Construction · Prompt payment law

South Carolina prompt payment law for construction: deadlines and interest

South Carolina's Prompt Pay Act sets 21 days for the owner to pay the GC an undisputed pay request and 7 days for the GC, and each sub in turn, to pay the full amount received for a lower tier's work (S.C. Code §29-6-30). Late amounts bear 1% a month or pro rata fraction from the due date, but only if the payer was told of the section when the payment request was made (§29-6-50). The Act's 'owner' includes state and local governments, and it carves out residential homebuilders, small residential projects and self-financed private owners (§29-6-60).

Also in South Carolina: retainage law

South Carolina prompt payment calculator: days late and interest

Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from South Carolina law; change them if your contract or the statute's trigger differs.

Which clock

Clock starts: after the contractor or subcontractor receives each periodic or final payment; pay the full amount received for the sub's work and materials

Statute: One percent a month or a pro rata fraction on the unpaid balance, from the due date; no interest is due unless the payer was notified of the section when the payment request was made

Payment due by
June 22, 2026
Days late
30
Interest owed
$473.42
Total now owed
$48,473.42

30 days late at 12% a year.

Statute: S.C. Code §§29-6-10, 29-6-30, 29-6-40, 29-6-50, 29-6-60, 29-6-230

Calendar days and simple interest (12% a year ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Prompt payment on private jobs

RuleSouth Carolina law
Residential workYes. The Act does not apply to residential homebuilders, to improvements intended for residential purposes with 16 or fewer units, or to private owners whose improvements are not financed by a non-owner (S.C. Code §29-6-60).S.C. Code §§29-6-10, 29-6-30, 29-6-40, 29-6-50, 29-6-60, 29-6-230
Owner pays the GC within21 days after the owner receives a pay request based on work completed or service provided (undisputed amount, mailed first class or delivered)S.C. Code §§29-6-10, 29-6-30, 29-6-40, 29-6-50, 29-6-60, 29-6-230
GC pays each sub within7 days after the contractor or subcontractor receives each periodic or final payment; pay the full amount received for the sub's work and materialsS.C. Code §§29-6-10, 29-6-30, 29-6-40, 29-6-50, 29-6-60, 29-6-230
Flows down to sub-tiersYesS.C. Code §§29-6-10, 29-6-30, 29-6-40, 29-6-50, 29-6-60, 29-6-230
Interest on late paymentOne percent a month or a pro rata fraction on the unpaid balance, from the due date; no interest is due unless the payer was notified of the section when the payment request was madeS.C. Code §§29-6-10, 29-6-30, 29-6-40, 29-6-50, 29-6-60, 29-6-230

Prompt payment on public jobs

RuleSouth Carolina law
Agency pays the prime within21 daysS.C. Code §§29-6-10(4), 29-6-30, 29-6-50; 11-35-45; 11-35-3030(4)(b)
Prime pays each sub within7 days of receiving paymentS.C. Code §§29-6-10(4), 29-6-30, 29-6-50; 11-35-45; 11-35-3030(4)(b)
Interest on late paymentConstruction pay requests: 1% a month or pro rata fraction (§29-6-50), same notice condition. Separate state-agency voucher rule for supplies and services: 30 work days, then interest up to 15% a year (§11-35-45)S.C. Code §§29-6-10(4), 29-6-30, 29-6-50; 11-35-45; 11-35-3030(4)(b)

When the GC says it hasn't been paid in South Carolina

Pay-if-paid is void for construction subs in South Carolina. Under the Subcontractors' and Suppliers' Payment Protection Act, payment by the owner to the contractor, or by the contractor to another sub or supplier, is not a condition precedent to paying the construction sub, and any contrary agreement is not enforceable (S.C. Code §29-6-230). A payer may still withhold for listed causes such as defective work not remedied, disputed work, third-party claims or damage (§29-6-40), so the GC's real defence is a documented dispute, not 'the owner hasn't paid me'.

After the deadline: what a sub can do in South Carolina

Once the 7-day point passes, send a written demand that states the pay request date, the amount received by the GC and the interest accrued, and cite §29-6-30 and §29-6-50. Make sure each payment request carried the interest notice, because no interest is due without it. On a bonded public job, a supplier or sub that is unpaid 90 days after its last work can sue on the payment bond, and a remote claimant must give written notice within 90 days; suit must be filed within one year (§11-35-3030(2)(c)-(d)). Private-job lien deadlines are in S.C. Code Title 29, Chapter 5 and run separately.

South Carolina quirks to know

Interest has a notice trap: the payer owes nothing unless it was notified of §29-6-50 at the time of the payment request, so the statutory text should be on pay apps and invoices. On private projects only, parties can contract for different rates and payment periods if they specifically waive §§29-6-30 and 29-6-50 by section number in conspicuous bold or underlined type. The 3.5% retainage cap sits in the state Procurement Code, which counties, cities and school districts do not automatically follow because each adopts its own procurement law (§11-35-5320). State agencies' own invoice payment rule is a separate 30-work-day clock (§11-35-45).

Worked example: a $48,000 pay app paid late in South Carolina

ClockPrivate job: GC → sub
Clock startsJune 15, 2026
Payment due byJune 22, 2026S.C. Code §§29-6-10, 29-6-30, 29-6-40, 29-6-50, 29-6-60, 29-6-230
PaidJuly 22, 2026 (30 days late)
Interest owed$473.42S.C. Code §§29-6-10, 29-6-30, 29-6-40, 29-6-50, 29-6-60, 29-6-230

In South Carolina, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. Paid 30 days after that, a $48,000 payment carries $473.42 of interest at 12% a year, simple.

Run a payment like this in the split calculator

South Carolina prompt payment law: questions

How many days does an owner have to pay a contractor in South Carolina?

21 days from receipt of a pay request based on work completed, for the undisputed amount (S.C. Code §29-6-30). The owner can be a private party or a state, local or municipal government body (§29-6-10(4)).

How long does a South Carolina GC have to pay a sub after getting paid?

7 days after the contractor receives each periodic or final payment, for the full amount received for the sub's work and materials (S.C. Code §29-6-30). Each sub owes the same to its own subs.

What interest applies to late payments under the South Carolina Prompt Pay Act?

One percent a month, or a pro rata fraction, on the unpaid balance from the due date, but only if the payer was notified of the section when the payment request was made (S.C. Code §29-6-50).

Does the South Carolina Prompt Pay Act cover residential work?

Not for residential homebuilders, for residential improvements with 16 or fewer units, or for private owners whose project is not financed by someone other than the owner (S.C. Code §29-6-60).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.