Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Mississippi prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Mississippi prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

For private construction, Miss. Code 87-7-3 makes progress payments bear 1% per month interest if still unpaid 60 calendar days after they were due, and 87-7-5 requires a prime to pay each sub and supplier, in proportion to the work completed, on receipt of owner payment, with a penalty of 0.5% per day (max 15%) if it pays later than 15 days. Public jobs follow the same pattern in 31-5-25 and 31-5-27. Single-family dwelling contracts are outside 87-7-5.

## Prompt payment on private jobs

| Rule | Mississippi law |
|---|---|
| Residential work | 87-7-5 (sub payment) does not apply to contracts for construction of single-family dwellings; 87-7-3 excludes public construction contracts ([Miss. Code §§87-7-3, 87-7-5](https://www.mscode.com/free/statutes/87/007/0005.htm)) |
| Owner pays the GC within | 60 days calendar days after the progress or final payment was due and payable under the contract: the 1% per month interest starts from the due date only if the payment is not made within 60 calendar days; final payment is due at substantial completion, owner's beneficial use or occupancy, or architect/engineer certification of completion, whichever occurs first, and needs the surety's written consent ([Miss. Code §§87-7-3, 87-7-5](https://www.mscode.com/free/statutes/87/007/0005.htm)) |
| GC pays each sub within | 15 days days after the prime contractor receives payment from the owner; payment on receipt must be proportional to the percentage of work completed by each sub and supplier, and prorated if the contractor is paid less than the full amount ([Miss. Code §§87-7-3, 87-7-5](https://www.mscode.com/free/statutes/87/007/0005.htm)) |
| Interest on late payment | Owner to contractor: 1% per month from the due date if unpaid after 60 calendar days. Contractor to subs/suppliers: penalty of one-half of 1% per day from the 15th day, up to 15% of the outstanding balance, if payment is withheld without reasonable cause ([Miss. Code §§87-7-3, 87-7-5](https://www.mscode.com/free/statutes/87/007/0005.htm)) |

## Prompt payment on public jobs

| Rule | Mississippi law |
|---|---|
| Agency pays the prime within | 60 days ([Miss. Code §§31-5-25, 31-5-27, 31-5-29](https://www.mscode.com/free/statutes/31/005/0025.htm)) |
| Prime pays each sub within | 15 days of receiving payment ([Miss. Code §§31-5-25, 31-5-27, 31-5-29](https://www.mscode.com/free/statutes/31/005/0025.htm)) |
| Interest on late payment | Public owner to contractor: progress and final payments due under the contract; interest of 1% per month if not paid within 60 calendar days of the due date (final payment: of completion, beneficial use or certification). Contractor to subs/suppliers: pay in proportion on receipt; penalty of one-half of 1% per day after 15 days, capped at 15% of the balance. Applies to state agencies, boards, districts, municipalities and counties (31-5-29) ([Miss. Code §§31-5-25, 31-5-27, 31-5-29](https://www.mscode.com/free/statutes/31/005/0025.htm)) |

## When the GC says it hasn't been paid in Mississippi

The GC must pay subs pro rata on receipt: if the owner pays less than the full amount, the GC disburses what it receives proportionally among itself, its subs and suppliers (87-7-5; 31-5-27 for public work). The statute's 15-day penalty clock runs from the GC's receipt of payment from the owner, so a pay-if-paid clause can delay it. The 2024 retainage act expressly keeps pay-if-paid and lien-release conditions enforceable, so read your subcontract.

## After the deadline: what a sub can do in Mississippi

If the GC does not pay within 15 days after it is paid, demand the payment plus the 0.5% per day penalty (capped at 15%). For retainage on a private job entered after July 1, 2024, sue only the party in direct privity under S.B. 2762 section 1(6) for the amount plus 1% per month on any excess held; the prevailing party recovers attorney's fees, costs and expenses. Public job: claim on the payment bond and observe the notice deadlines under Miss. Code Title 31, chapter 5.

## Mississippi quirks to know

Private retainage rules cover contracts over $10,000 and exclude residential homebuilding and residential improvements of 16 or fewer units; lenders are not parties from whom interest can be claimed. The 5% retainage cap applies at every tier, and only the excess carries interest. Public retainage drops from 5% to 2.5% after the 50% mark on contracts of $250,000 or more and halves the held amount at that point. Mississippi Transportation Commission road and bridge contracts are outside 31-5-33.

## Worked example: a $48,000 pay app paid late in Mississippi

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 30, 2026 ([Miss. Code §§87-7-3, 87-7-5](https://www.mscode.com/free/statutes/87/007/0005.htm)) |
| Paid | July 30, 2026 (30 days late) |
| Interest owed | $473.42 ([Miss. Code §§87-7-3, 87-7-5](https://www.mscode.com/free/statutes/87/007/0005.htm)) |

In Mississippi, a GC paid by the owner has to pay the sub within 15 days: with the clock starting June 15, 2026, payment is due by June 30, 2026. Paid 30 days after that, a $48,000 payment carries $473.42 of interest at 12% a year, simple.

## Mississippi prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/mississippi/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 15 days (days after the prime contractor receives payment from the owner; payment on receipt must be proportional to the percentage of work completed by each sub and supplier, and prorated if the contractor is paid less than the full amount); interest: Owner to contractor: 1% per month from the due date if unpaid after 60 calendar days. Contractor to subs/suppliers: penalty of one-half of 1% per day from the 15th day, up to 15% of the outstanding balance, if payment is withheld without reasonable cause.
- **Private job: owner → GC:** 60 days (calendar days after the progress or final payment was due and payable under the contract: the 1% per month interest starts from the due date only if the payment is not made within 60 calendar days; final payment is due at substantial completion, owner's beneficial use or occupancy, or architect/engineer certification of completion, whichever occurs first, and needs the surety's written consent); interest: Owner to contractor: 1% per month from the due date if unpaid after 60 calendar days. Contractor to subs/suppliers: penalty of one-half of 1% per day from the 15th day, up to 15% of the outstanding balance, if payment is withheld without reasonable cause.
- **Public job: prime → sub:** 15 days (after the prime is paid); interest: Public owner to contractor: progress and final payments due under the contract; interest of 1% per month if not paid within 60 calendar days of the due date (final payment: of completion, beneficial use or certification). Contractor to subs/suppliers: pay in proportion on receipt; penalty of one-half of 1% per day after 15 days, capped at 15% of the balance. Applies to state agencies, boards, districts, municipalities and counties (31-5-29).
- **Public job: agency → prime:** 60 days; interest: Public owner to contractor: progress and final payments due under the contract; interest of 1% per month if not paid within 60 calendar days of the due date (final payment: of completion, beneficial use or certification). Contractor to subs/suppliers: pay in proportion on receipt; penalty of one-half of 1% per day after 15 days, capped at 15% of the balance. Applies to state agencies, boards, districts, municipalities and counties (31-5-29).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Mississippi prompt payment law: questions

### How fast must a Mississippi GC pay a sub after the owner pays?

Within 15 days of receipt; after that a penalty of 0.5% per day, up to 15% of the balance, applies (Miss. Code 87-7-5; 31-5-27 on public contracts).

### Is pay-if-paid enforceable in Mississippi?

The 2024 retainage act says a payer may condition payment on receipt of payment from its own payer and on lien releases (section 1(4)); Mississippi courts' treatment beyond that was not researched here.

## Sources

- [Miss. Code §§87-7-3, 87-7-5](https://www.mscode.com/free/statutes/87/007/0005.htm) (mirror; the official site did not load)
- [Miss. Code §§31-5-25, 31-5-27, 31-5-29](https://www.mscode.com/free/statutes/31/005/0025.htm) (mirror; the official site did not load)

Sources marked "mirror" were read from the linked copy on October 13, 2026 because the state's official code site did not load for us. Check the official code before relying on those figures.

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Mississippi retainage law](https://fynex.ai/construction/retainage/mississippi/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- Mississippi
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)