New Mexico prompt payment law for construction: deadlines and interest
New Mexico runs two clocks. Owner to contractor: 21 days after the owner receives an undisputed request for payment, or 45 days for a local public body funded by grant money if the contract and plans carry the conspicuous extended-payment legend. Contractor or sub to the next tier: 7 days after receiving payment. Late amounts bear 1.5% of the undisputed amount per month or fraction of a month, so a single day late costs a full month's interest. Every construction contract must provide for these terms (NMSA 57-28-5).
Also in New Mexico: retainage law
New Mexico prompt payment calculator: days late and interest
Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from New Mexico law; change them if your contract or the statute's trigger differs.
Clock starts: after the contractor or sub receives payment from the owner, contractor or subcontractor, for amounts owed for work performed; applies to all tiers of contractors, subcontractors and suppliers, and every construction contract must provide for it
Statute: one and one-half percent of the undisputed amount per month or fraction of a month, owner: beginning on the twenty-second day after payment was due; contractor to sub or supplier: beginning on the eighth day after payment was due, until payment is issued
- Payment due by
- June 22, 2026
- Days late
- 30
- Interest owed
- $710.14
- Total now owed
- $48,710.14
30 days late at 18% a year.
Statute: NMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11
Calendar days and simple interest (18% a year ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.
Prompt payment on private jobs
| Rule | New Mexico law |
|---|---|
| Residential work | The Prompt Payment Act does not apply to construction contracts for residential property containing four or fewer dwelling units (NMSA 57-28-3).NMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11 |
| Owner pays the GC within | 21 days after the owner receives an undisputed request for payment; an improperly completed invoice must be answered with the defect within 7 days of receipt, and the owner has no duty to pay it until resubmitted completeNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11 |
| GC pays each sub within | 7 days after the contractor or sub receives payment from the owner, contractor or subcontractor, for amounts owed for work performed; applies to all tiers of contractors, subcontractors and suppliers, and every construction contract must provide for itNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11 |
| Flows down to sub-tiers | YesNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11 |
| Written notice to withhold | Within 7 daysNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11 |
| Interest on late payment | one and one-half percent of the undisputed amount per month or fraction of a month, owner: beginning on the twenty-second day after payment was due; contractor to sub or supplier: beginning on the eighth day after payment was due, until payment is issuedNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11 |
| Attorney's fees to the prevailing party | YesNMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11 |
Prompt payment on public jobs
| Rule | New Mexico law |
|---|---|
| Agency pays the prime within | 21 days Same 21 days after the owner receives an undisputed request for payment: 'owner' includes a local public body or state agency other than the Department of Transportation (57-28-2). A local public body may pay within 45 days when grant money is a funding source, only if the construction contract provides for it clearly and conspicuously and the plans carry the 'Notice of Extended Payment Provision' legend on each page (57-28-5(B)). Department of Transportation highway work is outside the Act.NMSA 1978, 57-28-2, 57-28-5 |
| Prime pays each sub within | 7 days of receiving paymentNMSA 1978, 57-28-2, 57-28-5 |
| Interest on late payment | One and one-half percent of the undisputed amount per month or fraction of a month (57-28-5(A), (C))NMSA 1978, 57-28-2, 57-28-5 |
When the GC says it hasn't been paid in New Mexico
New Mexico's sub clock starts when the contractor or sub receives payment 'from the owner, contractor or subcontractor' (57-28-5(C)), and every tier is covered. The statute is silent on pay-if-paid clauses, so whether a contract can delay your payment beyond the owner's is a contract and case-law question. It does stop a creditor of the GC, owner or surety from garnishing or levying on progress payments owed to the people who furnished labor or material (57-28-5(D)). If the owner has paid, the GC's 7 days have run.
After the deadline: what a sub can do in New Mexico
1) Confirm your pay app was an 'undisputed request' complete on its face; an owner that finds a defect must tell you within 7 days of receipt (57-28-5(A)). 2) Count 21 days to the owner (or 7 days from the GC's receipt of payment). 3) Send a written demand citing the Prompt Payment Act and the 1.5%-per-month-or-fraction interest. 4) For the final payment, deliver the release, certified voucher and proof of completion; payment is due 10 days after certification of completion (57-28-8). 5) In an enforcement action the court may award costs and reasonable attorney fees (57-28-11). Lien and bond-claim deadlines are separate.
New Mexico quirks to know
Interest is 'per month or fraction of a month', so partial months count in full. The Act excludes residential property with four or fewer dwelling units and Department of Transportation owners. A local public body can stretch payment to 45 days only with the conspicuous contract language and plan-sheet legend on each page of the plans. The key retainage rule is indirect: the ban on holding back amounts owed, not a retainage section. Creditors cannot garnish or levy progress payments owed to the people who furnished labor or material (57-28-5(D)).
Worked example: a $48,000 pay app paid late in New Mexico
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 22, 2026NMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11 |
| Paid | July 22, 2026 (30 days late) |
| Interest owed | $710.14NMSA 1978, 57-28-2, 57-28-3, 57-28-5, 57-28-8, 57-28-11 |
In New Mexico, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. Paid 30 days after that, a $48,000 payment carries $710.14 of interest at 18% a year, simple.
New Mexico prompt payment law: questions
How long does a New Mexico owner have to pay a contractor?
21 days after receiving an undisputed request for payment (57-28-5(A)). A local public body funded with grant money may take 45 days only if the contract and every page of the plans carry the extended-payment notice (57-28-5(B)).
How fast must a New Mexico GC pay its subs?
7 days after receiving payment from the owner, contractor or subcontractor, at every tier (57-28-5(C)). Interest starts on the eighth day.
What interest applies to late payment in New Mexico?
1.5% of the undisputed amount per month or fraction of a month (57-28-5(A), (C)), about 18% a year. Because part of a month counts as a month, a short delay still costs a full month of interest.
When is final payment due after a New Mexico project is complete?
Ten days after certification of completion, on presentation of a release and certified voucher, a release of lien claims (other than any stated exceptions), and proof of completion (57-28-8).
Sources
Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.