North Carolina prompt payment law for construction: deadlines and interest
North Carolina's private chapter (G.S. 22C) covers only the payment down the chain: a contractor must pay each sub within 7 days of receiving a periodic or final payment, and late sums carry 1% per month or fraction from the eighth day (22C-3, 22C-5). It sets no owner-to-GC deadline. On public jobs, the final balance is due within 45 days after acceptance, certification of completion or use, with 1% per month interest from day 46, and the prime must pay subs within 7 days (G.S. 143-134.1).
Also in North Carolina: retainage law
North Carolina prompt payment calculator: days late and interest
Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from North Carolina law; change them if your contract or the statute's trigger differs.
Clock starts: within seven days of the contractor's or subcontractor's receipt of each periodic or final payment, the full amount received for the sub's work and materials, once the sub has performed under its contract
Statute: one percent (1%) per month or a fraction thereof on the unpaid balance, beginning on the eighth day after receipt of payment by the contractor or subcontractor
- Payment due by
- June 22, 2026
- Days late
- 30
- Interest owed
- $473.42
- Total now owed
- $48,473.42
30 days late at 12% a year.
Statute: N.C. Gen. Stat. 22C-1 to 22C-6
Calendar days and simple interest (12% a year ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.
Prompt payment on private jobs
| Rule | North Carolina law |
|---|---|
| Residential work | Chapter 22C does not apply to residential contractors as defined in G.S. 87-10(1a), to residential improvements exempt from Chapter 83A under G.S. 83A-13(c)(1), or to residential improvements of 12 or fewer units (G.S. 22C-6).N.C. Gen. Stat. 22C-1 to 22C-6 |
| Owner pays the GC within | Not set by statute |
| GC pays each sub within | 7 days within seven days of the contractor's or subcontractor's receipt of each periodic or final payment, the full amount received for the sub's work and materials, once the sub has performed under its contractN.C. Gen. Stat. 22C-1 to 22C-6 |
| Flows down to sub-tiers | YesN.C. Gen. Stat. 22C-1 to 22C-6 |
| Interest on late payment | one percent (1%) per month or a fraction thereof on the unpaid balance, beginning on the eighth day after receipt of payment by the contractor or subcontractorN.C. Gen. Stat. 22C-1 to 22C-6 |
Chapter 22C covers only payments to subcontractors. No North Carolina statute read sets an owner-to-contractor payment deadline or interest on private projects; that is governed by the contract. The chapter has no attorney-fee provision.
Prompt payment on public jobs
| Rule | North Carolina law |
|---|---|
| Agency pays the prime within | 45 days Final balance due prime contractors is paid in full within 45 days after the prime contract is accepted by the owner, certified complete by the architect, engineer or designer, or occupied and used by the owner, whichever happens first; periodic payments follow the contract documents consistent with the section. Applies to public construction contracts let by a board or governing body of State government or any political subdivision, except Department of Transportation contracts under G.S. 136-28.1 (G.S. 143-134.1(a)).N.C. Gen. Stat. 143-134.1(a), (b) |
| Prime pays each sub within | 7 days of receiving paymentN.C. Gen. Stat. 143-134.1(a), (b) |
| Interest on late payment | one percent (1%) per month or fraction thereof, unless a lower rate is agreed: owner to prime from the 46th day after completion/acceptance/occupancy on the final balance, and from the due date on periodic payments; prime to sub from the eighth day after the prime's receipt of payment. Funds for interest on State-owned projects come from the owning agency's current budget.N.C. Gen. Stat. 143-134.1(a), (b) |
When the GC says it hasn't been paid in North Carolina
North Carolina has a plain rule here: payment by the owner to the contractor is not a condition precedent to payment of a subcontractor, and an agreement to the contrary is unenforceable (G.S. 22C-2). A GC cannot hide behind a pay-if-paid clause on a covered private job; its 7 days run from receipt of payment, but the sub's right to be paid is not conditioned on it. On public jobs the same 7-day rule applies on the prime's receipt of payment (143-134.1(b)). Residential jobs of 12 or fewer units are outside Chapter 22C.
After the deadline: what a sub can do in North Carolina
1) Confirm your work was performed in accordance with the subcontract and the GC received a periodic or final payment: the 7 days run from receipt. 2) Send a written demand citing G.S. 22C-3 and 22C-5, or 143-134.1(b) on a public job, with interest at 1% per month or fraction from the eighth day. 3) On a public job, ask the owner for the status of retainage: it must be released within 60 days after the pay request and substantial completion or beneficial occupancy (143-134.1(b1)(4)). 4) Keep lien (G.S. 44A) and bond-claim deadlines in view; they are separate and not covered here.
North Carolina quirks to know
Public retainage has a 50% step-down that needs the surety's written consent, a $150,000 floor below which no retainage is allowed, and line-item early release at 0.5% for structural steel, piling, caisson and demolition trades. Owners can hold up to 2.5 times the value of remaining work, but not for third-party claims or additive change orders. Department of Transportation contracts under G.S. 136-28.1 are outside the section. Early-release trades are paid within 60 days of the sub's request or on the surety's consent, whichever is later. S.L. 2026-9, s. 5.1(c) (H 1123, signed and effective 2026-06-19) raised the no-retainage floor from $100,000 to $150,000 of total project costs. The act has no transition clause; the UNC School of Government reads it as likely not reaching contracts already in place, so a contract signed before 2026-06-19 for $100,000 to $149,999 may still carry up to 5% retainage.
Worked example: a $48,000 pay app paid late in North Carolina
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 22, 2026N.C. Gen. Stat. 22C-1 to 22C-6 |
| Paid | July 22, 2026 (30 days late) |
| Interest owed | $473.42N.C. Gen. Stat. 22C-1 to 22C-6 |
In North Carolina, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. Paid 30 days after that, a $48,000 payment carries $473.42 of interest at 12% a year, simple.
North Carolina prompt payment law: questions
How fast must a North Carolina GC pay its subs?
Within 7 days of receiving each periodic or final payment, with 1% per month or fraction interest beginning the eighth day (G.S. 22C-3 and 22C-5 on private jobs; 143-134.1(b) on public jobs).
Can a North Carolina GC refuse to pay a sub until the owner pays it?
No. Payment by the owner to a contractor is not a condition precedent to payment of a subcontractor, and an agreement to the contrary is unenforceable (G.S. 22C-2). The sub's right to payment follows performance of the subcontract.
Sources
Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.