Oregon prompt payment law for construction: deadlines and interest

Private jobs run on 14 days and 7 days: the owner pays progress billings within 14 days of receipt, and final payment within 7 days after approving the work; the contractor pays subs within 7 days after it is paid (ORS 701.625, 701.630). Late amounts bear 1.5% per month or fraction, and the prevailing party gets attorney fees. Public improvements: contracts must require the prime to pay first-tier subs within 10 days out of amounts the agency pays it, with 9% interest if not paid within 30 days of receipt (279C.580, 279C.515); the agency's own interest on progress payments starts 30 days after invoice or 15 days after approval (279C.570).

Also in Oregon: retainage law

Oregon prompt payment calculator: days late and interest

Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from Oregon law; change them if your contract or the statute's trigger differs.

Which clock

Clock starts: no later than 7 days after the original contractor receives payment from the owner for the sub's work (original sub to its subs and suppliers: 7 days after its own receipt); the sub must have provided a billing or invoice and an appropriate lien waiver

Statute: one and one-half percent a month or fraction of a month on the unpaid balance, or a higher agreed rate (owner to contractor: ORS 701.625(11); contractor to sub: from the eighth day after receipt of payment, 701.630(6))

Payment due by
June 22, 2026
Days late
30
Interest owed
$710.14
Total now owed
$48,710.14

30 days late at 18% a year.

Statute: ORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645

Calendar days and simple interest (18% a year ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Prompt payment on private jobs

RuleOregon law
Residential workORS 701.620 to 701.640 do not apply to a contract for a building subject to the Low-Rise Residential Dwelling Code, to public contracts under ORS chapter 279C (and 279A, 279B, 279.835 to 279.855), or to housing where all or part of the units are reserved for renters at or below 80% of area median income (ORS 701.645).ORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645
Owner pays the GC within14 days progress payments no later than 14 days after the owner receives the billing (jobs expected to take 60 or more days); final payment of all remaining amounts no later than 7 days after the owner approves the work. A billing is deemed certified 10 days after receipt unless the owner issues a written statement of items not approved. Longer periods are allowed only if the drawings and specifications carry the conspicuous 'Notice of Extended Payment Provision' on each page.ORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645
GC pays each sub within7 days no later than 7 days after the original contractor receives payment from the owner for the sub's work (original sub to its subs and suppliers: 7 days after its own receipt); the sub must have provided a billing or invoice and an appropriate lien waiverORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645
Flows down to sub-tiersYesORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645
Written notice to withholdWithin 10 daysORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645
Withholding for a disputeUp to 150% of the disputed amountORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645
Interest on late paymentone and one-half percent a month or fraction of a month on the unpaid balance, or a higher agreed rate (owner to contractor: ORS 701.625(11); contractor to sub: from the eighth day after receipt of payment, 701.630(6))ORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645
Attorney's fees to the prevailing partyYesORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645

Prompt payment on public jobs

RuleOregon law
Agency pays the prime within30 days Contracting agencies make progress payments monthly; interest on the progress payment (not retainage) starts 30 days after receipt of the invoice or 15 days after the payment is approved, whichever is earlier (ORS 279C.570(2)). The agency must notify the contractor of a defective invoice or good-faith dispute within 15 days (279C.570(4)).ORS 279C.515, 279C.570, 279C.580
Prime pays each sub within10 days of receiving paymentORS 279C.515, 279C.570, 279C.580
Interest on late paymentAgency to contractor on progress payments: three times the discount rate on 90-day commercial paper at the Federal Reserve Bank for the Oregon district, set at the earlier of 30 days after invoice receipt or 15 days after approval, capped at 30% (279C.570(2)). Final payment: 1.5% per month from 30 days after completion and acceptance (279C.570(8)). Contractor to sub: 9% per annum (279C.515(2), 279C.580(3)(d)).ORS 279C.515, 279C.570, 279C.580

When the GC says it hasn't been paid in Oregon

Oregon's sub clock is triggered by the contractor receiving the owner's payment for your work, 7 days later on private jobs (701.630(2)) and 10 days later on public ones (279C.580(3)). A GC does not owe interest on a public job if the only reason it did not pay is that it was not paid in turn (279C.580(3)(d)). You can ask the owner in writing to tell you within 5 days after it pays the GC (701.625(12)). A sub that is not paid under 701.630(2) may suspend work on 3 days' written notice to the contractor and owner (701.635(2)).

After the deadline: what a sub can do in Oregon

1) Confirm your billing and lien waiver went to the GC (payment is not required without them, 701.630(2)(b)). 2) Check the date the GC received the owner's payment; on a private job ask the owner under 701.625(12). 3) Send a written demand citing ORS 701.630 and 1.5% per month interest from day 8. 4) Suspend work on written notice if needed (3 days if the owner has not paid certified amounts or you are unpaid under 701.630(2); 7 days if the owner paid but the GC did not) (701.635). 5) The prevailing party in an action to collect interest recovers costs and attorney fees (701.630(7)). 6) On public work, a complaint can go to the Construction Contractors Board for non-payment (279C.515(3)). Lien and bond claim deadlines are separate.

Oregon quirks to know

Oregon reads as one retainage ceiling (5%) shared by private and public work, enforced through the withholding rule that a lower tier cannot hold more than its contract allows. Billings are deemed certified 10 days after receipt unless the owner states reasons in writing. The disputed-amount withholding cap is 150% of the amount in dispute. Surety bonds in lieu of retainage must be accepted on large commercial structures and public improvements, and contractors can recover the added premium from the sub that asks for one. Public agency interest on progress payments floats at three times the 90-day commercial paper discount rate, up to 30%.

Worked example: a $48,000 pay app paid late in Oregon

ClockPrivate job: GC → sub
Clock startsJune 15, 2026
Payment due byJune 22, 2026ORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645
PaidJuly 22, 2026 (30 days late)
Interest owed$710.14ORS 701.620, 701.625, 701.630, 701.635, 701.640, 701.645

In Oregon, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. Paid 30 days after that, a $48,000 payment carries $710.14 of interest at 18% a year, simple.

Run a payment like this in the split calculator

Oregon prompt payment law: questions

How soon must an Oregon owner pay a contractor on a private job?

Progress payments no later than 14 days after the owner receives the billing, and final payment no later than 7 days after the owner approves the work, unless the drawings and specifications carry the conspicuous extended-payment notice (ORS 701.625(3)). Late payment bears 1.5% per month or fraction of a month (701.625(11)).

How soon must an Oregon GC pay subs?

No later than 7 days after the original contractor receives payment from the owner for the sub's work (ORS 701.630(2)); interest at 1.5% a month or fraction starts the eighth day, and the prevailing party gets costs and attorney fees (701.630(6), (7)). On public jobs the contract must require payment within 10 days of the agency's payment to the contractor (ORS 279C.580(3)).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.