Construction · Prompt payment law

Washington prompt payment law for construction: deadlines and interest

Washington has no private-sector prompt-pay act. On public work, a public body must pay a prime within 30 days of a proper invoice and owes 1% per month (at least $1) on late payments (RCW 39.76.011). A prime or sub that receives payment must pass each sub's share down within 10 days (RCW 39.04.250(1)), and a sub wrongly held up recovers interest and fees. Public bodies must send written notice of any withholding within 8 working days of a pay request, naming what the prime has to fix (RCW 39.76.011(2)(b)).

Also in Washington: retainage law

Washington prompt payment calculator: days late and interest

Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from Washington law; change them if your contract or the statute's trigger differs.

Which clock

Clock starts: after the prime is paid

Statute: Public body to prime: 1% per month, minimum $1 per month (RCW 39.76.011(1)). Prime or sub to a sub: interest at the highest rate allowed under RCW 19.52.025 for every month and portion of a month payment, including retainage, is wrongfully withheld (RCW 39.04.250(3))

Payment due by
June 25, 2026
Days late
30
Interest owed
$473.42
Total now owed
$48,473.42

30 days late at 12% a year.

Statute: RCW 39.76.011, 39.76.020, 39.76.040; RCW 39.04.250

Calendar days and simple interest (12% a year ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Prompt payment on private jobs

No statute. No Washington statute found that sets owner-to-GC or GC-to-sub payment deadlines on private projects. RCW 39.04.250 (10-day pass-through) is limited to public works and RCW 39.76 to payments by public bodies. On private jobs the contract sets the payment dates and interest, and a sub's statutory leverage is the lien chapter (RCW 60.04), not a prompt-pay act.

Prompt payment on public jobs

RuleWashington law
Agency pays the prime within30 daysRCW 39.76.011, 39.76.020, 39.76.040; RCW 39.04.250
Prime pays each sub within10 days of receiving paymentRCW 39.76.011, 39.76.020, 39.76.040; RCW 39.04.250
Interest on late paymentPublic body to prime: 1% per month, minimum $1 per month (RCW 39.76.011(1)). Prime or sub to a sub: interest at the highest rate allowed under RCW 19.52.025 for every month and portion of a month payment, including retainage, is wrongfully withheld (RCW 39.04.250(3))RCW 39.76.011, 39.76.020, 39.76.040; RCW 39.04.250

When the GC says it hasn't been paid in Washington

Washington's public-works pass-through duty runs from receipt of payment, not from the agency's final acceptance: the contractor or sub that is paid must pay each sub its share within 10 days (RCW 39.04.250(1)). A good-faith dispute lets a party withhold no more than 150% of the disputed amount, and everyone else in the chain is entitled to full and prompt payment of their portion, including released retainage (RCW 39.04.250(2)). For private projects the statutes read here do not address pay-if-paid; whether a contingent-payment clause is enforceable depends on the contract and case law, which was not reviewed.

After the deadline: what a sub can do in Washington

On a public job, a sub that is paid late can claim interest for every month and portion of a month at the highest rate allowed under RCW 19.52.025, plus costs and attorneys' fees to the prevailing party (RCW 39.04.250(3)). To protect the retainage fund itself, a laborer, sub or supplier must file a lien notice within 45 days of completion of the contract work, and material suppliers must give the contractor the written notice in RCW 60.28.015. A lien action must be brought within four months of the claim filing (RCW 60.28.030). The prime's payment bond (ch. 39.08) is a separate route.

Washington quirks to know

Washington treats public retainage as a statutory trust fund and gives claimants a lien on it (RCW 60.28.011(1)-(2)). Contractors may substitute a retainage bond for all or part of the retainage, and a sub can ask its prime to post a bond for the sub's share, which the prime must provide within 30 days unless the public body shows good cause (RCW 60.28.011(6)). Retainage on contracts funded by federal transportation money is replaced by reliance on the contract bond (RCW 60.28.011(1)(b)). Public bodies may not reserve anything from earnings other than this retainage (RCW 60.28.011(9)). Private projects have none of this.

Worked example: a $48,000 pay app paid late in Washington

ClockPublic job: prime → sub
Clock startsJune 15, 2026
Payment due byJune 25, 2026RCW 39.76.011, 39.76.020, 39.76.040; RCW 39.04.250
PaidJuly 25, 2026 (30 days late)
Interest owed$473.42RCW 39.76.011, 39.76.020, 39.76.040; RCW 39.04.250

In Washington, a prime paid by the agency has to pay the sub within 10 days: with the clock starting June 15, 2026, payment is due by June 25, 2026. Paid 30 days after that, a $48,000 payment carries $473.42 of interest at 12% a year, simple.

Run a payment like this in the split calculator

Washington prompt payment law: questions

How soon must a Washington prime or sub pay down after being paid on a public job?

Within 10 days after receipt, to the extent of each sub's interest in the payment (RCW 39.04.250(1)).

Does Washington have a prompt pay law for private construction?

The statutes read for this entry do not contain one. RCW 39.04.250 and RCW 39.76 are limited to public works and public bodies, so private payment deadlines and interest are set by contract.

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.