Construction · Prompt payment law

Maine prompt payment law for construction: deadlines and interest

Maine's Construction Contracts chapter (10 M.R.S. 1111-1120) sets two clocks. The owner pays the GC 20 days after the end of the billing period or 20 days after the invoice is delivered, whichever is later, unless the parties agree otherwise. The GC pays each sub 7 days after receiving payment or 7 days after the sub's invoice, whichever is later. Interest runs at the post-judgment rate (one-year Treasury bill rate plus 6%), and a litigation or arbitration award adds a 1% per month penalty and attorney fees.

Also in Maine: retainage law

Maine prompt payment calculator: days late and interest

Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from Maine law; change them if your contract or the statute's trigger differs.

Which clock

Clock starts: after receipt of each progress or final payment, or after receipt of the sub's or supplier's invoice, whichever is later; the contractor must also disclose the owner's payment due date before the subcontract is signed

Statute: Interest at the post-judgment rate in 14 M.R.S. 1602-C (one-year US Treasury bill rate plus 6%), from the 21st day (owner) or the next day (GC to sub); plus a 1% per month penalty on wrongfully withheld sums awarded in arbitration or litigation

Payment due by
June 22, 2026
Days late
30
Interest owed
—
Total now owed
$48,000.00

No fixed statutory rate: enter the rate from the statute or your contract.

Statute: 10 M.R.S. §§1111, 1112, 1113, 1114, 1115, 1118

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Prompt payment on private jobs

RuleMaine law
Owner pays the GC within20 days after the end of the billing period or after delivery of the invoice, whichever is later (unless the parties agree otherwise)10 M.R.S. §§1111, 1112, 1113, 1114, 1115, 1118
GC pays each sub within7 days after receipt of each progress or final payment, or after receipt of the sub's or supplier's invoice, whichever is later; the contractor must also disclose the owner's payment due date before the subcontract is signed10 M.R.S. §§1111, 1112, 1113, 1114, 1115, 1118
Flows down to sub-tiersYes10 M.R.S. §§1111, 1112, 1113, 1114, 1115, 1118
Written notice to withholdWithin 10 days10 M.R.S. §§1111, 1112, 1113, 1114, 1115, 1118
Interest on late paymentInterest at the post-judgment rate in 14 M.R.S. 1602-C (one-year US Treasury bill rate plus 6%), from the 21st day (owner) or the next day (GC to sub); plus a 1% per month penalty on wrongfully withheld sums awarded in arbitration or litigation10 M.R.S. §§1111, 1112, 1113, 1114, 1115, 1118
Attorney's fees to the prevailing partyYes10 M.R.S. §§1111, 1112, 1113, 1114, 1115, 1118

Prompt payment on public jobs

RuleMaine law
Agency pays the prime within20 days10 M.R.S. §§1111(6), 1112, 1113, 1114, 1118
Prime pays each sub within7 days of receiving payment10 M.R.S. §§1111(6), 1112, 1113, 1114, 1118
Interest on late paymentSame chapter as private work: the State and its instrumentalities, municipalities, school districts and school administrative districts are 'owners' (10 M.R.S. 1111(6)); interest at the 14 M.R.S. 1602-C rate from the 21st day; 1% per month penalty on wrongfully withheld sums in arbitration or litigation. Maine DOT contracts are excluded (1112)10 M.R.S. §§1111(6), 1112, 1113, 1114, 1118

When the GC says it hasn't been paid in Maine

A Maine GC must tell each sub, before the subcontract is signed, the date it expects to receive payment from the owner; if it fails to disclose accurately, it owes the sub as if the owner's 20-day due date had been met (10 M.R.S. 1114(2)). Otherwise the sub is paid 7 days after the GC receives payment, notwithstanding any contrary agreement, so pay-when-paid timing is built into the statute. A GC may withhold an amount equal to the value of good-faith claims against the sub (1118(1)).

After the deadline: what a sub can do in Maine

Interest starts the day after the 7-day sub deadline (the 21st day for an owner). If arbitration or litigation is commenced and the payer is found non-compliant, the court or arbitrator must award a penalty of 1% per month on the sums wrongfully withheld, on top of damages, and the substantially prevailing party must be awarded reasonable attorney's fees and expenses (1118(2), (4)). Watch the 10 working-day invoice-error notice rule: errors not flagged in writing within 10 working days are deemed waived (1115).

Maine quirks to know

Interest uses the 14 M.R.S. 1602-C post-judgment rate: the one-year Treasury bill rate (weekly average, last full week of the prior calendar year) plus 6%. The chapter has no residential carve-out and no contract-size threshold; it applies to oral and written construction contracts and to material suppliers. Maine DOT contracts are excluded, and contracts using federal funds may vary where federal law requires (1119). A person performing work on their own real property is excluded (1120).

Worked example: a $48,000 pay app paid late in Maine

ClockPrivate job: GC → sub
Clock startsJune 15, 2026
Payment due byJune 22, 202610 M.R.S. §§1111, 1112, 1113, 1114, 1115, 1118
PaidJuly 22, 2026 (30 days late)
Interest owedNo fixed statutory rate

In Maine, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. The statutory rate moves with an index ("Interest at the post-judgment rate in 14 M.R.S. 1602-C (one-year US Treasury bill rate plus 6%), from the 21st day (owner) or the next day (GC to sub); plus a 1% per month penalty on wrongfully withheld sums awarded in arbitration or litigation"), so enter the current figure in the calculator.

Run a payment like this in the split calculator

Maine prompt payment law: questions

How many days does a Maine owner have to pay the GC?

20 days after the end of the billing period or 20 days after delivery of the invoice, whichever is later, unless the parties agreed otherwise; interest starts on the 21st day (10 M.R.S. 1113(3)-(4)).

What penalty can I recover for late payment in Maine?

In arbitration or litigation, the arbitrator or court must award 1% per month of the sums wrongfully withheld in addition to damages, plus attorney's fees to the substantially prevailing party (10 M.R.S. 1118(2), (4)).

Does Maine's prompt payment law cover public projects?

Yes, because 'owner' includes the State, municipalities and school districts; Maine DOT contracts are excluded (10 M.R.S. 1111(6), 1112).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.