 'privilege' is its lien.

## Worked example: a $48,000 pay app paid late in Louisiana

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | August 15, 2026 |
| Payment due by | August 22, 2026 ([La. R.S. 9:2784 (as amended and reenacted by Acts 2026, No. 822, HB 638, eff. Aug. 1, 2026)](https://legis.la.gov/Legis/Law.aspx?d=107211)) |
| Paid | September 21, 2026 (30 days late) |
| Interest owed | $710.14 ([La. R.S. 9:2784 (as amended and reenacted by Acts 2026, No. 822, HB 638, eff. Aug. 1, 2026)](https://legis.la.gov/Legis/Law.aspx?d=107211)) |

In Louisiana, a GC paid by the owner has to pay the sub within 7 days: with the clock starting August 15, 2026, payment is due by August 22, 2026. Paid 30 days after that, a $48,000 payment carries $710.14 of interest at 18% a year, simple.

## Louisiana prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/louisiana/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 7 days (consecutive days after the contractor receives payment from the owner; the same 7 days apply from each subcontractor to the next tier); interest: 1.5% of the unpaid amount per month (penalty), starting the day after payment is due, stopping on payment, mailing if delivered in 3 days, or judgment.
- **Private job: owner → GC:** 35 days (after the owner (or its agent) receives a written payment request for properly performed work or suitably stored or specially fabricated materials; if the owner has a construction loan, the later of 35 days or the fifth day after the owner receives the loan proceeds); interest: 1.5% of the unpaid amount per month (penalty), starting the day after payment is due, stopping on payment, mailing if delivered in 3 days, or judgment.
- **Public job: prime → sub:** no statutory deadline; interest: 0.5% per day accumulated, capped at 15%, plus reasonable attorney fees, if a progress or final payment is not made within 45 days of a certified payment request (or of a clear lien certificate for final payment); interest received by the contractor is shared pro rata with subcontractors within 10 business days. Since May 15, 2026 (Act 255) a public entity may not withhold liquidated damages the contractor contests from any payment due (except under R.S. 38:2248(C)); it must pay and sue for them separately, and a mandamus for late payment also compels fees and accrued interest.
- **Public job: agency → prime:** 45 days; interest: 0.5% per day accumulated, capped at 15%, plus reasonable attorney fees, if a progress or final payment is not made within 45 days of a certified payment request (or of a clear lien certificate for final payment); interest received by the contractor is shared pro rata with subcontractors within 10 business days. Since May 15, 2026 (Act 255) a public entity may not withhold liquidated damages the contractor contests from any payment due (except under R.S. 38:2248(C)); it must pay and sue for them separately, and a mandamus for late payment also compels fees and accrued interest.

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Louisiana prompt payment law: questions

### How many days does a Louisiana GC have to pay a subcontractor after the owner pays?

Seven consecutive days after the GC receives payment from the owner (R.S. 9:2784(B)(1)); the same seven days apply from each subcontractor to its subs.

### What interest can I charge on late payment on a private Louisiana job?

A penalty of 1.5% of the unpaid amount per month, starting the day after payment was due, plus court costs and reasonable attorney fees if you win (R.S. 9:2784(D), (F)).

### How long does a Louisiana public entity have to pay a progress payment?

45 days after receiving a certified request for payment; after that it owes attorney fees and interest at 0.5% accumulated daily, not above 15% (R.S. 38:2191(B)(1)).

## Sources

- [La. R.S. 9:2784 (as amended and reenacted by Acts 2026, No. 822, HB 638, eff. Aug. 1, 2026)](https://legis.la.gov/Legis/Law.aspx?d=107211)
- [La. R.S. 38:2191 (as amended by Acts 2026, No. 255, SB 235, eff. May 15, 2026)](https://legis.la.gov/Legis/Law.aspx?d=94906)

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [Louisiana retainage law](https://fynex.ai/construction/retainage/louisiana/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- Louisiana
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)