Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states New York prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# New York prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

New York's private Prompt Payment Act (GBL Art. 35-E) covers contracts of $150,000 or more. The owner approves or disapproves an invoice within 12 business days and pays within 30 days of approval; the GC pays you within 7 days of receiving good funds; late amounts carry 1% per month or fraction of a month (756-a, 756-b). Public work runs separately: 30 days from receipt of an invoice for State agencies (SFL 179-f), 30 or 45 days for local owners (GML 106-b), and 7 days from the contractor's receipt of funds down to subs.

## Prompt payment on private jobs

| Rule | New York law |
|---|---|
| Applies to | Contracts of $150,000 or more ([N.Y. Gen. Bus. Law 756, 756-a, 756-b, 757](https://www.nysenate.gov/legislation/laws/GBS/756-A)) |
| Residential work | GBL Article 35-E (sections 756 to 758) covers a construction contract only where the aggregate cost of the construction project (all labor, services, materials and equipment) is $150,000 or more. It excludes public works contracts and, per the definition in GBL 756, one-, two- and three-family dwellings, residential tract developments of 100 or fewer one- or two-family homes, residential projects of 4,500 sq ft or less, and certain subsidized residential projects under 75 units. ([N.Y. Gen. Bus. Law 756, 756-a, 756-b, 757](https://www.nysenate.gov/legislation/laws/GBS/756-A)) |
| Owner pays the GC within | 30 days not later than 30 days after the owner approves the invoice; the owner must approve or disapprove (in writing, with reasons) within 12 business days after delivery of the invoice and all contractually required documentation. If payment depends on lender approval, due 7 days after the owner receives good funds (756-a(3)(a)(iii), subject to the lender-failure exception in 756-d). ([N.Y. Gen. Bus. Law 756, 756-a, 756-b, 757](https://www.nysenate.gov/legislation/laws/GBS/756-A)) |
| GC pays each sub within | 7 days 7 days after the contractor or subcontractor receives good funds for each interim or final payment, provided all contractually required documentation and waivers are received; the contractor must also approve or disapprove a sub's invoice within 12 business days ([N.Y. Gen. Bus. Law 756, 756-a, 756-b, 757](https://www.nysenate.gov/legislation/laws/GBS/756-A)) |
| Flows down to sub-tiers | Yes ([N.Y. Gen. Bus. Law 756, 756-a, 756-b, 757](https://www.nysenate.gov/legislation/laws/GBS/756-A)) |
| Interest on late payment | one percent per month or fraction of a month on the unpaid balance, from the day after the due date, or a higher rate consistent with the construction contract ([N.Y. Gen. Bus. Law 756, 756-a, 756-b, 757](https://www.nysenate.gov/legislation/laws/GBS/756-A)) |

## Prompt payment on public jobs

| Rule | New York law |
|---|---|
| Agency pays the prime within | 30 days State agencies: 30 calendar days (excluding legal holidays) after receipt of an invoice, 15 days for a qualifying small business that invoices electronically and asks for expedited payment, and 75 days for final payments on highway construction contracts; the agency has 15 days (7 for small business) to tell the contractor about defects, otherwise the clock is reduced (State Finance Law 179-f). Local public owners other than New York City: 'promptly pay' means within 30 days (excluding legal holidays) of receipt of the requisition, or 45 days where an elected official must approve progress payments (General Municipal Law 106-b(1)(a)). If budgeted State funds for the project have not arrived before the 30 or 45 days run out, a local owner's payment (and interest) is not due until 10 days after it receives the State funds (GML 106-b(1)(d)). ([N.Y. State Fin. Law 139-f, 179-f, 179-g; N.Y. Gen. Mun. Law 106-b](https://www.nysenate.gov/legislation/laws/STF/139-F)) |
| Prime pays each sub within | 7 days of receiving payment ([N.Y. State Fin. Law 139-f, 179-f, 179-g; N.Y. Gen. Mun. Law 106-b](https://www.nysenate.gov/legislation/laws/STF/139-F)) |
| Interest on late payment | Owner late to contractor: the tax-overpayment rate set under Tax Law 1096(e), in effect on the date the interest is paid, from the day after the required payment date (SFL 179-g; GML 106-b(1)(c)); not paid if under $10. Contractor late to sub: the rate in GBL 756-b(1)(b), one percent per month or fraction of a month. ([N.Y. State Fin. Law 139-f, 179-f, 179-g; N.Y. Gen. Mun. Law 106-b](https://www.nysenate.gov/legislation/laws/STF/139-F)) |

## When the GC says it hasn't been paid in New York

The private article does not expressly ban pay-if-paid, but it ties your 7 days to the GC's receipt of good funds and requires the GC to tell you, when you sign, the date it is due payment; if it does not disclose that date accurately, it owes you as though the owner had paid on the statutory dates (GBL 756-a(4)). You can ask in writing for the owner to notify you within 5 days of any payment to the GC. On public works, a pay-if-paid clause is invalid once the GC fails to submit a requisition for the remaining balance within 90 days of substantial completion (GML 106-b(2); SFL 139-f(2)).

## After the deadline: what a sub can do in New York

1) Check the dates: owner approval within 12 business days, payment 30 days after approval; GC pay-through within 7 days of good funds. 2) Send a written notice that payment for undisputed invoice amounts has not been received and that you intend to suspend; to the owner and GC for a sub, at least 10 calendar days before suspending (756-b(2)). 3) Demand 1% per month or fraction of a month from the day after the due date. 4) After 15 days from a complaint, you can refer the dispute to the American Arbitration Association for expedited arbitration, which the contract cannot take away (756-b(3); 757(3)). 5) Track separate Lien Law and bond-claim deadlines, including the Lien Law's trust-fund rules.

## New York quirks to know

The private act only applies where the project's aggregate cost is $150,000 or more, and excludes public works, small residential work and some subsidized housing. Interest is per month or fraction of a month, so partial months count whole. Retainage release is keyed to 'final approval of the work', not substantial completion. On State work where performance and payment bonds are dispensed with (small contracts), up to 20% may be retained until completion and acceptance (SFL 137(1), 139-f(4)); otherwise the 5% / 10% rule applies. Local owners waiting on budgeted State funds get until 10 days after the funds arrive (GML 106-b(1)(d)). Public interest is the Tax Law 1096(e) overpayment rate. The 7-day sub rule applies at every tier.

## Worked example: a $48,000 pay app paid late in New York

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 22, 2026 ([N.Y. Gen. Bus. Law 756, 756-a, 756-b, 757](https://www.nysenate.gov/legislation/laws/GBS/756-A)) |
| Paid | July 22, 2026 (30 days late) |
| Interest owed | $473.42 ([N.Y. Gen. Bus. Law 756, 756-a, 756-b, 757](https://www.nysenate.gov/legislation/laws/GBS/756-A)) |

In New York, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. Paid 30 days after that, a $48,000 payment carries $473.42 of interest at 12% a year, simple.

## New York prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/new-york/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 7 days (7 days after the contractor or subcontractor receives good funds for each interim or final payment, provided all contractually required documentation and waivers are received; the contractor must also approve or disapprove a sub's invoice within 12 business days); interest: one percent per month or fraction of a month on the unpaid balance, from the day after the due date, or a higher rate consistent with the construction contract.
- **Private job: owner → GC:** 30 days (not later than 30 days after the owner approves the invoice; the owner must approve or disapprove (in writing, with reasons) within 12 business days after delivery of the invoice and all contractually required documentation. If payment depends on lender approval, due 7 days after the owner receives good funds (756-a(3)(a)(iii), subject to the lender-failure exception in 756-d).); interest: one percent per month or fraction of a month on the unpaid balance, from the day after the due date, or a higher rate consistent with the construction contract.
- **Public job: prime → sub:** 7 days (after the prime is paid); interest: Owner late to contractor: the tax-overpayment rate set under Tax Law 1096(e), in effect on the date the interest is paid, from the day after the required payment date (SFL 179-g; GML 106-b(1)(c)); not paid if under $10. Contractor late to sub: the rate in GBL 756-b(1)(b), one percent per month or fraction of a month..
- **Public job: agency → prime:** 30 days (State agencies: 30 calendar days (excluding legal holidays) after receipt of an invoice, 15 days for a qualifying small business that invoices electronically and asks for expedited payment, and 75 days for final payments on highway construction contracts; the agency has 15 days (7 for small business) to tell the contractor about defects, otherwise the clock is reduced (State Finance Law 179-f). Local public owners other than New York City: 'promptly pay' means within 30 days (excluding legal holidays) of receipt of the requisition, or 45 days where an elected official must approve progress payments (General Municipal Law 106-b(1)(a)). If budgeted State funds for the project have not arrived before the 30 or 45 days run out, a local owner's payment (and interest) is not due until 10 days after it receives the State funds (GML 106-b(1)(d)).); interest: Owner late to contractor: the tax-overpayment rate set under Tax Law 1096(e), in effect on the date the interest is paid, from the day after the required payment date (SFL 179-g; GML 106-b(1)(c)); not paid if under $10. Contractor late to sub: the rate in GBL 756-b(1)(b), one percent per month or fraction of a month..

Calendar days, simple interest (annual rate ÷ 365 per day late).

## New York prompt payment law: questions

### How fast must a New York GC pay a sub after the owner pays?

7 days after the GC receives good funds, as long as the sub has delivered all contractually required documentation and waivers (Gen. Bus. Law 756-a(3)(b)(ii)). On public works it is 7 calendar days after the contractor receives any payment from the public owner (State Fin. Law 139-f(2); Gen. Mun. Law 106-b(2)).

### Can a New York sub stop work for non-payment?

Yes. After written notice to the owner and the GC and 10 calendar days to cure, a subcontractor may suspend without breach when the owner or GC has not paid undisputed amounts on time; clauses saying a party cannot suspend for non-payment are void (Gen. Bus. Law 756-b(2)(b), 757(2)).

## Sources

- [N.Y. Gen. Bus. Law 756, 756-a, 756-b, 757](https://www.nysenate.gov/legislation/laws/GBS/756-A)
- [N.Y. State Fin. Law 139-f, 179-f, 179-g; N.Y. Gen. Mun. Law 106-b](https://www.nysenate.gov/legislation/laws/STF/139-F)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [New York retainage law](https://fynex.ai/construction/retainage/new-york/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- New York
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)