title: "Michigan Prompt Payment Act for Construction (2026): Deadlines & Interest"
description: "Michigan prompt pay: no statute sets private payment dates, the contract does; public agencies pay within 30 days. Statute, steps and calculator."
url: "/construction/prompt-payment/michigan/"
updated: "2026-10-13"
---

Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Michigan prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Michigan prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

There is no private prompt-payment act in Michigan. On public agency contracts of $30,000 or more with more than three payments, each progress payment is due on the later of 30 days after the architect or engineer certifies work in place or 15 days after the agency receives the funds that will pay it, and the contractor may add reasonable interest to its next payment request. State principal executive departments owe a separate 0.75% per month penalty if payment is not mailed within 45 days of the invoice (Act 279 of 1984).

## Prompt payment on private jobs

**No statute.** Michigan has no prompt-payment statute for private construction. The Construction Lien Act (MCL 570.1101 et seq., Act 497 of 1980) has no payment deadline, interest rate or retainage rule between owner, GC and sub, and the Prompt Payment/Retainage statute (Act 524 of 1980) covers only contracts with public agencies. Private owners, GCs and subs are governed by the contract's payment terms, the lien waiver forms and priority rules in the Construction Lien Act, and the lien deadlines. Several private bills (2018, 2020, 2022 HB 6174, 2023 SB 451 / HB 4837) were introduced and none was found enacted. Verification 2026-10-13: the official compiled laws (complete through PA 103 of 2026) show no private payment clock in Act 524 or the Construction Lien Act; an enacted private prompt-pay act would appear there.

## Prompt payment on public jobs

| Rule | Michigan law |
|---|---|
| Agency pays the prime within | 30 days ([Mich. Comp. Laws §§125.1561-125.1566 (Act 524 of 1980); §§17.52, 17.54 (Act 279 of 1984)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1562)) |
| Prime pays each sub within | Not set by statute |
| Interest on late payment | Act 524: each progress payment (with reasonable interest if requested in the next payment request) is due on the later of 30 days after the architect or engineer certifies the work in place, or 15 days after the agency receives the funds from a state or federal source; no interest rate is fixed ('reasonable interest', MCL 125.1562(4)). Act 279 of 1984: unless otherwise agreed in writing, principal executive departments of the State mail payment within 45 days after receiving the goods or services, a complete invoice or a complete contract, whichever is later, and owe an extra 0.75% of the payment for the first month and each further month or portion of a month past due (MCL 17.52, 17.54); the statute states no annual rate. ([Mich. Comp. Laws §§125.1561-125.1566 (Act 524 of 1980); §§17.52, 17.54 (Act 279 of 1984)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1562)) |

Act 524 has no sub-payment deadline for the GC; it governs the agency-to-contractor relationship. Act 524 covers written contracts of $30,000 or more with more than 3 payments and excludes the state transportation department, school districts, community colleges, the Michigan State Housing Development Authority and municipal electric utilities.

## When the GC says it hasn't been paid in Michigan

On a private Michigan job, a pay-if-paid or pay-when-paid clause is a contract matter: no prompt-pay statute overrides it, and the Construction Lien Act treats retainage that is payable only after a further event as 'not due' until then (MCL 570.1115(5), 570.1119(5)). A 2010 bill to ban pay-when-paid clauses in public-works bonding (Senate Bill 1319, amending 1963 PA 213) was only referred to committee and never enacted, so Michigan has no statutory pay-if-paid ban on public or private work.

## After the deadline: what a sub can do in Michigan

Private job: send written demand citing the contract and protect your construction lien: serve a notice of furnishing and record a claim of lien within the Construction Lien Act deadlines. Public job: sue on the payment bond; the claimant must have served written notice on the principal contractor within 30 days after first furnishing labor or materials and given written notice to the contractor and the governmental unit within 90 days after last furnishing, and may sue after 90 days unpaid and within one year of final payment (MCL 129.207, 129.209).

## Michigan quirks to know

Act 524 applies only to contracts with public agencies of $30,000 or more with more than three payments and excludes MDOT, school districts, community colleges, MSHDA and municipal electric utilities. Agencies must put retainage in a separate interest-bearing account and account for it per contract. A dispute-resolution 'agent' may rule on contractor delay and decide who gets the interest earned on retainage. The statutory interest on a late progress payment is 'reasonable interest', not a number. Retained funds may not exceed the agency's pro rata matching share, and grant-funded retainage need not be deposited until the grant money arrives (125.1563(3)).

## Worked example: a $48,000 pay app paid late in Michigan

| | |
|---|---|
| Clock | Public job: agency → prime |
| Clock starts | June 15, 2026 |
| Payment due by | July 15, 2026 ([Mich. Comp. Laws §§125.1561-125.1566 (Act 524 of 1980); §§17.52, 17.54 (Act 279 of 1984)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1562)) |
| Paid | August 14, 2026 (30 days late) |
| Interest owed | No fixed statutory rate |

In Michigan, a public agency has to pay the prime within 30 days: with the clock starting June 15, 2026, payment is due by July 15, 2026. The statutory rate moves with an index ("Act 524: each progress payment (with reasonable interest if requested in the next payment request) is due on the later of 30 days after the architect or engineer certifies the work in place, or 15 days after the agency receives the funds from a state or federal source; no interest rate is fixed ('reasonable interest', MCL 125.1562(4)). Act 279 of 1984: unless otherwise agreed in writing, principal executive departments of the State mail payment within 45 days after receiving the goods or services, a complete invoice or a complete contract, whichever is later, and owe an extra 0.75% of the payment for the first month and each further month or portion of a month past due (MCL 17.52, 17.54); the statute states no annual rate."), so enter the current figure in the calculator.

## Michigan prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/michigan/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** no statutory deadline; no fixed statutory interest rate.
- **Private job: owner → GC:** no statutory deadline; no fixed statutory interest rate.
- **Public job: prime → sub:** no statutory deadline; interest: Act 524: each progress payment (with reasonable interest if requested in the next payment request) is due on the later of 30 days after the architect or engineer certifies the work in place, or 15 days after the agency receives the funds from a state or federal source; no interest rate is fixed ('reasonable interest', MCL 125.1562(4)). Act 279 of 1984: unless otherwise agreed in writing, principal executive departments of the State mail payment within 45 days after receiving the goods or services, a complete invoice or a complete contract, whichever is later, and owe an extra 0.75% of the payment for the first month and each further month or portion of a month past due (MCL 17.52, 17.54); the statute states no annual rate..
- **Public job: agency → prime:** 30 days; interest: Act 524: each progress payment (with reasonable interest if requested in the next payment request) is due on the later of 30 days after the architect or engineer certifies the work in place, or 15 days after the agency receives the funds from a state or federal source; no interest rate is fixed ('reasonable interest', MCL 125.1562(4)). Act 279 of 1984: unless otherwise agreed in writing, principal executive departments of the State mail payment within 45 days after receiving the goods or services, a complete invoice or a complete contract, whichever is later, and owe an extra 0.75% of the payment for the first month and each further month or portion of a month past due (MCL 17.52, 17.54); the statute states no annual rate..

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Michigan prompt payment law: questions

### How fast must a Michigan public agency pay a progress payment?

By the later of 30 days after the architect or engineer certifies the work in place or 15 days after the agency receives the funds, if funds come from the state or federal government (MCL 125.1562(3)).

### Does Michigan have a prompt payment act for private projects?

No. Bills to create one (2018, 2020, 2022 and 2023) were introduced and none was found enacted.

## Sources

- [Mich. Comp. Laws §§125.1561-125.1566 (Act 524 of 1980); §§17.52, 17.54 (Act 279 of 1984)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1562)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Michigan retainage law](https://fynex.ai/construction/retainage/michigan/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- Michigan
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)