Construction · Prompt payment law

Wisconsin prompt payment law for construction: deadlines and interest

Wisconsin's prompt-payment sections apply to public work only. A state agency or local governmental unit that does not pay within 30 days of a properly completed invoice owes interest from the 31st day (45-day periods apply to some older contracts), and a prime contractor that does not pay a sub within 7 days of receiving agency payment owes interest from the 8th day, at the Wis. Stat. §71.82(1)(a) rate compounded monthly (§§16.528, 66.0135). A court must award the prevailing party reasonable attorney fees in an action to recover the interest. No private-job statute was found.

Also in Wisconsin: retainage law

Wisconsin prompt payment calculator: days late and interest

Pick the clock, enter the date it started and the amount. The deadline and the interest rate are pre-filled from Wisconsin law; change them if your contract or the statute's trigger differs.

Which clock

Clock starts: after the prime is paid

Statute: Agency to prime: payment is timely if made by the later of the invoice date or 30 days after a properly completed invoice or receipt and acceptance of the work; interest runs from the 31st day at the rate in Wis. Stat. §71.82(1)(a), 12 percent per year, compounded monthly (16.528(2); 66.0135(2)). Prime to sub: timely if paid within 7 days after the prime receives any payment from the agency; interest from the 8th day at the same rate, compounded monthly, and the same rule flows to lower tiers (16.528(2m); 66.0135(3)). Local units must flag an improper invoice within 10 working days (66.0135(7)), and in a suit for interest under 66.0135 the court shall award the prevailing party reasonable attorney fees (66.0135(6)). Exceptions include federally funded portions and good-faith disputes noticed before the due date.

Payment due by
June 22, 2026
Days late
30
Interest owed
$473.42
Total now owed
$48,473.42

30 days late at 12% a year.

Statute: Wis. Stat. §§16.528(2), (2m) (state agencies); 66.0135(2), (3), (6) (local governmental units); 71.82(1)(a)

Calendar days and simple interest (12% a year ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Prompt payment on private jobs

No statute. No Wisconsin statute found that sets owner-to-GC or GC-to-sub payment deadlines or interest on private construction. The prompt-payment sections found (Wis. Stat. §§16.528 and 66.0135) cover state agencies and local governmental units only. For private jobs, Wis. Stat. §779.02(5) makes money an owner pays a prime or sub a trust fund for unpaid labor and material claims, with theft liability for diverting it; payment dates and interest otherwise come from the contract.

Prompt payment on public jobs

RuleWisconsin law
Agency pays the prime within30 daysWis. Stat. §§16.528(2), (2m) (state agencies); 66.0135(2), (3), (6) (local governmental units); 71.82(1)(a)
Prime pays each sub within7 days of receiving paymentWis. Stat. §§16.528(2), (2m) (state agencies); 66.0135(2), (3), (6) (local governmental units); 71.82(1)(a)
Interest on late paymentAgency to prime: payment is timely if made by the later of the invoice date or 30 days after a properly completed invoice or receipt and acceptance of the work; interest runs from the 31st day at the rate in Wis. Stat. §71.82(1)(a), 12 percent per year, compounded monthly (16.528(2); 66.0135(2)). Prime to sub: timely if paid within 7 days after the prime receives any payment from the agency; interest from the 8th day at the same rate, compounded monthly, and the same rule flows to lower tiers (16.528(2m); 66.0135(3)). Local units must flag an improper invoice within 10 working days (66.0135(7)), and in a suit for interest under 66.0135 the court shall award the prevailing party reasonable attorney fees (66.0135(6)). Exceptions include federally funded portions and good-faith disputes noticed before the due date.Wis. Stat. §§16.528(2), (2m) (state agencies); 66.0135(2), (3), (6) (local governmental units); 71.82(1)(a)

When the GC says it hasn't been paid in Wisconsin

Under the public-work sections, the prime's duty to pay a sub runs from the prime's receipt of agency payment: payment is timely if made no later than 7 days after that receipt, and interest runs from the 8th day (Wis. Stat. §§16.528(2m), 66.0135(3)). A good-faith dispute exception applies if notice of the dispute is sent before the payment date. These sections do not address whether a pay-if-paid clause is enforceable on private or public jobs, which was not researched. On private jobs, §779.02(5) treats money received from an owner as a trust fund for unpaid claims.

After the deadline: what a sub can do in Wisconsin

On a public job, count 7 days from the date the prime received agency payment, then send a written demand for the sub's share plus interest from the 8th day at the §71.82(1)(a) rate compounded monthly, citing §16.528(2m) or §66.0135(3). The prevailing party in an interest action recovers reasonable attorney fees (§§16.528(6), 66.0135(6)). Check that the dispute exception was not properly noticed. Private-job remedies are the contract, the lien chapter (Wis. Stat. ch. 779, with its own notice deadlines) and, for diverted funds, the trust-fund and theft rule in §779.02(5).

Wisconsin quirks to know

Wisconsin pairs a retainage taper with a hard ceiling: 5% until half the work is done, then no more withholding, with a 10% total cap if the work is unsatisfactory. The sub-payment clock is only 7 days and the interest compounds monthly, but both are statutory for public contracts only. Local public contracts under $1,000 are outside the local retainage rule. Wisconsin's best-known private-job protection is not a payment deadline but the construction trust fund and theft provision in §779.02(5), which can reach responsible officers of a contractor that diverts owner payments.

Worked example: a $48,000 pay app paid late in Wisconsin

ClockPublic job: prime → sub
Clock startsJune 15, 2026
Payment due byJune 22, 2026Wis. Stat. §§16.528(2), (2m) (state agencies); 66.0135(2), (3), (6) (local governmental units); 71.82(1)(a)
PaidJuly 22, 2026 (30 days late)
Interest owed$473.42Wis. Stat. §§16.528(2), (2m) (state agencies); 66.0135(2), (3), (6) (local governmental units); 71.82(1)(a)

In Wisconsin, a prime paid by the agency has to pay the sub within 7 days: with the clock starting June 15, 2026, payment is due by June 22, 2026. Paid 30 days after that, a $48,000 payment carries $473.42 of interest at 12% a year, simple.

Run a payment like this in the split calculator

Wisconsin prompt payment law: questions

How soon must a Wisconsin prime pay a sub on a state project?

Within 7 calendar days after the prime receives payment (Wis. Stat. §16.855(19)(b)); timely payment on agency work is also defined as no later than 7 days after the prime's receipt, with interest from the 8th day (§16.528(2m)).

How long does a Wisconsin local government have to pay a contractor?

Payment is timely if made within 30 days of a properly completed invoice or of receipt and acceptance of the work, whichever is later; interest runs from the 31st day (Wis. Stat. §66.0135(2)).

Does Wisconsin have a prompt payment law for private construction?

None was found. The prompt-payment sections located (§§16.528 and 66.0135) cover state agencies and local governmental units. Private payment terms are contractual, and §779.02(5) makes owner payments a trust fund for unpaid claims.

Do I get attorney fees if I sue for late-payment interest on a Wisconsin public job?

Yes. In an action to recover interest under §16.528 or §66.0135, the court shall award the prevailing party reasonable attorney fees (§16.528(6), §66.0135(6)).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.