Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Massachusetts prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Massachusetts prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

On private projects of $3,000,000 or more, c.149 §29E requires the contract to cap the pay cycle: 30 days to submit a pay application, 15 days for the owner to approve or reject it, and 45 days after approval to pay, with 7 more days of approval time per tier down the chain. An application not rejected in writing in time is deemed approved. The statute fixes no interest rate. Public building owners must pay within 15 days (30 for the Commonwealth) of a periodic estimate, with daily interest at 3 points above the Boston Fed rediscount rate.

## Prompt payment on private jobs

| Rule | Massachusetts law |
|---|---|
| Applies to | Contracts of $3M or more ([M.G.L. c.149 §29E](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXXI/Chapter149/Section29E)) |
| Residential work | Projects containing or designed to contain 1 to 4 dwelling units are excluded (c.149 §29E(a)) ([M.G.L. c.149 §29E](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXXI/Chapter149/Section29E)) |
| Owner pays the GC within | 45 days after approval of a progress payment application. The contract must set periods not exceeding: 30 days to submit (from the end of the first calendar month at least 14 days after work starts), 15 days to approve or reject (plus 7 days per tier below the owner), and 45 days after approval to pay; an application neither approved nor rejected in time is deemed approved ([M.G.L. c.149 §29E](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXXI/Chapter149/Section29E)) |
| GC pays each sub within | 45 days after approval of the sub's application; the same 45-day payment cap applies at every tier, with the approval window extended 7 days per tier. Unless the payment is subject to a pay-if-paid condition enforceable under §29E(e), which is void except for contractor non-performance and insolvency of the payer ([M.G.L. c.149 §29E](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXXI/Chapter149/Section29E)) |
| Flows down to sub-tiers | Yes ([M.G.L. c.149 §29E](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXXI/Chapter149/Section29E)) |
| Interest on late payment | §29E sets no interest rate or penalty; rejection must be in writing with the factual and contractual basis, certified as made in good faith ([M.G.L. c.149 §29E](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXXI/Chapter149/Section29E)) |

## Prompt payment on public jobs

| Rule | Massachusetts law |
|---|---|
| Agency pays the prime within | 15 days ([M.G.L. c.30 §§39K, 39G, 39F](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleIII/Chapter30/Section39K)) |
| Prime pays each sub within | Not set by statute |
| Interest on late payment | Daily interest at 3 percentage points above the Federal Reserve Bank of Boston rediscount rate from the first day after payment is due (c.30 §39K public buildings; §39G public works); on a final-payment estimate no interest is due until 15 days (24 for the Commonwealth) after receipt. Periodic payments: 15 days, 30 for the Commonwealth including local housing authorities. The contractor shares interest with subs pro rata. On contracts under c.149 §§44A-44L and c.30 §39M, the GC must pay each sub 'forthwith' after receiving payment for its work (no day count), the sub's balance is due by day 65 after its substantial completion, and a sub unpaid 70 days after its substantial completion may demand direct payment from the awarding authority, which pays within 15 days of the demand (c.30 §39F) ([M.G.L. c.30 §§39K, 39G, 39F](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleIII/Chapter30/Section39K)) |

No fixed day count for the prime to pay a sub: c.30 §39F(1)(a)-(b) says 'forthwith' after the GC receives payment. The 70-day figure is the trigger for a sub's direct-payment demand, not a payment deadline.

## When the GC says it hasn't been paid in Massachusetts

A pay-if-paid clause in a covered private contract is void and unenforceable except to the extent the money is missing because the sub failed to perform and did not cure after written notice, or because the payer became insolvent within 90 days of the requisition, and the sub must have filed a notice of contract and its lien statement and pursued reasonable legal remedies first (c.149 §29E(e)). No such clause is a defense to a c.254 lien claim. A sub also cannot be forced to keep working if an approved amount is more than 30 days past due (§29E(f)).

## After the deadline: what a sub can do in Massachusetts

Private job (covered): send written notice of the overdue approved amount; after 30 days unpaid you may stop work without breaching, subject to the dispute carve-outs in §29E(f). Protect your c.254 lien by filing a notice of contract and the statement of amount due within the lien deadlines. Public building job: demand the daily interest under §39K, and if the GC has not paid your balance within 70 days after your substantial completion, send a demand for direct payment to the awarding authority (c.30 §39F).

## Massachusetts quirks to know

Everything in the private statutes turns on a $3,000,000 prime-contract threshold and excludes 1 to 4 dwelling units. Retainage release under §29F is a paperwork process: substantial-completion notice, owner list, sub list, deliverables, then an application, and the amount withheld is capped at 150% of the cost to fix incomplete work plus deliverables up to 2.5% of the adjusted contract price plus good-faith claims. On contracts awarded under c.149 §§44A-44L and c.30 §39M, c.30 §39F binds the GC to pay each sub forthwith after receiving payment, makes the sub's balance due by day 65 after its substantial completion, and lets the sub demand direct payment from the awarding authority if it is unpaid after 70 days.

## Worked example: a $480,000 pay app paid late in Massachusetts

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | July 30, 2026 ([M.G.L. c.149 §29E](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXXI/Chapter149/Section29E)) |
| Paid | August 29, 2026 (30 days late) |
| Interest owed | No fixed statutory rate |

In Massachusetts, a GC paid by the owner has to pay the sub within 45 days: with the clock starting June 15, 2026, payment is due by July 30, 2026. The statutory rate moves with an index ("§29E sets no interest rate or penalty; rejection must be in writing with the factual and contractual basis, certified as made in good faith"), so enter the current figure in the calculator.

## Massachusetts prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/massachusetts/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 45 days (after approval of the sub's application; the same 45-day payment cap applies at every tier, with the approval window extended 7 days per tier. Unless the payment is subject to a pay-if-paid condition enforceable under §29E(e), which is void except for contractor non-performance and insolvency of the payer); interest: §29E sets no interest rate or penalty; rejection must be in writing with the factual and contractual basis, certified as made in good faith.
- **Private job: owner → GC:** 45 days (after approval of a progress payment application. The contract must set periods not exceeding: 30 days to submit (from the end of the first calendar month at least 14 days after work starts), 15 days to approve or reject (plus 7 days per tier below the owner), and 45 days after approval to pay; an application neither approved nor rejected in time is deemed approved); interest: §29E sets no interest rate or penalty; rejection must be in writing with the factual and contractual basis, certified as made in good faith.
- **Public job: prime → sub:** no statutory deadline; interest: Daily interest at 3 percentage points above the Federal Reserve Bank of Boston rediscount rate from the first day after payment is due (c.30 §39K public buildings; §39G public works); on a final-payment estimate no interest is due until 15 days (24 for the Commonwealth) after receipt. Periodic payments: 15 days, 30 for the Commonwealth including local housing authorities. The contractor shares interest with subs pro rata. On contracts under c.149 §§44A-44L and c.30 §39M, the GC must pay each sub 'forthwith' after receiving payment for its work (no day count), the sub's balance is due by day 65 after its substantial completion, and a sub unpaid 70 days after its substantial completion may demand direct payment from the awarding authority, which pays within 15 days of the demand (c.30 §39F).
- **Public job: agency → prime:** 15 days; interest: Daily interest at 3 percentage points above the Federal Reserve Bank of Boston rediscount rate from the first day after payment is due (c.30 §39K public buildings; §39G public works); on a final-payment estimate no interest is due until 15 days (24 for the Commonwealth) after receipt. Periodic payments: 15 days, 30 for the Commonwealth including local housing authorities. The contractor shares interest with subs pro rata. On contracts under c.149 §§44A-44L and c.30 §39M, the GC must pay each sub 'forthwith' after receiving payment for its work (no day count), the sub's balance is due by day 65 after its substantial completion, and a sub unpaid 70 days after its substantial completion may demand direct payment from the awarding authority, which pays within 15 days of the demand (c.30 §39F).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Massachusetts prompt payment law: questions

### Is pay-if-paid enforceable in Massachusetts?

Only narrowly on covered private projects: the clause is void except for the sub's own uncured non-performance or the payer's insolvency within 90 days of the requisition, with lien and remedy prerequisites (c.149 §29E(e)).

### How fast must a Massachusetts public building owner pay?

Within 15 days (30 days for the Commonwealth and local housing authorities) of a periodic estimate, with daily interest at 3 points above the Boston Fed rediscount rate after that (c.30 §39K).

### How fast must a Massachusetts GC pay a sub on a public building job?

'Forthwith' after the GC receives payment for that sub's work; no day count is set. The sub's full balance is due by the 65th day after it substantially completes its work, and if it is still unpaid on day 70 the sub may demand direct payment from the awarding authority by sworn statement; the authority pays within 15 days of the demand, less disputed amounts it deposits in a joint interest-bearing account (c.30 §39F).

## Sources

- [M.G.L. c.149 §29E](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleXXI/Chapter149/Section29E) (mirror; the official site did not load)
- [M.G.L. c.30 §§39K, 39G, 39F](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleIII/Chapter30/Section39K) (mirror; the official site did not load)

Sources marked "mirror" were read from the linked copy on October 13, 2026 because the state's official code site did not load for us. Check the official code before relying on those figures.

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Massachusetts retainage law](https://fynex.ai/construction/retainage/massachusetts/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- Massachusetts
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)