Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Missouri prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Missouri prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

On public works, the owner pays the contractor within 30 days of delivery, invoice or approval of the estimate, and the contractor pays each sub and supplier within 15 days of receiving payment; late amounts bear 1.5% per month at each tier (RSMo 8.960). On private work, RSMo 431.180 only requires scheduled payments to be made as the contract says; a court may award interest up to 1.5% per month and attorney fees, but there are no statutory day counts.

## Prompt payment on private jobs

| Rule | Missouri law |
|---|---|
| Residential work | Contracts for private construction work on owner-occupied residential property of four units or less are excluded (RSMo 431.180.3) ([RSMo 431.180, 431.183](https://revisor.mo.gov/main/OneSection.aspx?section=431.180)) |
| Owner pays the GC within | Not set by statute |
| GC pays each sub within | Not set by statute |
| Interest on late payment | A court may award interest of up to 1.5% per month from the date payment was due under the contract, plus reasonable attorney fees to the prevailing party; an arbitrator has the same remedies ([RSMo 431.180, 431.183](https://revisor.mo.gov/main/OneSection.aspx?section=431.180)) |
| Attorney's fees to the prevailing party | Yes ([RSMo 431.180, 431.183](https://revisor.mo.gov/main/OneSection.aspx?section=431.180)) |

## Prompt payment on public jobs

| Rule | Missouri law |
|---|---|
| Agency pays the prime within | 30 days ([RSMo 8.960 (formerly 34.057)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |
| Prime pays each sub within | 15 days of receiving payment ([RSMo 8.960 (formerly 34.057)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |
| Interest on late payment | 1.5% per month from the end of the 30-day period (owner to contractor), and 1.5% per month from the end of the 15th day after receipt (contractor to subs and suppliers, and every lower tier); RSMo 8.960 ([RSMo 8.960 (formerly 34.057)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |

## When the GC says it hasn't been paid in Missouri

On private jobs, a contract term making a sub's payment contingent on the GC's receipt from a private owner is no defense to a mechanic's lien claim under chapter 429 (RSMo 431.183), but Missouri's private statute does not otherwise limit pay-if-paid. On public works, a contractor must pay subs pro rata on whatever it receives; when the owner rejects specific work in writing, only the subs responsible for that work go unpaid and all others are paid in full (RSMo 8.960.1(6)).

## After the deadline: what a sub can do in Missouri

Public job: claim 1.5% per month from the 16th day after the GC was paid and from the owner's day-30 for the prime; the contractor must separately identify and carry forward any amount it withholds from a sub in its next application (8.960.3). Private job: demand in writing and sue under RSMo 431.180.2 for up to 1.5% per month and attorney fees; keep the chapter 429 lien deadlines and, on residential property, the notice-of-rights requirement (429.016) running.

## Missouri quirks to know

The old 34.057 text now lives at 8.960 (transferred 2022). The public prompt-pay clock for subs runs 15 days from the contractor's receipt of payment and reaches every lower tier. Retainage released to subs is a separate 30-day clock after acceptance. The state's general supplier-invoice interest in RSMo 34.055 (45 days, prime plus 3 points) is for supplies and services and yields to 8.960 for public works. Missouri's DOT is carved out of 8.962 (delay-damages clauses).

## Worked example: a $48,000 pay app paid late in Missouri

| | |
|---|---|
| Clock | Public job: prime → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 30, 2026 ([RSMo 8.960 (formerly 34.057)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |
| Paid | July 30, 2026 (30 days late) |
| Interest owed | $710.14 ([RSMo 8.960 (formerly 34.057)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)) |

In Missouri, a prime paid by the agency has to pay the sub within 15 days: with the clock starting June 15, 2026, payment is due by June 30, 2026. Paid 30 days after that, a $48,000 payment carries $710.14 of interest at 18% a year, simple.

## Missouri prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/missouri/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** no statutory deadline; interest: A court may award interest of up to 1.5% per month from the date payment was due under the contract, plus reasonable attorney fees to the prevailing party; an arbitrator has the same remedies.
- **Private job: owner → GC:** no statutory deadline; interest: A court may award interest of up to 1.5% per month from the date payment was due under the contract, plus reasonable attorney fees to the prevailing party; an arbitrator has the same remedies.
- **Public job: prime → sub:** 15 days (after the prime is paid); interest: 1.5% per month from the end of the 30-day period (owner to contractor), and 1.5% per month from the end of the 15th day after receipt (contractor to subs and suppliers, and every lower tier); RSMo 8.960.
- **Public job: agency → prime:** 30 days; interest: 1.5% per month from the end of the 30-day period (owner to contractor), and 1.5% per month from the end of the 15th day after receipt (contractor to subs and suppliers, and every lower tier); RSMo 8.960.

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Missouri prompt payment law: questions

### How fast must a Missouri GC pay a subcontractor on public work?

Within 15 days of receiving payment, with 1.5% per month interest after that, down every tier (RSMo 8.960.1(7)); retainage is paid within 30 days after acceptance (8.960.1(4)).

### What interest can I charge on late payment in Missouri?

On public works, 1.5% per month (8.960). On private jobs, a court may award up to 1.5% per month from the contract due date, plus attorney fees (431.180.2).

### Is pay-if-paid enforceable against my mechanic's lien in Missouri?

No: a private pay-if-paid or similar contingency is no defense to a mechanic's lien claim under chapter 429 (RSMo 431.183).

## Sources

- [RSMo 431.180, 431.183](https://revisor.mo.gov/main/OneSection.aspx?section=431.180)
- [RSMo 8.960 (formerly 34.057)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Missouri retainage law](https://fynex.ai/construction/retainage/missouri/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- Missouri
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)