Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Alabama retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Alabama retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

On a private Alabama job, an owner may hold no more than 10% of the value of work done, and retainage stops entirely once the job is 50% complete (Ala. Code §8-29-3(i)). The same 10% and 50% limits apply to GC-to-sub and sub-to-sub retainage, and no tier may hold a higher percentage than the tier above it, or it owes 1% per month interest on the excess. The owner must release retainage within 60 days after the contractor's work is complete or after substantial completion, whichever comes first, with certificates of occupancy issued (§8-29-3(l)). On a public job the cap is 5%, also ending at 50% completion, and none on Alabama DOT highway work (§39-2-12(c)).

## Retainage on private jobs

| Rule | Alabama law |
|---|---|
| Applies to | Contracts of $10,000 or more ([Ala. Code §8-29-3(f)-(l)](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Retainage cap | 10% of each payment ([Ala. Code §8-29-3(f)-(l)](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| How the cap applies | No more than 10% of the estimated value of work done and stored materials may be retained; after 50% completion, no further retainage may be withheld ([Ala. Code §8-29-3(f)-(l)](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Release deadline | 60 days Owner must release retainage to the contractor no later than 60 days after completion of the contractor's work or 60 days after substantial completion of the project (whichever occurs first), with all necessary certificates of occupancy issued; the contractor then releases each sub's retainage ([Ala. Code §8-29-3(f)-(l)](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| GC passes the sub's share within | 7 days of receiving it ([Ala. Code §8-29-3(f)-(l)](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Interest on late retainage | 1% per month (12% per annum) on retainage held above the 10% cap or above the percentage held by the tier above; general late-payment interest is also 1% per month ([Ala. Code §8-29-3(f)-(l)](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |

## Retainage on public jobs

| Rule | Alabama law |
|---|---|
| Retainage cap | 5% of each payment ([Ala. Code §39-2-12(c), (e)-(g), (i)](https://alison.legislature.state.al.us/code-of-alabama?section=39-2-12)) |
| Release deadline | 35 days Held until final completion and acceptance of all work, then payable 35 days after the contractor presents a certified voucher, release of claims and proof of advertisement; no retainage at all on Alabama DOT highway, bridge and road contracts ([Ala. Code §39-2-12(c), (e)-(g), (i)](https://alison.legislature.state.al.us/code-of-alabama?section=39-2-12)) |
| Interest on late retainage | Interest at the rate assessed for underpayment of taxes under Ala. Code §40-1-44(a) from the day after the 35-day period; prevailing party recovers attorneys' fees, costs and expenses (not for Alabama Building Commission contracts) ([Ala. Code §39-2-12(c), (e)-(g), (i)](https://alison.legislature.state.al.us/code-of-alabama?section=39-2-12)) |
| Retainage bond in lieu | Allowed ([Ala. Code §39-2-12(c), (e)-(g), (i)](https://alison.legislature.state.al.us/code-of-alabama?section=39-2-12)) |
| Applies to local governments | Yes ([Ala. Code §39-2-12(c), (e)-(g), (i)](https://alison.legislature.state.al.us/code-of-alabama?section=39-2-12)) |

## When the GC says it hasn't been paid in Alabama

Alabama's 7-day clock starts when the GC receives payment from the owner for the sub's work, so the statute is built on a pay-when-paid timing rule (Ala. Code §8-29-3(b), (e)). The chapter does not say that a pay-if-paid clause is void or enforceable. The sub can sue only the party it contracted with (§8-29-6), so the remedy against a GC that has not been paid sits in the subcontract, a lien, or a payment-bond claim, not in a direct claim against the owner. Whether a pay-if-paid clause is enforceable is a case-law question the statute text does not resolve.

## After the deadline: what a sub can do in Alabama

When an Alabama pay app or retainage is late, a sub (1) checks that the contract exceeds $10,000 and is not a 16-unit-or-smaller residential project; (2) confirms it billed early enough for the GC to include it in the GC's own pay request, the condition for the 7-day clock (§8-29-3(b)); (3) sends a written demand for the balance plus 1% per month interest (12% a year); (4) checks whether the GC gave written notice of a bona fide dispute within 5 days (§8-29-4(c)); (5) sues the party it contracted with, which carries attorneys' fees and costs for the winner (§8-29-6), and preserves its lien and bond rights on separate deadlines.

## Alabama quirks to know

Alabama is one of the few states where private retainage simply stops at 50% completion: the 10% (private) and 5% (public) caps apply to work done up to that point, so on a $480,000 contract the most that can ever be held is 10% of $240,000. The release clock is the earlier of 60 days after the contractor's work or 60 days after substantial completion, and the certificates of occupancy must be in hand. Payment may be conditioned on a full lien release for the amount paid (§8-29-3(n)). Interest cannot be waived before payment is due (§8-29-5). The chapter excludes residential homebuilders and public contracts, so public subs rely on §39-2-12 and bond claims under §39-1-1.

## Worked example: retainage on a $480,000 subcontract in Alabama

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 10% = $48,000 |
| Completion | June 15, 2026 |
| Private job: owner releases by | August 14, 2026 ([Ala. Code §8-29-3(f)-(l)](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| GC pays the sub's share by | August 21, 2026 ([Ala. Code §8-29-3(f)-(l)](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Private job at the 10% cap. Retainage stops at 50% completion, so the most that can be held is 10% x $240,000 (half the contract) = $24,000, not $48,000. If the contractor's work is complete on 2026-06-15 and certificates of occupancy are issued, the owner must release by 2026-08-14 (60 days, §8-29-3(l)). If released on 2026-10-14, two months late, interest at 1% per month (§8-29-3(d)) is 2 x 1% x $24,000 = $480. The GC then owes each sub its share within 7 days after the GC receives the money (§8-29-3(e)). On a public contract the cap would be 5% x $240,000 = $12,000.

## Alabama retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/alabama/#calculator. The statutory figures it starts from:

- **Private job:** 60 days (Owner must release retainage to the contractor no later than 60 days after completion of the contractor's work or 60 days after substantial completion of the project (whichever occurs first), with all necessary certificates of occupancy issued; the contractor then releases each sub's retainage); then 7 days for the GC to pay the sub; interest: 1% per month (12% per annum) on retainage held above the 10% cap or above the percentage held by the tier above; general late-payment interest is also 1% per month.
- **Public job:** 35 days (Held until final completion and acceptance of all work, then payable 35 days after the contractor presents a certified voucher, release of claims and proof of advertisement; no retainage at all on Alabama DOT highway, bridge and road contracts); interest: Interest at the rate assessed for underpayment of taxes under Ala. Code §40-1-44(a) from the day after the 35-day period; prevailing party recovers attorneys' fees, costs and expenses (not for Alabama Building Commission contracts).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Alabama retainage law: questions

### What is the maximum retainage on a private Alabama job?

10% of the estimated value of work properly done and materials stored; after 50% completion no further retainage may be withheld (Ala. Code §8-29-3(i)-(k)). A tier cannot hold a higher percentage than the tier above it (§8-29-3(f)-(g)).

### When must an Alabama owner release retainage?

No later than 60 days after the contractor's work is completed or 60 days after substantial completion, whichever occurs first, with all necessary certificates of occupancy issued (Ala. Code §8-29-3(l)). The contractor then releases subs' retainage under the same chapter.

### What is the retainage cap on Alabama public works?

5% of the estimated work done, ending at 50% completion, and none on Alabama DOT highway, bridge or road contracts (Ala. Code §39-2-12(c)). Final payment, including retainage, is due 35 days after the contractor's voucher, release and proof of advertisement (§39-2-12(i)).

## Sources

- [Ala. Code §8-29-3(f)-(l)](https://alison.legislature.state.al.us/code-of-alabama?section=8-29-3)
- [Ala. Code §39-2-12(c), (e)-(g), (i)](https://alison.legislature.state.al.us/code-of-alabama?section=39-2-12)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Alabama prompt payment law](https://fynex.ai/construction/prompt-payment/alabama/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- Alabama
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)