Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Texas prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Texas prompt payment law for construction: deadlines and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Texas runs two statutory clocks on private jobs. The owner must pay the GC within 35 days after receiving a written payment request, and the GC must pay each sub its share within 7 days after the GC is paid; a sub then owes its own subs within 7 days (Prop. Code §28.002). Unpaid amounts accrue 1.5% a month from the day after the due date. On public jobs the agency's payment is overdue on the 31st day after the later of delivery, completion or invoice, the prime owes its subs within 10 days of receipt, and interest is 1% plus the WSJ prime rate (Gov't Code §§2251.021, 2251.022, 2251.025).

## Prompt payment on private jobs

| Rule | Texas law |
|---|---|
| Residential work | Not excluded. Chapter 28 covers detached single-family homes, duplexes, triplexes and quadruplexes too; only the good-faith-dispute withholding cap (110% vs 100%), the work-suspension right (§28.009(e)) and a 60-day owner-pay option for single-family contracts (§28.006(b)) differ. ([Tex. Prop. Code §§28.002, 28.003, 28.004, 28.005, 28.006, 28.009](https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm)) |
| Owner pays the GC within | 35 days after the owner receives a written payment request for work properly performed or materials suitably stored/specially fabricated ([Tex. Prop. Code §§28.002, 28.003, 28.004, 28.005, 28.006, 28.009](https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm)) |
| GC pays each sub within | 7 days after the contractor receives the owner's payment (the sub's share, including interest) ([Tex. Prop. Code §§28.002, 28.003, 28.004, 28.005, 28.006, 28.009](https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm)) |
| Flows down to sub-tiers | Yes ([Tex. Prop. Code §§28.002, 28.003, 28.004, 28.005, 28.006, 28.009](https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm)) |
| Withholding for a dispute | Up to 100% of the disputed amount ([Tex. Prop. Code §§28.002, 28.003, 28.004, 28.005, 28.006, 28.009](https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm)) |
| Interest on late payment | 1-1/2 percent each month, starting the day after the payment becomes due, until delivery or mailing of the payment or judgment ([Tex. Prop. Code §§28.002, 28.003, 28.004, 28.005, 28.006, 28.009](https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm)) |
| Attorney's fees to the prevailing party | Yes ([Tex. Prop. Code §§28.002, 28.003, 28.004, 28.005, 28.006, 28.009](https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm)) |

## Prompt payment on public jobs

| Rule | Texas law |
|---|---|
| Agency pays the prime within | 30 days ([Tex. Gov't Code §§2251.021, 2251.022, 2251.023, 2251.025, 2251.042, 2251.043](https://statutes.capitol.texas.gov/Docs/GV/htm/GV.2251.htm)) |
| Prime pays each sub within | 10 days of receiving payment ([Tex. Gov't Code §§2251.021, 2251.022, 2251.023, 2251.025, 2251.042, 2251.043](https://statutes.capitol.texas.gov/Docs/GV/htm/GV.2251.htm)) |
| Interest on late payment | 1% plus the Wall Street Journal prime rate, fixed on 1 September of the fiscal year in which the payment becomes overdue (§2251.025(b)) ([Tex. Gov't Code §§2251.021, 2251.022, 2251.023, 2251.025, 2251.042, 2251.043](https://statutes.capitol.texas.gov/Docs/GV/htm/GV.2251.htm)) |

## When the GC says it hasn't been paid in Texas

Texas has no blanket pay-if-paid ban, but a GC's "we haven't been paid" defence is limited by Bus. & Com. Code ch. 56. A contingent payment clause cannot be enforced if the owner's nonpayment is the GC's own fault (§56.051), after the sub sends a written objection notice (available after the 45th day following its payment request) (§56.052), or if enforcement would be unconscionable (§56.054). Chapter 56 does not apply to detached homes, duplexes, triplexes or quadruplexes, or to road and civil-engineering work (§56.002). The clause is an affirmative defence the GC must plead (§56.056).

## After the deadline: what a sub can do in Texas

When the 7-day (private) or 10-day (public) pass-through lapses, document the date the GC was paid and send a written demand for the unpaid amount plus interest. On private non-residential jobs a sub can give written notice that it will suspend work on the 10th day after notice, copying the owner's lender where the statute's lender-notice conditions are met (Prop. Code §28.009); public subs have a parallel right through the vendor (Gov't Code §2251.052). A court may award reasonable attorney's fees under §28.005; on public contracts the losing side pays the winner's fees (§2251.043). Lien and bond deadlines (Prop. Code ch. 53; Gov't Code ch. 2253) run separately and are not extended by prompt-pay demands.

## Texas quirks to know

Three details catch people. First, the retainage statute is an owner reserve for lien claimants, not a payment deadline: if the owner skips the 10% reserve, claimants get a lien to the extent it should have been held (§53.105). Second, public retainage rules do not apply to contracts under $400,000, to TxDOT highway contracts, or to contracts involving federal funds (§§2252.004, 2252.033). Third, an interest-bearing retainage account is optional for competitively bid contracts of $10 million or more and for non-competitive contracts (§2252.032(c)); the mandatory-escrow rule applies only to certain Texas Water Development Board projects (§2252.032(i)). Local governments (counties, municipalities, school districts, special districts) are covered by both public chapters.

## Worked example: a $48,000 pay app paid late in Texas

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 22, 2026 ([Tex. Prop. Code §§28.002, 28.003, 28.004, 28.005, 28.006, 28.009](https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm)) |
| Paid | July 22, 2026 (30 days late) |
| Interest owed | $710.14 ([Tex. Prop. Code §§28.002, 28.003, 28.004, 28.005, 28.006, 28.009](https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm)) |

In Texas, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. Paid 30 days after that, a $48,000 payment carries $710.14 of interest at 18% a year, simple.

## Texas prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/texas/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 7 days (after the contractor receives the owner's payment (the sub's share, including interest)); interest: 1-1/2 percent each month, starting the day after the payment becomes due, until delivery or mailing of the payment or judgment.
- **Private job: owner → GC:** 35 days (after the owner receives a written payment request for work properly performed or materials suitably stored/specially fabricated); interest: 1-1/2 percent each month, starting the day after the payment becomes due, until delivery or mailing of the payment or judgment.
- **Public job: prime → sub:** 10 days (after the prime is paid); interest: 1% plus the Wall Street Journal prime rate, fixed on 1 September of the fiscal year in which the payment becomes overdue (§2251.025(b)).
- **Public job: agency → prime:** 30 days; interest: 1% plus the Wall Street Journal prime rate, fixed on 1 September of the fiscal year in which the payment becomes overdue (§2251.025(b)).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Texas prompt payment law: questions

### How long does an owner have to pay a GC in Texas on a private job?

35 days after the owner receives a written payment request for properly performed work (Prop. Code §28.002(a)). If the owner's lender fails to disburse, the date moves to 5 days after the owner receives loan proceeds in the situations described in §28.008.

### How soon must a Texas GC pay a sub after getting paid?

By the 7th day after the GC receives the owner's payment, for the sub's share of work performed or stored materials (Prop. Code §28.002(b)). Each sub-tier then has 7 days after it receives payment.

### What interest can a sub charge on late payment in Texas?

1-1/2 percent each month on a late private-job payment, starting the day after it was due (Prop. Code §28.004). On public jobs the rate is 1% plus the WSJ prime rate, set each 1 September (Gov't Code §2251.025).

## Sources

- [Tex. Prop. Code §§28.002, 28.003, 28.004, 28.005, 28.006, 28.009](https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm)
- [Tex. Gov't Code §§2251.021, 2251.022, 2251.023, 2251.025, 2251.042, 2251.043](https://statutes.capitol.texas.gov/Docs/GV/htm/GV.2251.htm)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Texas retainage law](https://fynex.ai/construction/retainage/texas/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- Texas
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- [Virginia](https://fynex.ai/construction/prompt-payment/virginia/)
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)