Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Pennsylvania prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Pennsylvania prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

The Contractor and Subcontractor Payment Act sets the private-job clocks: the owner pays within 20 days after the billing period ends or the invoice is delivered, and the contractor pays a sub within 14 days of receiving payment or the sub's invoice, whichever is later (73 P.S. §§505(c), 507(c)). Interest is 1% per month starting after a 7-day grace period for owners and the next day for contractors. Public agencies pay within 45 calendar days of a payment application by default, and prime contractors pay subs within 14 days of receiving a progress payment (62 Pa.C.S. §§3932-3933).

## Prompt payment on private jobs

| Rule | Pennsylvania law |
|---|---|
| Residential work | Yes. The Act does not apply to construction contracts for six or fewer residential units under construction simultaneously, nor to a person buying materials for work on his or her own property (73 P.S. §503). ([73 P.S. §§501-516 (Contractor and Subcontractor Payment Act, 1994 Act 7, §§2-12)](https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=PDF&SessYr=1994&ActNum=0007.&SessInd=0)) |
| Owner pays the GC within | 20 days after the billing period ends or after delivery of the invoice, whichever is later, unless the parties agree otherwise ([73 P.S. §§501-516 (Contractor and Subcontractor Payment Act, 1994 Act 7, §§2-12)](https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=PDF&SessYr=1994&ActNum=0007.&SessInd=0)) |
| GC pays each sub within | 14 days after receipt of each progress or final payment or of the sub's invoice, whichever is later, for the amount received for the sub's work; the contractor must also disclose the owner's payment due date before the subcontract is signed ([73 P.S. §§501-516 (Contractor and Subcontractor Payment Act, 1994 Act 7, §§2-12)](https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=PDF&SessYr=1994&ActNum=0007.&SessInd=0)) |
| Flows down to sub-tiers | Yes ([73 P.S. §§501-516 (Contractor and Subcontractor Payment Act, 1994 Act 7, §§2-12)](https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=PDF&SessYr=1994&ActNum=0007.&SessInd=0)) |
| Written notice to withhold | Within 14 days ([73 P.S. §§501-516 (Contractor and Subcontractor Payment Act, 1994 Act 7, §§2-12)](https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=PDF&SessYr=1994&ActNum=0007.&SessInd=0)) |
| Interest on late payment | 1% per month or fraction of a month on the balance due, starting on the 8th day after the payment due date (owner, 73 P.S. §505(d); 'except as otherwise agreed by the parties'), or the day after the 14-day due date (contractor to sub, §507(d) by reference to §505(d)). Added penalty of 1% per month on amounts wrongfully withheld, awarded in arbitration or litigation (§512(a)) ([73 P.S. §§501-516 (Contractor and Subcontractor Payment Act, 1994 Act 7, §§2-12)](https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=PDF&SessYr=1994&ActNum=0007.&SessInd=0)) |
| Attorney's fees to the prevailing party | Yes ([73 P.S. §§501-516 (Contractor and Subcontractor Payment Act, 1994 Act 7, §§2-12)](https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=PDF&SessYr=1994&ActNum=0007.&SessInd=0)) |

## Prompt payment on public jobs

| Rule | Pennsylvania law |
|---|---|
| Agency pays the prime within | 45 days If the contract sets no payment time, the government agency pays a progress application, less retainage, within 45 calendar days of receiving it (62 Pa.C.S. §3932(b)). Chapter 39 covers construction contracts over $50,000 let by competitive sealed bidding or proposals by Commonwealth agencies, State-aided institutions and local government units (counties, cities, boroughs, townships, school districts, authorities); it excludes PennDOT contracts under §301(c)(1), distressed municipalities and school districts, Philadelphia PICA entities and metropolitan transportation authorities (§§3901, 3902, 3938(b)). The 45-day rule is suspended where nonpayment is caused by a missing state budget or by federal or state funds not paid to the agency (§3938(a)). ([62 Pa.C.S. §§3931-3935](https://www.palegis.us/statutes/consolidated/view-statute?txtType=PDF&ttl=62&div=00.&chpt=39)) |
| Prime pays each sub within | 14 days of receiving payment ([62 Pa.C.S. §§3931-3935](https://www.palegis.us/statutes/consolidated/view-statute?txtType=PDF&ttl=62&div=00.&chpt=39)) |
| Interest on late payment | Interest on a late progress payment at the rate the Secretary of Revenue sets for overdue taxes and tax refunds under sections 806 and 806.1 of The Fiscal Code (62 Pa.C.S. §3932(c)), 'except as otherwise agreed'; variable, no number in the statute; no interest if paid by the 15th calendar day after the due date where the contract has no grace period (§§3932(d), 3933(e)). A tribunal may add a penalty of 1% per month on amounts withheld in bad faith (arbitrary or vexatious), and may award attorney fees on the same bad-faith finding (§3935). ([62 Pa.C.S. §§3931-3935](https://www.palegis.us/statutes/consolidated/view-statute?txtType=PDF&ttl=62&div=00.&chpt=39)) |

## When the GC says it hasn't been paid in Pennsylvania

Pennsylvania's Act ties a GC's duty to pay a sub to what the GC received, but does not make owner payment a condition precedent in the text read. The GC must disclose the owner's payment due date before the subcontract is signed; if it discloses it wrongly, it owes payment as though the owner had paid on time, except for delays outside its control such as change orders or weather (73 P.S. §507(b)). A GC may withhold for good-faith claims only if it gives the sub and owner written notice within the contract period or 14 calendar days, otherwise it waives the right (§511(b)). Pay-if-paid case law was not reviewed.

## After the deadline: what a sub can do in Pennsylvania

Once 14 days pass after the GC's receipt of payment (or retainage), send a written demand citing 73 P.S. §507 or §509 for the amount plus 1% per month interest. If the sub is still unpaid 30 days after the end of the billing period, it can send written notice by email or mail, wait 30 more days, then give at least 10 days' certified-mail notice to the owner and suspend work without penalty (§507(e)). In arbitration or litigation the tribunal adds a penalty of 1% per month on wrongly withheld amounts, and the substantially prevailing party recovers a reasonable attorney fee (§512). On public jobs the equivalents are 62 Pa.C.S. §§3933 and 3935, with a bad-faith standard for the penalty and fees.

## Pennsylvania quirks to know

The private Act cannot be waived by contract unless it says so (73 P.S. §503(c)) and does not cover projects of six or fewer residential units under construction at once. The public Procurement Code penalty and attorney fees require bad faith ('arbitrary or vexatious'), while the private Act's penalty and fees apply simply when the payment terms were not met and the withholding was not reasonably related to a good-faith claim (§512). Public retainage steps down at 50% completion: half of what was held is returned. A subcontractor's retainage clock follows final acceptance (30 days), not substantial completion, unless it posts the 120% maintenance bond. The public chapter covers only contracts over $50,000 and excludes PennDOT, distressed municipalities and school districts, Philadelphia PICA entities and transit authorities; a public project cannot be certified substantially complete until 90% of the work is done (62 Pa.C.S. §§3902, 3938).

## Worked example: a $48,000 pay app paid late in Pennsylvania

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 29, 2026 ([73 P.S. §§501-516 (Contractor and Subcontractor Payment Act, 1994 Act 7, §§2-12)](https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=PDF&SessYr=1994&ActNum=0007.&SessInd=0)) |
| Paid | July 29, 2026 (30 days late) |
| Interest owed | $473.42 ([73 P.S. §§501-516 (Contractor and Subcontractor Payment Act, 1994 Act 7, §§2-12)](https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=PDF&SessYr=1994&ActNum=0007.&SessInd=0)) |

In Pennsylvania, a GC paid by the owner has to pay the sub within 14 days: with the clock starting June 15, 2026, payment is due by June 29, 2026. Paid 30 days after that, a $48,000 payment carries $473.42 of interest at 12% a year, simple.

## Pennsylvania prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/pennsylvania/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 14 days (after receipt of each progress or final payment or of the sub's invoice, whichever is later, for the amount received for the sub's work; the contractor must also disclose the owner's payment due date before the subcontract is signed); interest: 1% per month or fraction of a month on the balance due, starting on the 8th day after the payment due date (owner, 73 P.S. §505(d); 'except as otherwise agreed by the parties'), or the day after the 14-day due date (contractor to sub, §507(d) by reference to §505(d)). Added penalty of 1% per month on amounts wrongfully withheld, awarded in arbitration or litigation (§512(a)).
- **Private job: owner → GC:** 20 days (after the billing period ends or after delivery of the invoice, whichever is later, unless the parties agree otherwise); interest: 1% per month or fraction of a month on the balance due, starting on the 8th day after the payment due date (owner, 73 P.S. §505(d); 'except as otherwise agreed by the parties'), or the day after the 14-day due date (contractor to sub, §507(d) by reference to §505(d)). Added penalty of 1% per month on amounts wrongfully withheld, awarded in arbitration or litigation (§512(a)).
- **Public job: prime → sub:** 14 days (after the prime is paid); interest: Interest on a late progress payment at the rate the Secretary of Revenue sets for overdue taxes and tax refunds under sections 806 and 806.1 of The Fiscal Code (62 Pa.C.S. §3932(c)), 'except as otherwise agreed'; variable, no number in the statute; no interest if paid by the 15th calendar day after the due date where the contract has no grace period (§§3932(d), 3933(e)). A tribunal may add a penalty of 1% per month on amounts withheld in bad faith (arbitrary or vexatious), and may award attorney fees on the same bad-faith finding (§3935)..
- **Public job: agency → prime:** 45 days (If the contract sets no payment time, the government agency pays a progress application, less retainage, within 45 calendar days of receiving it (62 Pa.C.S. §3932(b)). Chapter 39 covers construction contracts over $50,000 let by competitive sealed bidding or proposals by Commonwealth agencies, State-aided institutions and local government units (counties, cities, boroughs, townships, school districts, authorities); it excludes PennDOT contracts under §301(c)(1), distressed municipalities and school districts, Philadelphia PICA entities and metropolitan transportation authorities (§§3901, 3902, 3938(b)). The 45-day rule is suspended where nonpayment is caused by a missing state budget or by federal or state funds not paid to the agency (§3938(a)).); interest: Interest on a late progress payment at the rate the Secretary of Revenue sets for overdue taxes and tax refunds under sections 806 and 806.1 of The Fiscal Code (62 Pa.C.S. §3932(c)), 'except as otherwise agreed'; variable, no number in the statute; no interest if paid by the 15th calendar day after the due date where the contract has no grace period (§§3932(d), 3933(e)). A tribunal may add a penalty of 1% per month on amounts withheld in bad faith (arbitrary or vexatious), and may award attorney fees on the same bad-faith finding (§3935)..

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Pennsylvania prompt payment law: questions

### How long does a Pennsylvania owner have to pay a contractor?

Twenty days after the billing period ends or the invoice is delivered, whichever is later, unless the parties agree otherwise. Interest of 1% per month starts on the 8th day after that due date (73 P.S. §505(c)-(d)).

### How soon must a Pennsylvania GC pay a sub?

Fourteen days after receiving each progress or final payment, or the sub's invoice, whichever is later (73 P.S. §507(c)). Late payment accrues interest from the next day at the §505(d) rate.

### Can I suspend work in Pennsylvania if the GC does not pay?

Yes, after the conditions in 73 P.S. §507(e)(2) are met: payment is late, 30 days have passed since the end of the unpaid billing period with written notice sent, 30 days have passed since that notice, and the sub has given the owner at least 10 days' certified-mail notice.

## Sources

- [73 P.S. §§501-516 (Contractor and Subcontractor Payment Act, 1994 Act 7, §§2-12)](https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?txtType=PDF&SessYr=1994&ActNum=0007.&SessInd=0)
- [62 Pa.C.S. §§3931-3935](https://www.palegis.us/statutes/consolidated/view-statute?txtType=PDF&ttl=62&div=00.&chpt=39)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Pennsylvania retainage law](https://fynex.ai/construction/retainage/pennsylvania/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- Pennsylvania
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)