Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Alaska retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Alaska retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Alaska regulates public-job retainage but not private. On public construction the state or political subdivision owes the prime interest on retainage, including warranty retainage, at the 10.5% legal rate from the date a pay request is approved (AS 36.90.250), and each subcontract must require the prime to pay subs all retainage within 8 working days after final payment is received or after the 90-day bond-notice period expires, whichever is later (AS 36.90.210(a)(2)). Subs are also owed interest on retainage held. No Alaska statute caps the percentage retained, on public or private work; the contract sets it.

## Retainage on private jobs

**No statute.** Alaska statutes contain no private-job retainage cap, release deadline, interest rule or lien-fund reserve. The contract governs the percentage and the release trigger; the 10.5% legal rate (AS 45.45.010(a)) applies to money due and unpaid unless the contract sets a rate.

## Retainage on public jobs

| Rule | Alaska law |
|---|---|
| Retainage cap | No statutory cap |
| Release deadline | Prime pays each sub all retainage due within 8 working days after final payment is received from the state or political subdivision, or after the notice period under AS 36.25.020(b) expires, whichever is later; sub-tier retainage within 8 working days after the sub receives its share ([Alaska Stat. §§36.90.210(a)(2), (a)(4), (b)(2), (b)(4); 36.90.250](https://www.akleg.gov/basis/statutes.asp?media=print&secStart=36.90.200&secEnd=36.90.260)) |
| Prime passes the sub's share within | 8 days of receiving it ([Alaska Stat. §§36.90.210(a)(2), (a)(4), (b)(2), (b)(4); 36.90.250](https://www.akleg.gov/basis/statutes.asp?media=print&secStart=36.90.200&secEnd=36.90.260)) |
| Interest on late retainage | State or political subdivision pays the prime interest on retainage (including warranty retainage) at the 10.5% legal rate from the date a pay request is approved to the date of payment; the prime must pay subs interest on retainage at the same rate ([Alaska Stat. §§36.90.210(a)(2), (a)(4), (b)(2), (b)(4); 36.90.250](https://www.akleg.gov/basis/statutes.asp?media=print&secStart=36.90.200&secEnd=36.90.260)) |
| Applies to local governments | Yes ([Alaska Stat. §§36.90.210(a)(2), (a)(4), (b)(2), (b)(4); 36.90.250](https://www.akleg.gov/basis/statutes.asp?media=print&secStart=36.90.200&secEnd=36.90.260)) |

No statutory cap on the percentage retained on a public job appears in AS 36.25, AS 36.30 or AS 36.90; the amount is set by the contract documents. The statute regulates interest and the sub pass-through, not the rate.

## When the GC says it hasn't been paid in Alaska

On public jobs the sub's 8-working-day clock starts when the prime receives payment from the state or political subdivision (AS 36.90.210(a)(1)), a pay-when-paid timing rule. A prime may withhold from a sub for unsatisfactory performance only if the subcontract allows it and the prime gives a written notice stating the amount, the cause and the cure, with a copy to the contracting officer, before the sub's due date (AS 36.90.230, .240). A prime that skips the notice owes interest from the 8th working day. The statute does not address pay-if-paid clauses, and on private jobs there is no statutory rule at all.

## After the deadline: what a sub can do in Alaska

An Alaska public-job sub whose payment or retainage is late (1) checks the prime has received payment from the owner and that the 8 working days have passed; (2) checks whether the prime sent the written AS 36.90.240 withholding notice; (3) demands payment plus interest at 10.5% from the day after the due date; (4) calendars the payment-bond clock: a person suing the prime's payment bond must be unpaid 90 days after the last labor or material, and a sub-tier person must serve notice within 90 days (AS 36.25.020), and the suit must start within one year after final settlement. Contract waivers of these rights are void (AS 36.90.270).

## Alaska quirks to know

The interest clock is split: the owner's interest on a late payment to the prime starts the 21st calendar day after the payment date, while the prime's interest to a sub starts the day after its payment date. The owner's interest obligation does not apply to retainage under the late-payment section, but separate interest on retainage runs from pay-request approval (AS 36.90.200(f), .250). A political subdivision with a population under 800 is outside the public prompt-payment rules, and one with 500 or fewer people is exempt from retainage interest. Grant-funded or state-funded subdivision projects trigger the 21-day-from-receipt-of-funds rule. 'Working day' excludes weekends and state holidays.

## Worked example: retainage on a $480,000 subcontract in Alaska

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 10% = $48,000 |
| Completion | June 15, 2026 |
| Release deadline | No statutory deadline in Alaska; the contract sets it |

Public job; Alaska sets no cap, so the 10% here is an assumed contract percentage = $48,000. Suppose the state pays the prime final payment on 2026-06-15. The prime owes the sub's share within 8 working days after that, or after the AS 36.25.020(b) 90-day notice period ends (about 2026-09-13 if labor ended 2026-06-15), whichever is later. If the sub's $48,000 retainage is paid late, interest is 10.5% a year = $5,040 a year, about $13.81 a day ($48,000 x 10.5% / 365). Owed from the day after the due date (AS 36.90.210(a)(3), (a)(4)). On a private job there is no statutory clock, cap or interest rate beyond the 10.5% legal rate.

## Alaska retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/alaska/#calculator. The statutory figures it starts from:

- **Private job:** no statutory deadline; no fixed statutory interest rate.
- **Public job:** no statutory deadline; then 8 days for the GC to pay the sub; interest: State or political subdivision pays the prime interest on retainage (including warranty retainage) at the 10.5% legal rate from the date a pay request is approved to the date of payment; the prime must pay subs interest on retainage at the same rate.

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Alaska retainage law: questions

### When is retainage paid to a sub on an Alaska public project?

Within 8 working days after the prime receives final payment, or after the 90-day AS 36.25.020(b) notice period expires, whichever is later, and the sub is owed interest on retainage held (AS 36.90.210(a)(2), (a)(4)).

### Is there a cap on retainage in Alaska?

None appears in the statutes read (AS 36.25, 36.30, 36.90 and 34.35). Retainage percentage is set by the contract documents; the statute only regulates interest and release timing on public work.

## Sources

- [Alaska Stat. §§36.90.210(a)(2), (a)(4), (b)(2), (b)(4); 36.90.250](https://www.akleg.gov/basis/statutes.asp?media=print&secStart=36.90.200&secEnd=36.90.260)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Alaska prompt payment law](https://fynex.ai/construction/prompt-payment/alaska/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- Alaska
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)