Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Virginia prompt payment law for construction: the owner-to-GC and GC-to-sub deadlines and late-payment interest. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when pay apps must be paid down the subcontractor chain inside the statutory clocks, with late payments tracked.

# Virginia prompt payment law for construction: deadlines and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

Virginia has two clocks on private jobs. The owner pays the GC within 60 days after receiving an invoice for satisfactorily completed work, and the GC pays a sub by the earlier of 60 days after the sub's invoice or 7 days after the GC receives the owner's payment for the sub's work (Va. Code §11-4.6(B)). Late payment draws interest consistent with §2.2-4355. On public jobs the prime must pay or give written notice of withholding within 7 days of receiving agency payment, and interest runs at 1% per month unless the contract says otherwise (§2.2-4354).

## Prompt payment on private jobs

| Rule | Virginia law |
|---|---|
| Residential work | Not excluded for the basic owner-to-GC and GC-to-sub clocks, which apply to any construction contract. The flow-down to lower-tier subs and suppliers applies only to projects other than single-family residential projects valued above $500,000 (§11-4.6(B)(2)). ([Va. Code §11-4.6(B)](https://law.lis.virginia.gov/vacode/title11/chapter2/section11-4.6/)) |
| Owner pays the GC within | 60 days after receipt of an invoice following satisfactory completion of the portion of the work invoiced ([Va. Code §11-4.6(B)](https://law.lis.virginia.gov/vacode/title11/chapter2/section11-4.6/)) |
| GC pays each sub within | 7 days the earlier of 7 days after the GC receives the owner's payment for the sub's work, or 60 days after the sub's invoice for satisfactorily completed work ([Va. Code §11-4.6(B)](https://law.lis.virginia.gov/vacode/title11/chapter2/section11-4.6/)) |
| Flows down to sub-tiers | Yes ([Va. Code §11-4.6(B)](https://law.lis.virginia.gov/vacode/title11/chapter2/section11-4.6/)) |
| Written notice to withhold | Within 50 days ([Va. Code §11-4.6(B)](https://law.lis.virginia.gov/vacode/title11/chapter2/section11-4.6/)) |
| Interest on late payment | Interest penalties 'consistent with' §2.2-4355: the Wall Street Journal prime rate (the lower figure if a split rate is published), capped at the §58.1-1812 rate, on amounts unpaid more than 7 days after the payment date ([Va. Code §11-4.6(B)](https://law.lis.virginia.gov/vacode/title11/chapter2/section11-4.6/)) |

## Prompt payment on public jobs

| Rule | Virginia law |
|---|---|
| Agency pays the prime within | 30 days ([Va. Code §§2.2-4347, 2.2-4352, 2.2-4354, 2.2-4355](https://law.lis.virginia.gov/vacode/title2.2/chapter43/section2.2-4354/)) |
| Prime pays each sub within | 7 days of receiving payment ([Va. Code §§2.2-4347, 2.2-4352, 2.2-4354, 2.2-4355](https://law.lis.virginia.gov/vacode/title2.2/chapter43/section2.2-4354/)) |
| Interest on late payment | State agency to prime: WSJ prime rate (lower of a split rate), capped at the §58.1-1812 rate, after 7 days past the payment date (§2.2-4355). Prime to sub: contract must say 'one percent per month' unless it provides otherwise, on amounts unpaid 7 days after the prime is paid (§2.2-4354(4)-(5)). Localities: finance charges up to 1% per month (§2.2-4352) ([Va. Code §§2.2-4347, 2.2-4352, 2.2-4354, 2.2-4355](https://law.lis.virginia.gov/vacode/title2.2/chapter43/section2.2-4354/)) |

## When the GC says it hasn't been paid in Virginia

Pay-if-paid is mostly dead in Virginia. Payment from the owner is not a condition precedent to paying a sub, whatever the GC has or has not received, unless the party above the GC is insolvent or a debtor in bankruptcy; a contrary clause is unenforceable (§11-4.6(B)(2)). Public work has the same rule for lower-tier subs (§2.2-4354(1)): the prime stays liable for the whole amount owed to the sub within 60 days of the sub's invoice even if the agency has not paid the prime.

## After the deadline: what a sub can do in Virginia

If the 7-day or 60-day point passes, check whether the GC sent the written withholding notice (within 50 days of the invoice). It must name the contractual noncompliance, the dollar amount and the responsible sub. No notice, no excuse: send a written demand for the invoice plus interest, citing §11-4.6(B)(2) or §2.2-4354. The sections read here provide interest but no fee-shifting, so recovery rests on the contract and a lawsuit. Mechanic's-lien deadlines (Va. Code Title 43) and the payment bond required on public contracts over $500,000 (§2.2-4337) run separately.

## Virginia quirks to know

Mechanic's-lien and bond deadlines are short and are not extended by prompt-pay demands. The lower-tier flow-down in §11-4.6 applies only to non-single-family projects over $500,000, but sub-tier subs on public work get the same clause by statute (§2.2-4354). Interest for private jobs is defined by cross-reference to a state-agency statute (§2.2-4355) and is capped at the Virginia judgment-interest rate in §58.1-1812. Locality payments default to 45 days (§2.2-4352) versus 30 for state agencies. For subcontracts entered into on or after July 1, 2026 the GC and sub are also jointly liable for the sub's unpaid wages (§11-4.6(C); the section was last amended by 2026 Acts c. 1040). A 2026 act allowing retainage bonds instead of cash retainage (c. 485, SB 165) takes effect only if the 2027 General Assembly reenacts it.

## Worked example: a $48,000 pay app paid late in Virginia

| | |
|---|---|
| Clock | Private job: GC → sub |
| Clock starts | June 15, 2026 |
| Payment due by | June 22, 2026 ([Va. Code §11-4.6(B)](https://law.lis.virginia.gov/vacode/title11/chapter2/section11-4.6/)) |
| Paid | July 22, 2026 (30 days late) |
| Interest owed | No fixed statutory rate |

In Virginia, a GC paid by the owner has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. The statutory rate moves with an index ("Interest penalties 'consistent with' §2.2-4355: the Wall Street Journal prime rate (the lower figure if a split rate is published), capped at the §58.1-1812 rate, on amounts unpaid more than 7 days after the payment date"), so enter the current figure in the calculator.

## Virginia prompt payment calculator: days late and interest

Interactive on the page: https://fynex.ai/construction/prompt-payment/virginia/#calculator. The statutory figures it starts from:

- **Private job: GC → sub:** 7 days (the earlier of 7 days after the GC receives the owner's payment for the sub's work, or 60 days after the sub's invoice for satisfactorily completed work); interest: Interest penalties 'consistent with' §2.2-4355: the Wall Street Journal prime rate (the lower figure if a split rate is published), capped at the §58.1-1812 rate, on amounts unpaid more than 7 days after the payment date.
- **Private job: owner → GC:** 60 days (after receipt of an invoice following satisfactory completion of the portion of the work invoiced); interest: Interest penalties 'consistent with' §2.2-4355: the Wall Street Journal prime rate (the lower figure if a split rate is published), capped at the §58.1-1812 rate, on amounts unpaid more than 7 days after the payment date.
- **Public job: prime → sub:** 7 days (after the prime is paid); interest: State agency to prime: WSJ prime rate (lower of a split rate), capped at the §58.1-1812 rate, after 7 days past the payment date (§2.2-4355). Prime to sub: contract must say 'one percent per month' unless it provides otherwise, on amounts unpaid 7 days after the prime is paid (§2.2-4354(4)-(5)). Localities: finance charges up to 1% per month (§2.2-4352).
- **Public job: agency → prime:** 30 days; interest: State agency to prime: WSJ prime rate (lower of a split rate), capped at the §58.1-1812 rate, after 7 days past the payment date (§2.2-4355). Prime to sub: contract must say 'one percent per month' unless it provides otherwise, on amounts unpaid 7 days after the prime is paid (§2.2-4354(4)-(5)). Localities: finance charges up to 1% per month (§2.2-4352).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Virginia prompt payment law: questions

### Does Virginia's prompt pay law apply to private construction?

Yes. Va. Code §11-4.6 requires every private construction contract to have an owner-to-GC clause (60 days from invoice) and a GC-to-sub clause (earlier of 60 days or 7 days after the GC is paid). It applies to residential too, but the sub-tier flow-down is limited to non-single-family projects over $500,000.

### How many days does a Virginia GC have to pay a sub after getting paid?

Seven days after the GC receives the owner's payment for the sub's work, or 60 days after the sub's invoice if that comes first (Va. Code §11-4.6(B)(2)). On public work, the prime must pay or give written notice of withholding within 7 days (§2.2-4354(2)).

### Can a Virginia GC refuse to pay me because the owner has not paid?

Generally no. Owner payment cannot be a condition precedent to paying a sub unless the owner is insolvent or in bankruptcy, and a contrary contract clause is unenforceable (Va. Code §11-4.6(B)(2)). The GC may still withhold for the sub's own noncompliance if it gives written notice within 50 days.

### What interest can I charge on a late public-job payment in Virginia?

From the prime contractor, the contract must carry the clause 'interest shall accrue at the rate of one percent per month' unless it provides otherwise, running from 7 days after the prime is paid (Va. Code §2.2-4354(4)-(5)). The agency itself owes WSJ prime after 7 days past the payment date (§2.2-4355).

## Sources

- [Va. Code §11-4.6(B)](https://law.lis.virginia.gov/vacode/title11/chapter2/section11-4.6/)
- [Va. Code §§2.2-4347, 2.2-4352, 2.2-4354, 2.2-4355](https://law.lis.virginia.gov/vacode/title2.2/chapter43/section2.2-4354/)

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [Virginia retainage law](https://fynex.ai/construction/retainage/virginia/)
- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Prompt payment law in every state

- [Alabama](https://fynex.ai/construction/prompt-payment/alabama/)
- [Alaska](https://fynex.ai/construction/prompt-payment/alaska/)
- [Arizona](https://fynex.ai/construction/prompt-payment/arizona/)
- [Arkansas](https://fynex.ai/construction/prompt-payment/arkansas/)
- [California](https://fynex.ai/construction/prompt-payment/california/)
- [Colorado](https://fynex.ai/construction/prompt-payment/colorado/)
- [Connecticut](https://fynex.ai/construction/prompt-payment/connecticut/)
- [Delaware](https://fynex.ai/construction/prompt-payment/delaware/)
- [Florida](https://fynex.ai/construction/prompt-payment/florida/)
- [Georgia](https://fynex.ai/construction/prompt-payment/georgia/)
- [Hawaii](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Idaho](https://fynex.ai/construction/prompt-payment/idaho/)
- [Illinois](https://fynex.ai/construction/prompt-payment/illinois/)
- [Indiana](https://fynex.ai/construction/prompt-payment/indiana/)
- [Iowa](https://fynex.ai/construction/prompt-payment/iowa/)
- [Kansas](https://fynex.ai/construction/prompt-payment/kansas/)
- [Kentucky](https://fynex.ai/construction/prompt-payment/kentucky/)
- [Louisiana](https://fynex.ai/construction/prompt-payment/louisiana/)
- [Maine](https://fynex.ai/construction/prompt-payment/maine/)
- [Maryland](https://fynex.ai/construction/prompt-payment/maryland/)
- [Massachusetts](https://fynex.ai/construction/prompt-payment/massachusetts/)
- [Michigan](https://fynex.ai/construction/prompt-payment/michigan/)
- [Minnesota](https://fynex.ai/construction/prompt-payment/minnesota/)
- [Mississippi](https://fynex.ai/construction/prompt-payment/mississippi/)
- [Missouri](https://fynex.ai/construction/prompt-payment/missouri/)
- [Montana](https://fynex.ai/construction/prompt-payment/montana/)
- [Nebraska](https://fynex.ai/construction/prompt-payment/nebraska/)
- [Nevada](https://fynex.ai/construction/prompt-payment/nevada/)
- [New Hampshire](https://fynex.ai/construction/prompt-payment/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/prompt-payment/new-jersey/)
- [New Mexico](https://fynex.ai/construction/prompt-payment/new-mexico/)
- [New York](https://fynex.ai/construction/prompt-payment/new-york/)
- [North Carolina](https://fynex.ai/construction/prompt-payment/north-carolina/)
- [North Dakota](https://fynex.ai/construction/prompt-payment/north-dakota/)
- [Ohio](https://fynex.ai/construction/prompt-payment/ohio/)
- [Oklahoma](https://fynex.ai/construction/prompt-payment/oklahoma/)
- [Oregon](https://fynex.ai/construction/prompt-payment/oregon/)
- [Pennsylvania](https://fynex.ai/construction/prompt-payment/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/prompt-payment/rhode-island/)
- [South Carolina](https://fynex.ai/construction/prompt-payment/south-carolina/)
- [South Dakota](https://fynex.ai/construction/prompt-payment/south-dakota/)
- [Tennessee](https://fynex.ai/construction/prompt-payment/tennessee/)
- [Texas](https://fynex.ai/construction/prompt-payment/texas/)
- [Utah](https://fynex.ai/construction/prompt-payment/utah/)
- [Vermont](https://fynex.ai/construction/prompt-payment/vermont/)
- Virginia
- [Washington](https://fynex.ai/construction/prompt-payment/washington/)
- [West Virginia](https://fynex.ai/construction/prompt-payment/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/prompt-payment/wisconsin/)
- [Wyoming](https://fynex.ai/construction/prompt-payment/wyoming/)