Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Minnesota prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Minnesota prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Minnesota's one hard clock is the sub-payment clock: the contract is deemed to require the GC and every sub tier to pay a sub or supplier within 10 days after receiving payment for the sub's undisputed work, with 1.5% per month interest (minimum $10 a month), costs and attorney fees to a prevailing party, and a right to suspend work if unpaid after 10 days (337.10 subd. 3). The owner has no statutory day count: progress payments are monthly on approved estimates. Municipalities have 35 days from receipt (471.425).

## Prompt payment on private jobs

| Rule | Minnesota law |
|---|---|
| Owner pays the GC within | Not set by statute |
| GC pays each sub within | 10 days days after the party responsible for payment receives payment for undisputed services (the contract is deemed to require this of the prime contractor and every subcontractor tier), including retainage payments ([Minn. Stat. §337.10 subds. 3-4; §337.01 subd. 2](https://www.revisor.mn.gov/statutes/cite/337.10)) |
| Flows down to sub-tiers | Yes ([Minn. Stat. §337.10 subds. 3-4; §337.01 subd. 2](https://www.revisor.mn.gov/statutes/cite/337.10)) |
| Interest on late payment | 1.5% per month on any undisputed amount not paid on time; minimum $10 per month on a balance of $100 or more; a prevailing party gets costs, disbursements and attorney fees; an unpaid party may suspend work after 10 days ([Minn. Stat. §337.10 subds. 3-4; §337.01 subd. 2](https://www.revisor.mn.gov/statutes/cite/337.10)) |
| Attorney's fees to the prevailing party | Yes ([Minn. Stat. §337.10 subds. 3-4; §337.01 subd. 2](https://www.revisor.mn.gov/statutes/cite/337.10)) |

## Prompt payment on public jobs

| Rule | Minnesota law |
|---|---|
| Agency pays the prime within | 35 days ([Minn. Stat. §§471.425, 16A.124, 15.72, 337.10 subd. 3](https://www.revisor.mn.gov/statutes/cite/471.425)) |
| Prime pays each sub within | 10 days of receiving payment ([Minn. Stat. §§471.425, 16A.124, 15.72, 337.10 subd. 3](https://www.revisor.mn.gov/statutes/cite/471.425)) |
| Interest on late payment | Municipalities (cities, counties, towns, school districts, political subdivisions): pay according to the contract or within 35 days of the date of receipt (45 days if the governing board meets less than monthly); interest 1.5% per month, minimum $10 (Minn. Stat. 471.425). State agencies: 30 days from invoice, but no interest penalty accrues against an agency for claims made by a contractor under a construction contract (16A.124 subd. 5(e)). Prime contractor must pay subs within 10 days of receiving payment, with 1.5% per month interest (471.425 subd. 4a; 337.10 subd. 3) ([Minn. Stat. §§471.425, 16A.124, 15.72, 337.10 subd. 3](https://www.revisor.mn.gov/statutes/cite/471.425)) |

## When the GC says it hasn't been paid in Minnesota

Minnesota keys the sub's 10 days to the GC receiving payment from the party responsible for payment, so the GC cannot stretch it without having been paid. Undisputed amounts only: a GC with a real dispute about a sub's work must still pay out retainage to subs whose work is not involved and give a written statement of the amount and reason (337.10 subd. 4(d)). A contract cannot require a lien or payment-bond claim waiver before you have been paid (337.10 subd. 2).

## After the deadline: what a sub can do in Minnesota

If an undisputed payment is not received within 10 days, you may suspend work until it arrives (337.10 subd. 3). Demand the amount plus 1.5% per month interest, and note that a prevailing party in a civil action to collect the penalties must be awarded costs, disbursements and attorney fees. Keep the mechanic's lien notice and claim deadlines running in parallel. On public work, request payment information in writing: from 2026 (Laws 2026 ch. 90) the agency must give you the amount, date and pay application copy within 7 calendar days.

## Minnesota quirks to know

State agency interest does not apply to construction contractor claims (16A.124 subd. 5(e)), but municipalities owe 1.5% per month under 471.425. The same 5% / 60 / 10-day retainage rules appear twice, in 337.10 for private jobs and in 15.72 for public improvements (337.10 subd. 4(g) carves public agencies out). Federal- or state-aid projects: the agency need not pay the aided portion until the aid is received (15.72 subd. 2(h)). Maintenance or repair of production machinery and utility equipment is outside the definition of a building and construction contract.

## Worked example: a $48,000 pay app paid late in Minnesota

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 25, 2026 ([Minn. Stat. §337.10 subds. 3-4; §337.01 subd. 2](https://www.revisor.mn.gov/statutes/cite/337.10)) |
| Paid | July 25, 2026 (30 days late) |
| Interest owed | $710.14 ([Minn. Stat. §337.10 subds. 3-4; §337.01 subd. 2](https://www.revisor.mn.gov/statutes/cite/337.10)) |

In Minnesota, a GC paid by the owner has to pay the sub within 10 days: with the clock starting June 15, 2026, payment is due by June 25, 2026. Paid 30 days after that, a $48,000 payment carries $710.14 of interest at 18% a year, simple.

## Minnesota prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/minnesota/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 10 days (days after the party responsible for payment receives payment for undisputed services (the contract is deemed to require this of the prime contractor and every subcontractor tier), including retainage payments); interest: 1.5% per month on any undisputed amount not paid on time; minimum $10 per month on a balance of $100 or more; a prevailing party gets costs, disbursements and attorney fees; an unpaid party may suspend work after 10 days.
- **Private job: owner → GC:** no statutory deadline; interest: 1.5% per month on any undisputed amount not paid on time; minimum $10 per month on a balance of $100 or more; a prevailing party gets costs, disbursements and attorney fees; an unpaid party may suspend work after 10 days.
- **Public job: prime → sub:** 10 days (after the prime is paid); interest: Municipalities (cities, counties, towns, school districts, political subdivisions): pay according to the contract or within 35 days of the date of receipt (45 days if the governing board meets less than monthly); interest 1.5% per month, minimum $10 (Minn. Stat. 471.425). State agencies: 30 days from invoice, but no interest penalty accrues against an agency for claims made by a contractor under a construction contract (16A.124 subd. 5(e)). Prime contractor must pay subs within 10 days of receiving payment, with 1.5% per month interest (471.425 subd. 4a; 337.10 subd. 3).
- **Public job: agency → prime:** 35 days; interest: Municipalities (cities, counties, towns, school districts, political subdivisions): pay according to the contract or within 35 days of the date of receipt (45 days if the governing board meets less than monthly); interest 1.5% per month, minimum $10 (Minn. Stat. 471.425). State agencies: 30 days from invoice, but no interest penalty accrues against an agency for claims made by a contractor under a construction contract (16A.124 subd. 5(e)). Prime contractor must pay subs within 10 days of receiving payment, with 1.5% per month interest (471.425 subd. 4a; 337.10 subd. 3).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Minnesota prompt payment law: questions

### How many days does a Minnesota GC have to pay a sub?

10 days after receiving payment for the sub's undisputed work, including retainage (337.10 subd. 3; 15.72 subd. 2(c)).

### What interest applies to late payment to a Minnesota sub?

1.5% per month on the undisputed amount, with a minimum of $10 a month on balances of $100 or more (337.10 subd. 3).

### Can I stop work if my Minnesota GC does not pay?

Yes. If an undisputed payment is not received within 10 days, the prime contractor or a sub of any tier may suspend work until it is received (337.10 subd. 3).

## Sources

- [Minn. Stat. §337.10 subds. 3-4; §337.01 subd. 2](https://www.revisor.mn.gov/statutes/cite/337.10)
- [Minn. Stat. §§471.425, 16A.124, 15.72, 337.10 subd. 3](https://www.revisor.mn.gov/statutes/cite/471.425)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Minnesota retainage law](https://fynex.ai/construction/retainage/minnesota/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- Minnesota
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)