Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Montana prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Montana prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Montana runs two clocks. Owner to GC: a pay app is deemed approved 21 days after the owner receives it unless the owner sends a written statement disapproving specific items, and approved amounts are due 7 days later (MCA 28-2-2103(1)). GC to sub: 7 days after the GC receives payment from the owner or a state agency, and the same 7 days passes down to every lower tier (28-2-2103(2)-(3)). If a payment is more than 30 days late against its due date, interest runs at 1.5% a month from the day after the due date (28-2-2104). The prevailing party in a suit to enforce the part recovers attorney fees (28-2-2105).

## Prompt payment on private jobs

| Rule | Montana law |
|---|---|
| Residential work | Part 21 does not apply to residential projects or residential improvements with a total cost under $400,000 (MCA 28-2-2107). ([MCA 28-2-2101, 28-2-2102, 28-2-2103, 28-2-2104, 28-2-2105, 28-2-2107, 28-2-2115, 28-2-2116, 28-2-2117](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/sections_index.html)) |
| Owner pays the GC within | 28 days a pay request is deemed approved 21 days after the owner receives it unless the owner sends a written statement disapproving specific items; the owner then pays within 7 days after approval (21 + 7 = 28 days). Parties can lengthen either period only with the conspicuous bidder notices in MCA 28-2-2115. ([MCA 28-2-2101, 28-2-2102, 28-2-2103, 28-2-2104, 28-2-2105, 28-2-2107, 28-2-2115, 28-2-2116, 28-2-2117](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/sections_index.html)) |
| GC pays each sub within | 7 days after the contractor receives a periodic or final payment from the owner or a state agency; the sub must have sent a billing statement or invoice ([MCA 28-2-2101, 28-2-2102, 28-2-2103, 28-2-2104, 28-2-2105, 28-2-2107, 28-2-2115, 28-2-2116, 28-2-2117](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/sections_index.html)) |
| Flows down to sub-tiers | Yes ([MCA 28-2-2101, 28-2-2102, 28-2-2103, 28-2-2104, 28-2-2105, 28-2-2107, 28-2-2115, 28-2-2116, 28-2-2117](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/sections_index.html)) |
| Written notice to withhold | Within 21 days ([MCA 28-2-2101, 28-2-2102, 28-2-2103, 28-2-2104, 28-2-2105, 28-2-2107, 28-2-2115, 28-2-2116, 28-2-2117](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/sections_index.html)) |
| Interest on late payment | 1 1/2% a month (pro rata) on the unpaid balance, owed once a payment is delayed more than 30 days past its contract due date, running from the day after the due date; interest received must be passed to subs pro rata ([MCA 28-2-2101, 28-2-2102, 28-2-2103, 28-2-2104, 28-2-2105, 28-2-2107, 28-2-2115, 28-2-2116, 28-2-2117](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/sections_index.html)) |
| Attorney's fees to the prevailing party | Yes ([MCA 28-2-2101, 28-2-2102, 28-2-2103, 28-2-2104, 28-2-2105, 28-2-2107, 28-2-2115, 28-2-2116, 28-2-2117](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/sections_index.html)) |

## Prompt payment on public jobs

| Rule | Montana law |
|---|---|
| Agency pays the prime within | 28 days Same clock as private work: payment request deemed approved 21 days after receipt, then paid within 7 days (MCA 28-2-2103(1)); 18-2-123 sends public contractor and sub payment to Title 28, ch. 2, part 21. Separately, on a building contract a government entity decides on final acceptance within 10 days of the contractor's request and pays the final payment within 30 days after final acceptance (18-2-306(1)). ([MCA 18-2-123, 18-2-306, 28-2-2103, 28-2-2104, 17-8-242, 18-1-404](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0060/0180-0020-0030-0060.html)) |
| Prime pays each sub within | 7 days of receiving payment ([MCA 18-2-123, 18-2-306, 28-2-2103, 28-2-2104, 17-8-242, 18-1-404](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0060/0180-0020-0030-0060.html)) |
| Interest on late payment | Part 21 interest (1 1/2% a month, MCA 28-2-2104) applies between owner and contractor and between contractor and sub. On a late final payment by a government entity, 18-2-306(2) points to the rate in 17-8-242 (state agencies: simple interest of 0.05% each day) or 18-1-404 (10% simple interest a year if a good-faith dispute is in a court or agency). ([MCA 18-2-123, 18-2-306, 28-2-2103, 28-2-2104, 17-8-242, 18-1-404](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0060/0180-0020-0030-0060.html)) |

## When the GC says it hasn't been paid in Montana

Montana's statute ties your 7 days to the GC being paid, not to the GC feeling like paying you. It does not mention pay-if-paid, and it says performance of the subcontract entitles you to payment from the contractor (28-2-2102(2)). You can ask the owner in writing to tell you what it has paid the GC on your work (28-2-2103(1)(g)). If the owner did pay and the GC did not pass it through, the 7 days have run and Part 21 interest starts to build once you are more than 30 days past the due date. Enforceability of pay-if-paid clauses is a case-law question not covered here.

## After the deadline: what a sub can do in Montana

1) Check your billing statement or invoice went to the GC: payment is not required under 28-2-2103(2) without it. 2) Send a written request to the owner under 28-2-2103(1)(g) for the date and amount paid to the GC. 3) Give the GC and the owner at least 7 calendar days written notice before suspending work; you may suspend and, if still unpaid 30 days after suspension, terminate (28-2-2117). Contract clauses that remove this right are void (28-2-2116(2)). 4) Demand 1.5% a month once more than 30 days late. 5) A suit to enforce the part carries fees to the winner (28-2-2105). Check lien and bond-claim deadlines separately: they are not in Part 21.

## Montana quirks to know

Part 21 reaches both private and public owners, because 18-2-123 sends public contractor and sub payment to the same part. The owner may disapprove only for the seven reasons in 28-2-2103(1)(c), and may withhold only enough to cover the direct expense of correcting them. Parties can lengthen the 21-day approval and 7-day payment periods only with the conspicuous 'Information for Bidders' notices in 28-2-2115. Out-of-state governing-law and venue clauses on Montana projects are void (28-2-2116(1)). Residential projects under $400,000 are exempt.

## Worked example: a $48,000 pay app paid late in Montana

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 22, 2026 ([MCA 28-2-2101, 28-2-2102, 28-2-2103, 28-2-2104, 28-2-2105, 28-2-2107, 28-2-2115, 28-2-2116, 28-2-2117](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/sections_index.html)) |
| Paid | July 22, 2026 (30 days late) |
| Interest owed | $710.14 ([MCA 28-2-2101, 28-2-2102, 28-2-2103, 28-2-2104, 28-2-2105, 28-2-2107, 28-2-2115, 28-2-2116, 28-2-2117](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/sections_index.html)) |

In Montana, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. Paid 30 days after that, a $48,000 payment carries $710.14 of interest at 18% a year, simple.

## Montana prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/montana/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 7 days (after the contractor receives a periodic or final payment from the owner or a state agency; the sub must have sent a billing statement or invoice); interest: 1 1/2% a month (pro rata) on the unpaid balance, owed once a payment is delayed more than 30 days past its contract due date, running from the day after the due date; interest received must be passed to subs pro rata.
- **Private job: owner → GC:** 28 days (a pay request is deemed approved 21 days after the owner receives it unless the owner sends a written statement disapproving specific items; the owner then pays within 7 days after approval (21 + 7 = 28 days). Parties can lengthen either period only with the conspicuous bidder notices in MCA 28-2-2115.); interest: 1 1/2% a month (pro rata) on the unpaid balance, owed once a payment is delayed more than 30 days past its contract due date, running from the day after the due date; interest received must be passed to subs pro rata.
- **Public job: prime → sub:** 7 days (after the prime is paid); interest: Part 21 interest (1 1/2% a month, MCA 28-2-2104) applies between owner and contractor and between contractor and sub. On a late final payment by a government entity, 18-2-306(2) points to the rate in 17-8-242 (state agencies: simple interest of 0.05% each day) or 18-1-404 (10% simple interest a year if a good-faith dispute is in a court or agency)..
- **Public job: agency → prime:** 28 days (Same clock as private work: payment request deemed approved 21 days after receipt, then paid within 7 days (MCA 28-2-2103(1)); 18-2-123 sends public contractor and sub payment to Title 28, ch. 2, part 21. Separately, on a building contract a government entity decides on final acceptance within 10 days of the contractor's request and pays the final payment within 30 days after final acceptance (18-2-306(1)).); interest: Part 21 interest (1 1/2% a month, MCA 28-2-2104) applies between owner and contractor and between contractor and sub. On a late final payment by a government entity, 18-2-306(2) points to the rate in 17-8-242 (state agencies: simple interest of 0.05% each day) or 18-1-404 (10% simple interest a year if a good-faith dispute is in a court or agency)..

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Montana prompt payment law: questions

### How fast does a Montana GC have to pay a sub after the owner pays?

7 days after the GC receives a periodic or final payment from the owner or a state agency (MCA 28-2-2103(2)). You must have sent a billing statement or invoice under the subcontract for the clock to bind. The same 7 days applies from a sub to its own lower-tier subs (28-2-2103(3)).

### What interest can I charge on late payment on a Montana construction job?

1.5% a month, pro rata, on the unpaid balance, once the payment is delayed more than 30 days past the date the contract required it, counted from the day after the due date (MCA 28-2-2104). Accepting final payment releases any claim for interest on it (28-2-2104(3)).

### Can I stop work if the GC does not pay me in Montana?

Yes, after at least 7 calendar days written notice to the GC and owner. You may suspend, and terminate if payment is not made within 30 days of suspension, without being in breach (MCA 28-2-2117). Contract clauses barring suspension for nonpayment are void (28-2-2116(2)).

### Does Montana's prompt-payment law cover small residential jobs?

No. Part 21 does not apply to residential projects or improvements for residential purposes with a total cost under $400,000 (MCA 28-2-2107).

## Sources

- [MCA 28-2-2101, 28-2-2102, 28-2-2103, 28-2-2104, 28-2-2105, 28-2-2107, 28-2-2115, 28-2-2116, 28-2-2117](https://leg.mt.gov/bills/mca/title_0280/chapter_0020/part_0210/sections_index.html)
- [MCA 18-2-123, 18-2-306, 28-2-2103, 28-2-2104, 17-8-242, 18-1-404](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0060/0180-0020-0030-0060.html)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Montana retainage law](https://fynex.ai/construction/retainage/montana/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- Montana
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)