Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Ohio prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Ohio prompt payment law for construction: deadlines and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

Ohio's prompt-pay statute for GC to sub is R.C. 4113.61: within 10 calendar days after the contractor receives payment from the owner, it pays each sub the percentage of completion the owner allowed, reduced only by contractual retainage and amounts needed to resolve disputed liens or claims. Late payments carry 18% a year from the eleventh day, and a sub may sue after 30 days; the prevailing party gets attorney fees. Public owners must pay approved estimates within 30 days (R.C. 153.14). No Ohio statute read sets an owner-to-GC deadline on private jobs.

## Prompt payment on private jobs

| Rule | Ohio law |
|---|---|
| Residential work | R.C. 4113.61 does not apply to construction or improvement of any single-, two- or three-family detached dwelling houses (4113.61(C)). ([Ohio Rev. Code 4113.61, 4113.62](https://codes.ohio.gov/ohio-revised-code/section-4113.61)) |
| Owner pays the GC within | Not set by statute |
| GC pays each sub within | 10 days within ten calendar days after the contractor receives payment from the owner, if the sub submitted its application in time for the contractor to include it in its own pay request; the contractor pays the sub the percentage of completion of its contract that the owner allowed, and may reduce it by any contractual retainage and withhold amounts necessary to resolve disputed liens or claims ([Ohio Rev. Code 4113.61, 4113.62](https://codes.ohio.gov/ohio-revised-code/section-4113.61)) |
| Flows down to sub-tiers | Yes ([Ohio Rev. Code 4113.61, 4113.62](https://codes.ohio.gov/ohio-revised-code/section-4113.61)) |
| Interest on late payment | eighteen per cent per annum of the payment due, beginning on the eleventh day following the receipt of payment from the owner and ending on the date of full payment; a sub may sue once payment is 30 days past due ([Ohio Rev. Code 4113.61, 4113.62](https://codes.ohio.gov/ohio-revised-code/section-4113.61)) |
| Attorney's fees to the prevailing party | Yes ([Ohio Rev. Code 4113.61, 4113.62](https://codes.ohio.gov/ohio-revised-code/section-4113.61)) |

No Ohio statute read sets a payment deadline from a private owner to its contractor; that is governed by the contract.

## Prompt payment on public jobs

| Rule | Ohio law |
|---|---|
| Agency pays the prime within | 30 days Payment on approved estimates filed with the owner or its representative is due within thirty days (R.C. 153.14). Applies to public improvement contracts of the state, counties, townships, municipal corporations, school districts and other political subdivisions and public boards, commissions and authorities, except as provided in R.C. 5525.19 (Department of Transportation). ([Ohio Rev. Code 153.12, 153.13, 153.14 (as amended by 2025 H.B. 96, eff. 2025-09-30), 4113.61](https://codes.ohio.gov/ohio-revised-code/section-153.14)) |
| Prime pays each sub within | 10 days of receiving payment ([Ohio Rev. Code 153.12, 153.13, 153.14 (as amended by 2025 H.B. 96, eff. 2025-09-30), 4113.61](https://codes.ohio.gov/ohio-revised-code/section-153.14)) |
| Interest on late payment | Owner late (more than 30 days) or making an unauthorized withholding of retainage: interest at the average of the prime rate established at the commercial banks in the city of over 100,000 population nearest the project (153.14); this is in addition to interest on retainage under 153.13. Contractor late to a sub: 18% per annum (4113.61). ([Ohio Rev. Code 153.12, 153.13, 153.14 (as amended by 2025 H.B. 96, eff. 2025-09-30), 4113.61](https://codes.ohio.gov/ohio-revised-code/section-153.14)) |

## When the GC says it hasn't been paid in Ohio

Ohio's 10 days run from the contractor's receipt of payment from the owner, so the statute assumes the GC has been paid. It does not by itself ban pay-if-paid; R.C. 4113.62(E) says a clause making a sub's payment contingent on another person's payment cannot stop the sub from filing a lien or bond claim before the deadlines expire. On public jobs, a sub cannot be paid at a lower rate than the public authority pays the contractor (153.12). Interest, attorney fee and court cost rights cannot be waived (4113.61(D)).

## After the deadline: what a sub can do in Ohio

1) Make sure you submitted your pay application in time for the GC to include it in its request (4113.61(A)(1)). 2) Confirm the date the GC received payment from the owner; ask the owner in writing. 3) Send a written demand citing R.C. 4113.61 with 18% interest from day 11. 4) If still unpaid 30 days after the payment was due, sue; the court awards interest and, to the prevailing party, reasonable attorney fees and costs unless it finds that inequitable (4113.61(B)). 5) Protect your lien or bond-claim rights under R.C. 1311 and 153.56 so waiting does not expire them (4113.62(E)). 6) Public job: payments unpaid 30 days after an approved estimate, or retainage withheld without authority, earn interest at the local commercial prime rate (153.14).

## Ohio quirks to know

The 18% interest and attorney-fee rights in 4113.61 are non-waivable, and apply down every tier and to wages (laborers must be paid within 10 days of payment or retainage). Residential work on single-, two- or three-family detached homes is excluded. The public retainage ceiling is expressed as a floor on payment (96%), not as a 'retainage cap'. Contracts that choose another state's law or venue, or waive surety bond rights, or waive claims on the basis of final payment when notice was received, are void (4113.62). The 4% public ceiling is new: 2025 H.B. 96 (effective 2025-09-30) replaced the old 8%-to-50%-then-zero labor retainage, deleted the retainage escrow account, and added the rule that no sub may be paid at a lower rate than the prime. Material deliveries are still paid at 92% until incorporated, per law-firm summaries of the act.

## Worked example: a $48,000 pay app paid late in Ohio

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 25, 2026 ([Ohio Rev. Code 4113.61, 4113.62](https://codes.ohio.gov/ohio-revised-code/section-4113.61)) |
| Paid | July 25, 2026 (30 days late) |
| Interest owed | $710.14 ([Ohio Rev. Code 4113.61, 4113.62](https://codes.ohio.gov/ohio-revised-code/section-4113.61)) |

In Ohio, a GC paid by the owner has to pay the sub within 10 days: with the clock starting June 15, 2026, payment is due by June 25, 2026. Paid 30 days after that, a $48,000 payment carries $710.14 of interest at 18% a year, simple.

## Ohio prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/ohio/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 10 days (within ten calendar days after the contractor receives payment from the owner, if the sub submitted its application in time for the contractor to include it in its own pay request; the contractor pays the sub the percentage of completion of its contract that the owner allowed, and may reduce it by any contractual retainage and withhold amounts necessary to resolve disputed liens or claims); interest: eighteen per cent per annum of the payment due, beginning on the eleventh day following the receipt of payment from the owner and ending on the date of full payment; a sub may sue once payment is 30 days past due.
- **Private job: owner → GC:** no statutory deadline; interest: eighteen per cent per annum of the payment due, beginning on the eleventh day following the receipt of payment from the owner and ending on the date of full payment; a sub may sue once payment is 30 days past due.
- **Public job: prime → sub:** 10 days (after the prime is paid); interest: Owner late (more than 30 days) or making an unauthorized withholding of retainage: interest at the average of the prime rate established at the commercial banks in the city of over 100,000 population nearest the project (153.14); this is in addition to interest on retainage under 153.13. Contractor late to a sub: 18% per annum (4113.61)..
- **Public job: agency → prime:** 30 days (Payment on approved estimates filed with the owner or its representative is due within thirty days (R.C. 153.14). Applies to public improvement contracts of the state, counties, townships, municipal corporations, school districts and other political subdivisions and public boards, commissions and authorities, except as provided in R.C. 5525.19 (Department of Transportation).); interest: Owner late (more than 30 days) or making an unauthorized withholding of retainage: interest at the average of the prime rate established at the commercial banks in the city of over 100,000 population nearest the project (153.14); this is in addition to interest on retainage under 153.13. Contractor late to a sub: 18% per annum (4113.61)..

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Ohio prompt payment law: questions

### How soon must an Ohio GC pay a subcontractor?

Within ten calendar days after the contractor receives payment from the owner, if the sub submitted its application in time to be included in the contractor's request (R.C. 4113.61(A)(1)). The same 10 days applies at each lower tier.

## Sources

- [Ohio Rev. Code 4113.61, 4113.62](https://codes.ohio.gov/ohio-revised-code/section-4113.61)
- [Ohio Rev. Code 153.12, 153.13, 153.14 (as amended by 2025 H.B. 96, eff. 2025-09-30), 4113.61](https://codes.ohio.gov/ohio-revised-code/section-153.14)

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [Ohio retainage law](https://fynex.ai/construction/retainage/ohio/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- Ohio
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)