Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Oklahoma prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Oklahoma prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Public jobs over $25,000: the owner pays within 30 calendar days of a proper invoice, giving written reasons within 14 days if it cuts the invoice; the prime pays subs within 10 days of receipt, and sub-subs are paid within 7 days (61 O.S. 223, 224). Late payment to a sub bears 1.5% a month. Private jobs: the owner states the payment frequency and days in the bid documents; if not, monthly payments are due in 28 days, and the prime pays subs within 10 days of the owner's payment (15 O.S. 820). Private late payments carry no statutory interest.

## Prompt payment on private jobs

| Rule | Oklahoma law |
|---|---|
| Residential work | The act does not apply to any contract relating to a single-, two-, three- or four-family dwelling (15 O.S. 821(A)). ([15 O.S. 820, 821](https://www.oscn.net/applications/oscn/DeliverDocument.asp?CiteID=458619)) |
| Owner pays the GC within | 28 days on private bid projects the owner must state in the plans and specifications the payment frequency and the number of days to pay after receipt of billing; if the owner does not, monthly progress payments are due within 28 calendar days after receipt of billing. Private negotiated projects are not covered by the owner-payment default; the contractor must tell subs its payment frequency and a specific day of the month. ([15 O.S. 820, 821](https://www.oscn.net/applications/oscn/DeliverDocument.asp?CiteID=458619)) |
| GC pays each sub within | 10 days within ten calendar days of payment from the owner, or as otherwise agreed by the parties; payment may be reduced as provided in the subcontract ([15 O.S. 820, 821](https://www.oscn.net/applications/oscn/DeliverDocument.asp?CiteID=458619)) |
| Interest on late payment | none: 15 O.S. 820 sets no interest for late payment on private projects ([15 O.S. 820, 821](https://www.oscn.net/applications/oscn/DeliverDocument.asp?CiteID=458619)) |

## Prompt payment on public jobs

| Rule | Oklahoma law |
|---|---|
| Agency pays the prime within | 30 days On construction contracts over $25,000, the owner (state entity, municipality, township, public trust or instrumentality) makes progress payments for work performed and materials properly stored within thirty calendar days after a proper invoice is submitted (61 O.S. 223(A), Fair Pay for Construction Act). The owner may reduce an invoice only by an amount reasonable to correct the work, with written reasons sent within 14 calendar days of receipt; a prime or sub that cuts a lower tier's proper invoice must send written reasons within 7 calendar days, and must tell affected lower tiers within 7 days when its own invoice was cut (reductions under 1% or for math errors are exempt) (223(B), (C)). Highway, railroad and turnpike construction are excluded, and so (with exceptions) are roads, bridges, utilities, traffic control, drainage, sanitary sewer and waterline construction, and contracts for one- to four-family dwellings (227). ([61 O.S. 222, 223, 224, 225, 227, 113.3; 62 O.S. 34.72](https://www.oscn.net/applications/oscn/DeliverDocument.asp?CiteID=442368)) |
| Prime pays each sub within | 10 days of receiving payment ([61 O.S. 222, 223, 224, 225, 227, 113.3; 62 O.S. 34.72](https://www.oscn.net/applications/oscn/DeliverDocument.asp?CiteID=442368)) |
| Interest on late payment | Owner late to prime: interest under 62 O.S. 41.4b, now renumbered 62 O.S. 34.72: an annualized rate based on the average interest rate for 30-day time deposits of state funds in the last calendar quarter of the preceding fiscal year, as reported by the State Treasurer (variable; no number is printed in the statute). No interest is owed to a sub whose prime already paid it; a timely sub payment made after the prime received interest carries the same rate. Prime late to sub: one and one-half percent (1 1/2%) per month (61 O.S. 225(E)). Prime may suspend work or terminate if not properly paid within 49 days of a proper invoice, on 7 days' written notice to the owner (225(A)). Final payment: 1.5% per month for awarding agencies other than school districts, 3/4% per month for school districts, starting 30 days after completion and acceptance on lump-sum contracts (60 days on unit-price contracts) (61 O.S. 113.3). ([61 O.S. 222, 223, 224, 225, 227, 113.3; 62 O.S. 34.72](https://www.oscn.net/applications/oscn/DeliverDocument.asp?CiteID=442368)) |

## When the GC says it hasn't been paid in Oklahoma

Oklahoma's 10-day and 7-day pass-through clocks start when the prime or sub receives 'its corresponding payment' (61 O.S. 224). If the owner paid the prime, the 10 days have run; if the owner has not, a public prime can suspend work or terminate after 49 days (225(A)), and a sub is protected from owner-side interest only if the prime already paid it. The statutes do not mention pay-if-paid clauses; a contract provision that disallows or alters a sub's rights under the act is void (227(B)(2)).

## After the deadline: what a sub can do in Oklahoma

1) Confirm the invoice was a 'proper invoice' and the date the prime received its corresponding payment. 2) Send a written demand citing 61 O.S. 224 and the 1.5%-per-month interest rate in 225(E). 3) On a private job, give 10 calendar days' written notice by certified mail before suspending work after payment is more than 10 days late (15 O.S. 820(C)). 4) On a public job, ask the owner about retainage release at the 21-day mark after the certificate of substantial completion (226(C)). 5) Claims against the bond for public work, and mechanic's lien deadlines, are separate; check Title 61 bond provisions and Title 42.

## Oklahoma quirks to know

Section 113.1 exists in two co-existing 2022 versions (HB 4080 and SB 1520) with different wording on the 50% step-down; section 226 matches the SB 1520 wording. The Fair Pay for Construction Act excludes highway, railroad and turnpike construction, and one- to four-family dwelling contracts; the private-project statute (15 O.S. 820) also excludes one- to four-family dwellings (821(A)). A prime may suspend work or terminate on a public job 49 days after a proper invoice if unpaid. School districts pay 3/4% per month on late final payments instead of 1.5%. The Act voids out-of-state law and venue clauses (227(B)(1)).

## Worked example: a $48,000 pay app paid late in Oklahoma

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 25, 2026 ([15 O.S. 820, 821](https://www.oscn.net/applications/oscn/DeliverDocument.asp?CiteID=458619)) |
| Paid | July 25, 2026 (30 days late) |
| Interest owed | No fixed statutory rate |

In Oklahoma, a GC paid by the owner has to pay the sub within 10 days: with the clock starting June 15, 2026, payment is due by June 25, 2026. The statutory rate moves with an index ("none: 15 O.S. 820 sets no interest for late payment on private projects"), so enter the current figure in the calculator.

## Oklahoma prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/oklahoma/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 10 days (within ten calendar days of payment from the owner, or as otherwise agreed by the parties; payment may be reduced as provided in the subcontract); interest: none: 15 O.S. 820 sets no interest for late payment on private projects.
- **Private job: owner → GC:** 28 days (on private bid projects the owner must state in the plans and specifications the payment frequency and the number of days to pay after receipt of billing; if the owner does not, monthly progress payments are due within 28 calendar days after receipt of billing. Private negotiated projects are not covered by the owner-payment default; the contractor must tell subs its payment frequency and a specific day of the month.); interest: none: 15 O.S. 820 sets no interest for late payment on private projects.
- **Public job: prime → sub:** 10 days (after the prime is paid); interest: Owner late to prime: interest under 62 O.S. 41.4b, now renumbered 62 O.S. 34.72: an annualized rate based on the average interest rate for 30-day time deposits of state funds in the last calendar quarter of the preceding fiscal year, as reported by the State Treasurer (variable; no number is printed in the statute). No interest is owed to a sub whose prime already paid it; a timely sub payment made after the prime received interest carries the same rate. Prime late to sub: one and one-half percent (1 1/2%) per month (61 O.S. 225(E)). Prime may suspend work or terminate if not properly paid within 49 days of a proper invoice, on 7 days' written notice to the owner (225(A)). Final payment: 1.5% per month for awarding agencies other than school districts, 3/4% per month for school districts, starting 30 days after completion and acceptance on lump-sum contracts (60 days on unit-price contracts) (61 O.S. 113.3)..
- **Public job: agency → prime:** 30 days (On construction contracts over $25,000, the owner (state entity, municipality, township, public trust or instrumentality) makes progress payments for work performed and materials properly stored within thirty calendar days after a proper invoice is submitted (61 O.S. 223(A), Fair Pay for Construction Act). The owner may reduce an invoice only by an amount reasonable to correct the work, with written reasons sent within 14 calendar days of receipt; a prime or sub that cuts a lower tier's proper invoice must send written reasons within 7 calendar days, and must tell affected lower tiers within 7 days when its own invoice was cut (reductions under 1% or for math errors are exempt) (223(B), (C)). Highway, railroad and turnpike construction are excluded, and so (with exceptions) are roads, bridges, utilities, traffic control, drainage, sanitary sewer and waterline construction, and contracts for one- to four-family dwellings (227).); interest: Owner late to prime: interest under 62 O.S. 41.4b, now renumbered 62 O.S. 34.72: an annualized rate based on the average interest rate for 30-day time deposits of state funds in the last calendar quarter of the preceding fiscal year, as reported by the State Treasurer (variable; no number is printed in the statute). No interest is owed to a sub whose prime already paid it; a timely sub payment made after the prime received interest carries the same rate. Prime late to sub: one and one-half percent (1 1/2%) per month (61 O.S. 225(E)). Prime may suspend work or terminate if not properly paid within 49 days of a proper invoice, on 7 days' written notice to the owner (225(A)). Final payment: 1.5% per month for awarding agencies other than school districts, 3/4% per month for school districts, starting 30 days after completion and acceptance on lump-sum contracts (60 days on unit-price contracts) (61 O.S. 113.3)..

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Oklahoma prompt payment law: questions

### How fast must an Oklahoma owner pay on a public job?

Within 30 calendar days after a proper invoice on construction contracts over $25,000; written reasons for any cut are due within 14 days (61 O.S. 223).

### How soon must an Oklahoma GC pay subs?

Ten calendar days after the prime receives its corresponding payment on public work (61 O.S. 224(A)); on private bid projects, ten calendar days of payment from the owner unless otherwise agreed (15 O.S. 820).

### What interest applies to late payments in Oklahoma?

On public work, a prime that fails to pay a sub on time pays 1.5% per month (61 O.S. 225(E)); late final payment by an awarding agency also bears 1.5% per month, or 3/4% for school districts (113.3). On private work the statute provides no interest penalty.

## Sources

- [15 O.S. 820, 821](https://www.oscn.net/applications/oscn/DeliverDocument.asp?CiteID=458619)
- [61 O.S. 222, 223, 224, 225, 227, 113.3; 62 O.S. 34.72](https://www.oscn.net/applications/oscn/DeliverDocument.asp?CiteID=442368)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Oklahoma retainage law](https://fynex.ai/construction/retainage/oklahoma/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- Oklahoma
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)