Construction · Prompt payment law

New Mexico prompt payment law for construction: deadlines and interest

New Mexico runs two clocks. Owner to contractor: 21 days after the owner receives an undisputed request for payment, or 45 days for a local public body funded by grant money if the contract and plans carry the conspicuous extended-payment legend. Contractor or sub to the next tier: 7 days after receiving payment. Late amounts bear 1.5% of the undisputed amount per month or fraction of a month, so a single day late costs a full month's interest. Every construction contract must provide for these terms (NMSA 57-28-5).

Also in New Mexico: retainage law

New Mexico prompt payment calculator: days late and interest

Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from New Mexico law; change them if your contract or the statute's trigger differs.

Which clock

Clock starts: after the contractor or sub receives payment from the owner, contractor or subcontractor, for amounts owed for work performed; applies to all tiers of contractors, subcontractors and suppliers, and every construction contract must provide for it

Statute: one and one-half percent of the undisputed amount per month or fraction of a month, owner: beginning on the twenty-second day after payment was due; contractor to sub or supplier: beginning on the eighth day after payment was due, until payment is issued

Payment due by
June 22, 2026
Days late
30
Interest owed
$710.14
Total now owed
$48,710.14

30 days late at 18% a year.

Statute: NMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11

Calendar days and simple interest (18% a year ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Prompt payment on private jobs

RuleNew Mexico law
Residential workThe Prompt Payment Act does not apply to construction contracts for residential property containing four or fewer dwelling units (NMSA 57-28-3).NMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11
Owner pays the GC within21 days after the owner receives an undisputed request for payment; an improperly completed invoice must be answered with the defect within 7 days of receipt, and the owner has no duty to pay it until resubmitted completeNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11
GC pays each sub within7 days after the contractor or sub receives payment from the owner, contractor or subcontractor, for amounts owed for work performed; applies to all tiers of contractors, subcontractors and suppliers, and every construction contract must provide for itNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11
Flows down to sub-tiersYesNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11
Written notice to withholdWithin 7 daysNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11
Interest on late paymentone and one-half percent of the undisputed amount per month or fraction of a month, owner: beginning on the twenty-second day after payment was due; contractor to sub or supplier: beginning on the eighth day after payment was due, until payment is issuedNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11
Attorney's fees to the prevailing partyYesNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11

Prompt payment on public jobs

RuleNew Mexico law
Agency pays the prime within21 days Same 21 days after the owner receives an undisputed request for payment: 'owner' includes a local public body or state agency other than the Department of Transportation (57-28-2). A local public body may pay within 45 days when grant money is a funding source, only if the construction contract provides for it clearly and conspicuously and the plans carry the 'Notice of Extended Payment Provision' legend on each page (57-28-5(B)). Department of Transportation highway work is outside the Act.NMSA 1978, 57-28-2, 57-28-5
Prime pays each sub within7 days of receiving paymentNMSA 1978, 57-28-2, 57-28-5
Interest on late paymentOne and one-half percent of the undisputed amount per month or fraction of a month (57-28-5(A), (C))NMSA 1978, 57-28-2, 57-28-5

When the GC says it hasn't been paid in New Mexico

New Mexico's sub clock starts when the contractor or sub receives payment 'from the owner, contractor or subcontractor' (57-28-5(C)), and every tier is covered. The statute is silent on pay-if-paid clauses, so whether a contract can delay your payment beyond the owner's is a contract and case-law question. It does stop a creditor of the GC, owner or surety from garnishing or levying on progress payments owed to the people who furnished labor or material (57-28-5(D)). If the owner has paid, the GC's 7 days have run.

After the deadline: what a sub can do in New Mexico

1) Confirm your pay app was an 'undisputed request' complete on its face; an owner that finds a defect must tell you within 7 days of receipt (57-28-5(A)). 2) Count 21 days to the owner (or 7 days from the GC's receipt of payment). 3) Send a written demand citing the Prompt Payment Act and the 1.5%-per-month-or-fraction interest. 4) For the final payment, deliver the release, certified voucher and proof of completion; payment is due 10 days after certification of completion (57-28-8). 5) In an enforcement action the court may award costs and reasonable attorney fees (57-28-11). Lien and bond-claim deadlines are separate.

New Mexico quirks to know

Interest is 'per month or fraction of a month', so partial months count in full. The Act excludes residential property with four or fewer dwelling units and Department of Transportation owners. A local public body can stretch payment to 45 days only with the conspicuous contract language and plan-sheet legend on each page of the plans. The key retainage rule is indirect: the ban on holding back amounts owed, not a retainage section. Creditors cannot garnish or levy progress payments owed to the people who furnished labor or material (57-28-5(D)).

Worked example: a $48,000 pay app paid late in New Mexico

ClockPrivate job: GC → sub
Clock startsJune 15, 2026
Payment due byJune 22, 2026NMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11
PaidJuly 22, 2026 (30 days late)
Interest owed$710.14NMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11

In New Mexico, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. Paid 30 days after that, a $48,000 payment carries $710.14 of interest at 18% a year, simple.

Run a payment like this in the split calculator

New Mexico prompt payment law: questions

How long does a New Mexico owner have to pay a contractor?

21 days after receiving an undisputed request for payment (57-28-5(A)). A local public body funded with grant money may take 45 days only if the contract and every page of the plans carry the extended-payment notice (57-28-5(B)).

How fast must a New Mexico GC pay its subs?

7 days after receiving payment from the owner, contractor or subcontractor, at every tier (57-28-5(C)). Interest starts on the eighth day.

What interest applies to late payment in New Mexico?

1.5% of the undisputed amount per month or fraction of a month (57-28-5(A), (C)), about 18% a year. Because part of a month counts as a month, a short delay still costs a full month of interest.

When is final payment due after a New Mexico project is complete?

Ten days after certification of completion, on presentation of a release and certified voucher, a release of lien claims (other than any stated exceptions), and proof of completion (57-28-8).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.