Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page compares construction retainage law across the US states: caps, release deadlines and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Retainage laws by state: caps, release deadlines and interest

_Law as of October 14, 2026; 50 of 50 states. This page explains the law; it is not legal advice._

**Retainage** (retention, retainer, holdback) is the share of each progress payment an owner holds back from the GC, and the GC holds back from each sub, until the job is complete. State law decides three things about it: the **cap** (often 5% or 10%, sometimes stepping down at 50% complete), the **release deadline** after substantial completion or final acceptance, and the **interest or penalty** owed when retainage is released late.

Public jobs almost always have a statute; private jobs often don't, and then the subcontract governs. The table below gives each state's key figures with the statute behind them. Each state page has the full rule, what to do when the deadline passes, a worked example and a release-date and interest calculator.

![Chart of the 50 US states grouped by highest public-job retainage cap (retainage law). 0%: 1 state (NM); 2%: 1 state (NJ); 3%: 1 state (IA); 3.5%: 1 state (SC); 4%: 1 state (OH); 5%: 27 states (AL, AR, CA, CO, DE, FL, GA, HI, ID, KS, MA, MD, MN, MS, MT, NC, NV, NY, OK, OR, RI, TN, UT, VA, WA, WI, WY); 6%: 1 state (IN); 7.5%: 1 state (CT); 10%: 10 states (AZ, IL, KY, LA, MI, MO, ND, NE, PA, TX); Statute sets no cap: 4 states (AK, ME, SD, VT); No public-job statute: 2 states (NH, WV).](https://fynex.ai/charts/state-laws/construction-retainage.webp)

**27 states cap retainage on public jobs at 5%.** The highest share of each progress payment a state's statute lets a public owner hold back. Many states step down after 50% completion or vary the cap by contract size. Source: state statutes as cited on each state page, read 2026-10-14.

| Highest public-job retainage cap | States | Which |
|---|---|---|
| 0% | 1 | [New Mexico](https://fynex.ai/construction/retainage/new-mexico/) |
| 2% | 1 | [New Jersey](https://fynex.ai/construction/retainage/new-jersey/) |
| 3% | 1 | [Iowa](https://fynex.ai/construction/retainage/iowa/) |
| 3.5% | 1 | [South Carolina](https://fynex.ai/construction/retainage/south-carolina/) |
| 4% | 1 | [Ohio](https://fynex.ai/construction/retainage/ohio/) |
| 5% | 27 | [Alabama](https://fynex.ai/construction/retainage/alabama/), [Arkansas](https://fynex.ai/construction/retainage/arkansas/), [California](https://fynex.ai/construction/retainage/california/), [Colorado](https://fynex.ai/construction/retainage/colorado/), [Delaware](https://fynex.ai/construction/retainage/delaware/), [Florida](https://fynex.ai/construction/retainage/florida/), [Georgia](https://fynex.ai/construction/retainage/georgia/), [Hawaii](https://fynex.ai/construction/retainage/hawaii/), [Idaho](https://fynex.ai/construction/retainage/idaho/), [Kansas](https://fynex.ai/construction/retainage/kansas/), [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/), [Maryland](https://fynex.ai/construction/retainage/maryland/), [Minnesota](https://fynex.ai/construction/retainage/minnesota/), [Mississippi](https://fynex.ai/construction/retainage/mississippi/), [Montana](https://fynex.ai/construction/retainage/montana/), [North Carolina](https://fynex.ai/construction/retainage/north-carolina/), [Nevada](https://fynex.ai/construction/retainage/nevada/), [New York](https://fynex.ai/construction/retainage/new-york/), [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/), [Oregon](https://fynex.ai/construction/retainage/oregon/), [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/), [Tennessee](https://fynex.ai/construction/retainage/tennessee/), [Utah](https://fynex.ai/construction/retainage/utah/), [Virginia](https://fynex.ai/construction/retainage/virginia/), [Washington](https://fynex.ai/construction/retainage/washington/), [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/), [Wyoming](https://fynex.ai/construction/retainage/wyoming/) |
| 6% | 1 | [Indiana](https://fynex.ai/construction/retainage/indiana/) |
| 7.5% | 1 | [Connecticut](https://fynex.ai/construction/retainage/connecticut/) |
| 10% | 10 | [Arizona](https://fynex.ai/construction/retainage/arizona/), [Illinois](https://fynex.ai/construction/retainage/illinois/), [Kentucky](https://fynex.ai/construction/retainage/kentucky/), [Louisiana](https://fynex.ai/construction/retainage/louisiana/), [Michigan](https://fynex.ai/construction/retainage/michigan/), [Missouri](https://fynex.ai/construction/retainage/missouri/), [North Dakota](https://fynex.ai/construction/retainage/north-dakota/), [Nebraska](https://fynex.ai/construction/retainage/nebraska/), [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/), [Texas](https://fynex.ai/construction/retainage/texas/) |
| Statute sets no cap | 4 | [Alaska](https://fynex.ai/construction/retainage/alaska/), [Maine](https://fynex.ai/construction/retainage/maine/), [South Dakota](https://fynex.ai/construction/retainage/south-dakota/), [Vermont](https://fynex.ai/construction/retainage/vermont/) |
| No public-job statute | 2 | [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/), [West Virginia](https://fynex.ai/construction/retainage/west-virginia/) |

## Retainage caps and release deadlines, state by state

| State | Private jobs | Public jobs: cap | Public jobs: release | Statute |
|---|---|---|---|---|
| [Alabama](https://fynex.ai/construction/retainage/alabama/) | 10% cap | 5% of each payment | 35 days | [Ala. Code §39-2-12(c), (e)-(g), (i)](https://alison.legislature.state.al.us/code-of-alabama?section=39-2-12) |
| [Alaska](https://fynex.ai/construction/retainage/alaska/) | No statute | No cap | Per contract | [Alaska Stat. §§36.90.210(a)(2), (a)(4), (b)(2), (b)(4); 36.90.250](https://www.akleg.gov/basis/statutes.asp?media=print&secStart=36.90.200&secEnd=36.90.260) |
| [Arizona](https://fynex.ai/construction/retainage/arizona/) | No cap | 5–10% (varies) | 60 days | [A.R.S. §34-221(C)(2)-(6), (G)-(K)](https://www.azleg.gov/ars/34/00221.htm) |
| [Arkansas](https://fynex.ai/construction/retainage/arkansas/) | No statute | 5% of each payment | 30 days | [Ark. Code §22-9-604 (text as rewritten by Act 866 of 2015, the last amendment); §§22-9-601 to 22-9-603 (definitions, scope, non-waiver; mirror text only)](https://arkleg.state.ar.us/Acts/FTPDocument?path=%2FACTS%2F2015R%2FPublic%2F&file=866.pdf&ddBienniumSession=2015%2F2015R) |
| [California](https://fynex.ai/construction/retainage/california/) | 5% cap | 5% of each payment | 60 days | [Cal. Pub. Cont. Code §§7107, 7201 (as amended by Stats. 2022, ch. 121, AB 2173), 22300](https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PCC&sectionNum=7107) |
| [Colorado](https://fynex.ai/construction/retainage/colorado/) | 5% cap | 5% on contracts over $150,000 | 60 days | [C.R.S. §§24-91-102, 24-91-103, 24-91-104, 24-91-105; §38-26-107](https://colorado.public.law/statutes/crs_24-91-103) |
| [Connecticut](https://fynex.ai/construction/retainage/connecticut/) | 5% cap | 2.5–7.5% (varies) | Per contract | [Conn. Gen. Stat. §§49-41b, 49-41a, 49-41c (as amended by P.A. 25-168, §214), 4a-71, 46a-68e](https://www.cga.ct.gov/current/pub/chap_847.htm) |
| [Delaware](https://fynex.ai/construction/retainage/delaware/) | No statute | 5% of each payment | 60 days | [29 Del. C. §6962(d)(5); §6516(f)(3)-(4), (7)](https://delcode.delaware.gov/title29/c069/sc04/index.html) |
| [Florida](https://fynex.ai/construction/retainage/florida/) | No cap | 5% on contracts over $200,000 | 20 days | [Fla. Stat. §§255.078, 255.077 (state/public entities); §218.735(7)-(8) (local governmental entities)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0200-0299/0255/Sections/0255.078.html) |
| [Georgia](https://fynex.ai/construction/retainage/georgia/) | No cap | 5% on contracts over $150,000 | 30 days | [O.C.G.A. §13-10-80(b)-(c) as amended by 2022 Ga. Laws S.B. 438 (Act 871); §13-10-81](https://gov.georgia.gov/document/2022-signed-legislation/sb-438/download) |
| [Hawaii](https://fynex.ai/construction/retainage/hawaii/) | No statute | 5% of each payment | 30 days | [Haw. Rev. Stat. §§103-32.1, 103-32.2, 103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-32.1.html) |
| [Idaho](https://fynex.ai/construction/retainage/idaho/) | 5% cap | 5% | 30 days | [Idaho Code §§54-1926(3), 54-1926a, 67-2302(16)](https://legislature.idaho.gov/statutesrules/idstat/Title54/T54CH19/SECT54-1926/) |
| [Illinois](https://fynex.ai/construction/retainage/illinois/) | 10% cap | 5–10% (varies) | Per contract | [Public Construction Bond Act, 30 ILCS 550/1 (as amended by P.A. 102-968, eff. Jan. 1, 2023, and P.A. 103-570, eff. Jan. 1, 2024; further amended by P.A. 104-0168, eff. June 1, 2027)](https://www.ilga.gov/Legislation/PublicActs/View/104-0168) |
| [Indiana](https://fynex.ai/construction/retainage/indiana/) | No statute | 6% of each payment | 61 days | [Ind. Code §§4-13.6-7-1, 4-13.6-7-2, 4-13.6-7-3, 4-13.6-7-8; 5-16-5.5-2, 5-16-5.5-3, 5-16-5.5-3.5, 5-16-5.5-6; 36-1-12-14 (as amended by P.L.28-2025)](https://iga.in.gov/ic/2026/Title_36.pdf) |
| [Iowa](https://fynex.ai/construction/retainage/iowa/) | No statute | 3% of each payment | 30 days | [Iowa Code §§573.12(1), 573.13 (as amended by 2025 Iowa Acts ch. 29, S.F. 574), 573.14, 573.15, 573.16 (as amended by 2026 S.F. 2365, eff. July 1, 2026), 573.28; §4.5](https://www.legis.iowa.gov/docs/code/573.12.pdf) |
| [Kansas](https://fynex.ai/construction/retainage/kansas/) | 5% cap | 5% of each payment | 30 days | [K.S.A. 16-1904, 16-1902](https://www.ksrevisor.org/statutes/chapters/ch16/016_019_0004.html) |
| [Kentucky](https://fynex.ai/construction/retainage/kentucky/) | 10% cap | 10% of each payment | 30 days | [KRS 371.410, 371.425(1)](https://apps.legislature.ky.gov/law/statutes/statute.aspx?id=35259) |
| [Louisiana](https://fynex.ai/construction/retainage/louisiana/) | No statute | 10% on contracts under $500,000; 5% on contracts of $500,000 or more | 45 days | [La. R.S. 38:2248, 38:2241.1, 38:2191 (as amended by Acts 2026, No. 255)](https://legis.la.gov/Legis/Law.aspx?d=94968) |
| [Maine](https://fynex.ai/construction/retainage/maine/) | No cap | No cap | 30 days | [10 M.R.S. §§1111(6), 1112, 1116](https://legislature.maine.gov/statutes/10/title10ch201-A.pdf) |
| [Maryland](https://fynex.ai/construction/retainage/maryland/) | 5% cap | 5% of each payment | Per contract | [Md. Code, State Fin. & Proc. §13-225](https://mgaleg.maryland.gov/2026RS/Statute_Web/gsf/13-225.pdf) |
| [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/) | 5% cap | 5% of each payment | 65 days | [M.G.L. c.30 §§39K, 39G](https://malegislature.gov/Laws/GeneralLaws/PartI/TitleIII/Chapter30/Section39K) |
| [Michigan](https://fynex.ai/construction/retainage/michigan/) | No statute | 10% on contracts of $30,000 or more | 30 days | [Mich. Comp. Laws §§125.1561, 125.1563, 125.1564 (Act 524 of 1980)](https://www.legislature.mi.gov/Laws/MCL?objectName=mcl-125-1563) |
| [Minnesota](https://fynex.ai/construction/retainage/minnesota/) | 5% cap | 5% of each payment | 60 days | [Minn. Stat. §15.72 subd. 2 (public improvements); §15.71](https://www.revisor.mn.gov/statutes/cite/15.72) |
| [Mississippi](https://fynex.ai/construction/retainage/mississippi/) | 5% cap | 5% of each payment | 60 days | [Miss. Code §§31-5-33, 31-5-15, 31-5-25](https://www.mscode.com/free/statutes/31/005/0033.htm) |
| [Missouri](https://fynex.ai/construction/retainage/missouri/) | No statute | 10% on contracts under $50,000; 5% on contracts of $50,000 or more | 30 days | [RSMo 8.960.1(1), (3), (4), (8)](https://revisor.mo.gov/main/OneSection.aspx?section=8.960) |
| [Montana](https://fynex.ai/construction/retainage/montana/) | 5% cap | 5% of each payment | 30 days | [MCA 18-2-316, 18-2-306, 28-2-2110](https://leg.mt.gov/bills/mca/title_0180/chapter_0020/part_0030/section_0160/0180-0020-0030-0160.html) |
| [Nebraska](https://fynex.ai/construction/retainage/nebraska/) | 10% cap | 10% of each payment | 45 days | [Neb. Rev. Stat. 45-1202, 45-1203(3), 45-1204(1), 45-1210, 39-1349(2)](https://nebraskalegislature.gov/laws/statutes.php?statute=45-1203) |
| [Nevada](https://fynex.ai/construction/retainage/nevada/) | 5% cap | 5% of each payment | 30 days | [NRS 338.515, 338.520, 338.525, 338.555, 338.595](https://www.leg.state.nv.us/nrs/nrs-338.html#NRS338Sec515) |
| [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/) | No statute | No statute | — | [N.H. RSA ch. 447](https://www.gencourt.state.nh.us/rsa/html/NHTOC/NHTOC-XLI-447.htm) |
| [New Jersey](https://fynex.ai/construction/retainage/new-jersey/) | No statute | 2% of each payment | 45 days | [N.J.S.A. 40A:11-16.1, 40A:11-16.2, 40A:11-16.3, 18A:18A-40.1 to 40.3, 27:7-34](https://codes.findlaw.com/nj/title-40a-municipalities-and-counties/nj-st-sect-40a-11-16-3/) |
| [New Mexico](https://fynex.ai/construction/retainage/new-mexico/) | 0% cap | 0% of each payment | 10 days | [NMSA 1978, 57-28-2, 57-28-5(E), 57-28-8, 67-3-48](https://nmonesource.com/nmos/nmsa/en/item/4423/index.do) |
| [New York](https://fynex.ai/construction/retainage/new-york/) | 5% cap | 5% of each payment | 30 days | [N.Y. State Fin. Law 139-f, 137(1), 179-f, 179-g; N.Y. Gen. Mun. Law 106-b](https://www.nysenate.gov/legislation/laws/STF/139-F) |
| [North Carolina](https://fynex.ai/construction/retainage/north-carolina/) | No statute | 0% on contracts under $150,000; 5% on contracts of $150,000 or more | 60 days | [N.C. Gen. Stat. 143-134.1(b1) to (b6), as amended by S.L. 2026-9 (H 1123), s. 5.1(c), eff. 2026-06-19](https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_143/GS_143-134.1.html) |
| [North Dakota](https://fynex.ai/construction/retainage/north-dakota/) | 10% cap | 10% of each payment | 30 days | [N.D.C.C. 48-01.2-13, 48-01.2-14, 40-22-37](https://ndlegis.gov/cencode/t48c01-2.pdf) |
| [Ohio](https://fynex.ai/construction/retainage/ohio/) | No cap | 4% of each payment | 30 days | [Ohio Rev. Code 153.12, 153.13, 153.14, as amended by 2025 Am. Sub. H.B. 96 (eff. 2025-09-30)](https://codes.ohio.gov/ohio-revised-code/section-153.13) |
| [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/) | No statute | 5% of each payment | 21 days | [61 O.S. 113.1, 113.2, 113.3, 226](https://www.oscn.net/applications/oscn/DeliverDocument.asp?CiteID=442374) |
| [Oregon](https://fynex.ai/construction/retainage/oregon/) | 5% cap | 5% of each payment | 30 days | [ORS 279C.550, 279C.555, 279C.560, 279C.565, 279C.570(7), (8), 701.435](https://www.oregonlegislature.gov/bills_laws/ors/ors279C.html#279C.570) |
| [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/) | No cap | 10% of each payment | 45 days | [62 Pa.C.S. §§3902, 3921, 3922, 3933(c), 3938, 3941](https://www.palegis.us/statutes/consolidated/view-statute?txtType=PDF&ttl=62&div=00.&chpt=39) |
| [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/) | 5% cap | 5% on contracts under $500,000; 5% on contracts of $500,000 or more | 30 days | [R.I. Gen. Laws §37-12-10.1; §37-12-10 (older rule for sewer, water main and public works contracts under $500,000)](https://webserver.rilegislature.gov/Statutes/TITLE37/37-12/37-12-10.1.htm) |
| [South Carolina](https://fynex.ai/construction/retainage/south-carolina/) | No statute | 3.5% of each payment | Per contract | [S.C. Code §11-35-3030(4)](https://www.scstatehouse.gov/code/t11c035.php) |
| [South Dakota](https://fynex.ai/construction/retainage/south-dakota/) | No statute | No cap | 30 days | [SDCL 5-18B-11, 5-18B-12, 5-18B-13, 5-18B-14; 54-3-16](https://sdlegislature.gov/Statutes/5-18B-11) |
| [Tennessee](https://fynex.ai/construction/retainage/tennessee/) | 5% cap | 5% of each payment | 90 days | [Tenn. Code Ann. §§66-34-103(a)-(b), (e)(4), 66-34-104(g)](https://codes.findlaw.com/tn/title-66-property/tn-code-sect-66-34-103.html) |
| [Texas](https://fynex.ai/construction/retainage/texas/) | 10% reserve | 10% on contracts under $5M; 5% on contracts of $5M or more | Per contract | [Tex. Gov't Code §§2252.031-2252.033, 2251.022](https://statutes.capitol.texas.gov/Docs/GV/htm/GV.2252.htm) |
| [Utah](https://fynex.ai/construction/retainage/utah/) | 5% cap | 5% of each payment | 45 days | [Utah Code §13-8-5](https://le.utah.gov/xcode/Title13/Chapter8/C13-8-S5_2023022720230227.html) |
| [Vermont](https://fynex.ai/construction/retainage/vermont/) | No cap | No cap | 30 days | [9 V.S.A. §§4001(3), 4005](https://legislature.vermont.gov/statutes/section/09/102/04005) |
| [Virginia](https://fynex.ai/construction/retainage/virginia/) | No statute | 5% of each payment | Per contract | [Va. Code §§2.2-4333, 2.2-4355(D)](https://law.lis.virginia.gov/vacode/title2.2/chapter43/section2.2-4333/) |
| [Washington](https://fynex.ai/construction/retainage/washington/) | No statute | 5% of each payment | 60 days | [RCW 60.28.011, 60.28.015, 60.28.021, 60.28.030; RCW 39.04.250](https://app.leg.wa.gov/RCW/default.aspx?cite=60.28.011) |
| [West Virginia](https://fynex.ai/construction/retainage/west-virginia/) | No statute | No statute | — | [No retainage section found](https://code.wvlegislature.gov/pdf/38-2/) |
| [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/) | No statute | 5% of each payment | Per contract | [Wis. Stat. §16.855(19)(a)-(b) (state); 66.0901(9)(b) (local)](https://docs.legis.wisconsin.gov/document/statutes/16.855(21)) |
| [Wyoming](https://fynex.ai/construction/retainage/wyoming/) | No statute | 5% of each payment | 41 days | [Wyo. Stat. §§16-6-116(a), 16-6-702(b), 16-6-703, 16-6-704, 16-6-705, 16-6-706](https://wyoleg.gov/statutes/compress/title16.pdf) |

## Related

- [Prompt payment laws in every state](https://fynex.ai/construction/prompt-payment/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law by state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)