Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states South Dakota prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# South Dakota prompt payment law for construction: deadlines and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

South Dakota's Prompt Payment Act covers public work only. An agency, which includes the state, counties, municipalities and school districts, must pay on the contract date or, if none is set, within 45 days after receipt and written acceptance of the work and receipt of the invoice (SDCL 5-26-1, 5-26-2). A contractor paid by an agency must pay its subs and suppliers within 30 days of receiving payment (SDCL 5-26-6). Late amounts bear the Category B rate, 10% per year (SDCL 54-3-16). No private-job prompt-pay statute was found.

## Prompt payment on private jobs

**No statute.** No South Dakota statute found that sets payment deadlines for private construction. The South Dakota Prompt Payment Act (SDCL ch. 5-26) binds 'agencies' (the state, counties, municipalities and school districts) and the businesses they contract with, not private owners. Private payment terms and interest come from the contract; the sub's statutory leverage is the mechanics' lien chapter (SDCL ch. 44-9), including the owner's right to withhold from a contractor to protect lien claimants (SDCL 44-9-10).

## Prompt payment on public jobs

| Rule | South Dakota law |
|---|---|
| Agency pays the prime within | 45 days after receipt and written acceptance of the work and receipt of the invoice, unless the contract sets a payment date (SDCL 5-26-2). On public-improvement contracts under ch. 5-18B, final payment is due within 30 days after completion and acceptance (5-18B-14) ([SDCL 5-26-1, 5-26-2, 5-26-3, 5-26-3.1, 5-26-5, 5-26-6; 5-18B-14; 54-3-16](https://sdlegislature.gov/Statutes/5-26)) |
| Prime pays each sub within | 30 days of receiving payment ([SDCL 5-26-1, 5-26-2, 5-26-3, 5-26-3.1, 5-26-5, 5-26-6; 5-18B-14; 54-3-16](https://sdlegislature.gov/Statutes/5-26)) |
| Interest on late payment | Agency: Category B rate (10% per year, SDCL 54-3-16) or the contract rate; no interest under $5. Business to sub or supplier: Category B rate (10% per year) from the 31st day after the business is paid, unless the contract provides otherwise (SDCL 5-26-3, 5-26-3.1, 5-26-6) ([SDCL 5-26-1, 5-26-2, 5-26-3, 5-26-3.1, 5-26-5, 5-26-6; 5-18B-14; 54-3-16](https://sdlegislature.gov/Statutes/5-26)) |

## When the GC says it hasn't been paid in South Dakota

South Dakota's Prompt Payment Act ties the sub's clock to the contractor's own receipt of agency payment: the business must pay the sub within 30 days after it is paid, and interest starts on day 31 (SDCL 5-26-6). Payment is due when the sub 'has satisfied the terms of the contract or material delivery agreement'. The statute does not address what happens when the agency has not paid the prime, or pay-if-paid clauses, on either public or private jobs, so a sub in that situation relies on the contract, the payment bond (SDCL 5-21-1) and any lien on contract funds (SDCL ch. 5-22).

## After the deadline: what a sub can do in South Dakota

On a public job, count 30 days from the date the prime received the agency's payment, then send a written demand for the sub's share plus 10% per year interest from day 31, citing SDCL 5-26-6. If the prime still does not pay, the sub can sue on the bond the prime furnished (SDCL ch. 5-21) or assert a lien on the contract funds still owed under SDCL ch. 5-22, both of which have their own notice and filing deadlines. On a private job, use the contract and the mechanics' lien process in SDCL ch. 44-9, which has separate notice deadlines.

## South Dakota quirks to know

The Act's own dates do not line up: SDCL 5-26-2 allows 45 days, but 5-26-3 says interest starts on the thirtieth day after receipt of the goods or services and invoice. An agency gets an exemption if a dispute exists and it sends written notice of disagreement within 30 days of receipt of the work and invoice (SDCL 5-26-5). No interest under $5 is payable (SDCL 5-26-3.1), and transactions between government agencies are excluded (SDCL 5-26-8). Local governments are in: the definition of 'agency' expressly includes counties, municipalities and public school districts. Public-improvement contracts have their own clock in SDCL 5-18B-14: final payment within 30 days after completion and acceptance, shorter than the Prompt Payment Act's 45-day default. Retainage interest under 5-18B-11 is a floor (not less than 4% a year) rather than a fixed rate, and it also runs on retainage held from progress payments from 30 days after a progress inspection. If the agency occupies the building early it must release all but double the cost to complete, or 1% of the contract price (minimum $300) (5-18B-13).

## Worked example: a $48,000 pay app paid late in South Dakota

| | |
|---|---|
| Clock | Public job: prime → sub |
| Clock starts | June 15, 2026 |
| Payment due by | July 15, 2026 ([SDCL 5-26-1, 5-26-2, 5-26-3, 5-26-3.1, 5-26-5, 5-26-6; 5-18B-14; 54-3-16](https://sdlegislature.gov/Statutes/5-26)) |
| Paid | August 14, 2026 (30 days late) |
| Interest owed | $394.52 ([SDCL 5-26-1, 5-26-2, 5-26-3, 5-26-3.1, 5-26-5, 5-26-6; 5-18B-14; 54-3-16](https://sdlegislature.gov/Statutes/5-26)) |

In South Dakota, a prime paid by the agency has to pay the sub within 30 days: with the clock starting June 15, 2026, payment is due by July 15, 2026. Paid 30 days after that, a $48,000 payment carries $394.52 of interest at 10% a year, simple.

## South Dakota prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/south-dakota/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** no statutory deadline; no fixed statutory interest rate.
- **Private job: owner → GC:** no statutory deadline; no fixed statutory interest rate.
- **Public job: prime → sub:** 30 days (after the prime is paid); interest: Agency: Category B rate (10% per year, SDCL 54-3-16) or the contract rate; no interest under $5. Business to sub or supplier: Category B rate (10% per year) from the 31st day after the business is paid, unless the contract provides otherwise (SDCL 5-26-3, 5-26-3.1, 5-26-6).
- **Public job: agency → prime:** 45 days (after receipt and written acceptance of the work and receipt of the invoice, unless the contract sets a payment date (SDCL 5-26-2). On public-improvement contracts under ch. 5-18B, final payment is due within 30 days after completion and acceptance (5-18B-14)); interest: Agency: Category B rate (10% per year, SDCL 54-3-16) or the contract rate; no interest under $5. Business to sub or supplier: Category B rate (10% per year) from the 31st day after the business is paid, unless the contract provides otherwise (SDCL 5-26-3, 5-26-3.1, 5-26-6).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## South Dakota prompt payment law: questions

### How long does a South Dakota agency have to pay a contractor?

On the contract's payment date or, if none is specified, within 45 days after receipt and written acceptance of the work and receipt of the invoice (SDCL 5-26-2). Interest is the Category B rate, 10% per year.

### How soon must a South Dakota prime pay subs after the agency pays?

Within 30 days after receiving payment from the agency. Interest at the Category B rate accrues from the 31st day unless the contract says otherwise (SDCL 5-26-6).

### Does the South Dakota Prompt Payment Act apply to private construction?

No. It applies to agencies (state, counties, municipalities, school districts) and to businesses paying subs on agency contracts (SDCL 5-26-1, 5-26-6). No private-sector prompt-pay statute was found.

### What interest rate applies to late public payments in South Dakota?

The Category B rate, which is 10% per year under SDCL 54-3-16, or the rate specified by contract. An agency does not have to pay interest of less than $5 (SDCL 5-26-3.1).

## Sources

- [SDCL 5-26-1, 5-26-2, 5-26-3, 5-26-3.1, 5-26-5, 5-26-6; 5-18B-14; 54-3-16](https://sdlegislature.gov/Statutes/5-26)

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [South Dakota retainage law](https://fynex.ai/construction/retainage/south-dakota/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- South Dakota
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)