Construction · Prompt payment law

Maryland prompt payment law for construction: deadlines and interest

Maryland's private prompt-pay subtitle gives a contractor undisputed amounts within 7 days after the contract's payment date, or, if the contract sets no dates, within the earlier of 30 days after the occupancy permit or after the owner takes possession. A GC or sub must pay its own subs undisputed amounts within 7 days after each payment it receives. There is no statutory interest rate; a court may award interest from the due date and, for bad faith, attorney's fees. On State contracts, payment is due within 30 days and 9% per annum interest runs from the 31st day, and the contractor must pay subs within 10 days.

Also in Maryland: retainage law

Maryland prompt payment calculator: days late and interest

Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from Maryland law; change them if your contract or the statute's trigger differs.

Which clock

Clock starts: days after the contractor or subcontractor receives each payment for its subcontractors' work or materials (undisputed amounts, retention included)

Statute: No statutory rate. A court may award the prevailing party interest from the date it determines the amount was due, plus costs, and reasonable attorney's fees if the payer acted in bad faith (Real Prop. 9-303)

Payment due by
June 22, 2026
Days late
30
Interest owed
—
Total now owed
$48,000.00

No fixed statutory rate: enter the rate from the statute or your contract.

Statute: Md. Code, Real Prop. §§9-301 to 9-305

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Prompt payment on private jobs

RuleMaryland law
Residential workExcludes contracts for construction and sale of a single-family dwelling, Custom Home Protection Act transactions, and home improvement contracts by contractors licensed under the Maryland Home Improvement Law (Real Prop. 9-305). The owner-to-contractor rule also does not apply to contracts with the State, a county, a municipal corporation, a board of education or a public authority (9-302(b)(2))Md. Code, Real Prop. §§9-301 to 9-305
Owner pays the GC within7 days after the payment date specified in the contract (undisputed amounts); if the contract specifies no dates, the earlier of 30 days after the occupancy permit is granted or 30 days after the owner takes possessionMd. Code, Real Prop. §§9-301 to 9-305
GC pays each sub within7 days days after the contractor or subcontractor receives each payment for its subcontractors' work or materials (undisputed amounts, retention included)Md. Code, Real Prop. §§9-301 to 9-305
Flows down to sub-tiersYesMd. Code, Real Prop. §§9-301 to 9-305
Interest on late paymentNo statutory rate. A court may award the prevailing party interest from the date it determines the amount was due, plus costs, and reasonable attorney's fees if the payer acted in bad faith (Real Prop. 9-303)Md. Code, Real Prop. §§9-301 to 9-305
Attorney's fees to the prevailing partyYesMd. Code, Real Prop. §§9-301 to 9-305

Prompt payment on public jobs

RuleMaryland law
Agency pays the prime within30 daysMd. Code, State Fin. & Proc. §§15-103, 15-104, 15-226
Prime pays each sub within10 days of receiving paymentMd. Code, State Fin. & Proc. §§15-103, 15-104, 15-226
Interest on late paymentState procurement: 9% per annum on amounts unpaid more than 37 days after the unit receives an invoice, accruing from the 31st day after the payment became due or the invoice was received, if later (SF&P 15-104); contractor must pay subs within 10 days of receiving State payment, and the unit can order a penalty up to $100 per day to the sub (SF&P 15-226)Md. Code, State Fin. & Proc. §§15-103, 15-104, 15-226

These are State procurement rules. The Real Property subtitle's owner-pay rule excludes counties, municipalities, boards of education and public authorities, and no separate statewide local-government construction prompt-pay statute was found in this pass.

When the GC says it hasn't been paid in Maryland

The sub-payment duty in Real Prop. 9-302(b)(3) is triggered by the GC receiving payment: 7 days after each payment received for the sub's work or materials. Disputed amounts are excluded, and 'undisputed amount' means one for which there is no good-faith dispute, including retainage withheld. Maryland's Construction Trust Fund (Real Prop. 9-201 to 9-202) also makes money paid to a contractor trust money for the subcontractors who did the work.

After the deadline: what a sub can do in Maryland

Private job: written demand for the undisputed amount, then sue; the court may order equitable relief, interest from the due date, costs and, if the payer acted in bad faith, attorney's fees (Real Prop. 9-303). State job: give written notice to the procurement officer, who contacts the contractor within 2 business days; if payment is not made, meetings follow and the unit may withhold further payments to the contractor and order a penalty up to $100 per day (SF&P 15-226).

Maryland quirks to know

The 5% private cap works only if the GC furnished 100% bonds or equivalent security, and is excluded for contracts under $100,000 and for projects funded by the Department of Housing and Community Development. Owners may still withhold extra amounts where performance gives reasonable grounds (9-304(d)). Single-family homes, custom homes and licensed home-improvement contracts are outside the subtitle. The 90-day release clock runs from substantial completion 'as defined by the applicable contract or subcontract'.

Worked example: a $48,000 pay app paid late in Maryland

ClockPrivate job: GC → sub
Clock startsJune 15, 2026
Payment due byJune 22, 2026Md. Code, Real Prop. §§9-301 to 9-305
PaidJuly 22, 2026 (30 days late)
Interest owedNo fixed statutory rate

In Maryland, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. The statutory rate moves with an index ("No statutory rate. A court may award the prevailing party interest from the date it determines the amount was due, plus costs, and reasonable attorney's fees if the payer acted in bad faith (Real Prop. 9-303)"), so enter the current figure in the calculator.

Run a payment like this in the split calculator

Maryland prompt payment law: questions

How fast must a Maryland GC pay a subcontractor?

Within 7 days after receiving each payment for the sub's work or materials, for undisputed amounts (Real Prop. 9-302(b)(3)). On State contracts the deadline is 10 days (SF&P 15-226(c)).

What interest can I charge for late payment in Maryland?

On private jobs the statute sets no rate; a court may award interest from the date due (Real Prop. 9-303(b)). State procurement carries 9% per annum from the 31st day (SF&P 15-104).

Does Maryland's prompt payment law apply to my home improvement job?

No. Single-family house construction and sale, Custom Home Protection Act deals and contracts by licensed home improvement contractors are excluded (Real Prop. 9-305).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.