Construction · Retainage law

Arizona retainage law: cap, release deadline and interest

Arizona's private-job retainage rule is about timing and fairness, not a cap. An owner may withhold a reasonable amount for retention and must release it within 7 days after the retention billing is certified and approved, which happens automatically 14 days after the owner receives it unless the owner issues a written statement of reasons (A.R.S. §§32-1182(D), (H), (I)). The owner may hold back up to 150% of its direct cost to fix incomplete work. No GC or sub may hold more retention from a sub than the owner holds for that sub's work (§32-1183(D)). On local public works, retention is 10% until the contract is 50% complete, then at most 5%, with the remainder due within 60 days after completion (A.R.S. §34-221).

Also in Arizona: prompt payment law

Arizona retainage release date and interest calculator

Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from Arizona law; change them if your contract or the statute's trigger differs.

Job type

Clock starts: On substantial completion the contractor submits a billing for release of retention; it is deemed certified and approved 14 days after the owner receives it, and the owner must pay within 7 days after that (unless the contract extends the clock with the statutory legend). The owner may hold back up to 150% of its reasonable direct cost to fix incomplete work

Statute: 1.5% per month or fraction of a month on retention not released on time; 150% withholding limit for incomplete or disputed work; a GC or sub may not hold more retention from a sub than the owner holds for that sub's work

Owner releases by
July 6, 2026
GC pays the sub's share by
July 13, 2026
Days late
30
Interest owed
—
Total now owed
$48,000.00

No fixed statutory rate: enter the rate from the statute or your contract.

Statute: A.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Retainage on private jobs

RuleArizona law
Retainage capNo statutory cap; the contract sets the rate
Release deadline21 days On substantial completion the contractor submits a billing for release of retention; it is deemed certified and approved 14 days after the owner receives it, and the owner must pay within 7 days after that (unless the contract extends the clock with the statutory legend). The owner may hold back up to 150% of its reasonable direct cost to fix incomplete workA.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)
GC passes the sub's share within7 days of receiving itA.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)
Interest on late retainage1.5% per month or fraction of a month on retention not released on time; 150% withholding limit for incomplete or disputed work; a GC or sub may not hold more retention from a sub than the owner holds for that sub's workA.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)

The statute allows an owner to withhold 'a reasonable amount for retention' and sets no percentage cap; the contract sets the rate. Retention is defined as a portion of a progress payment withheld under the contract to ensure performance.

Retainage on public jobs

RuleArizona law
Retainage cap10% (Until the contract is 50% complete); 5% (On payments after 50% completion, if satisfactory progress; 10% reinstated if not)A.R.S. §34-221(C)(2)-(6), (G)-(K)
Release deadline60 days At 50% completion, half of the retained amount is paid on request if progress is satisfactory; the remaining retention is paid within 60 days after completion or filing of the notice of completion (a longer hold needs a written finding of reasons)A.R.S. §34-221(C)(2)-(6), (G)-(K)
Prime passes the sub's share within7 days of receiving itA.R.S. §34-221(C)(2)-(6), (G)-(K)
Interest on late retainage1% per month or fraction of a month on late payments to the contractor (A.R.S. §34-221(J)); sub-tier interest at 1% per month starting on the eighth day after receipt (A.R.S. §34-221(K))A.R.S. §34-221(C)(2)-(6), (G)-(K)
Retainage bond in lieuAllowedA.R.S. §34-221(C)(2)-(6), (G)-(K)
Applies to local governmentsYesA.R.S. §34-221(C)(2)-(6), (G)-(K)

When the GC says it hasn't been paid in Arizona

Arizona says performance entitles a contractor, sub or supplier to payment from the party it contracts with (A.R.S. §32-1183(A)). The 7-day clock runs from the GC's receipt of payment, but if the owner declines to approve part of a billing for defective work, the GC must still pay each sub whose work was not the cause within 21 days after the owner's payment would have been due (§32-1183(G)). The GC must send the sub the owner's written refusal within 7 days (§32-1183(F)). A clause barring a sub from suspending performance or terminating after nonpayment is void (§32-1186(A)(2)); the subcontractor may stop work for nonpayment under §32-1185.

After the deadline: what a sub can do in Arizona

An Arizona sub whose pay app or retention is past the 7-day mark (1) confirms it sent a billing and a conditional lien waiver (required before the GC's duty arises); (2) checks whether the GC sent a written statement of reasons within 14 days (§32-1183(E)); (3) demands payment plus 1.5% per month, running from the eighth day; (4) may file a complaint with the Registrar of Contractors, which requires a surety bond or cash deposit of $500 or half the amount due, whichever is less (§32-1183(I)); (5) may suspend performance or terminate under §32-1185 after notice, and (6) sues or arbitrates, where the winner recovers fees under §32-1183(J). Lien and bond rights run on separate deadlines.

Arizona quirks to know

Arizona's prompt-pay act does not apply to the state or its political subdivisions (A.R.S. §32-1187); public jobs follow A.R.S. §34-221, which applies to counties, cities and towns, districts and similar local bodies (A.R.S. §34-101). Owner-occupant dwellings are carved out of the owner-pay rules unless the contractor puts a prescribed notice on the front page of each billing (§32-1188). Contract terms can extend the 14-day approval and 7-day payment periods, but only with a conspicuous 'Notice of Extended Payment Provision' legend on every page of the plans (§32-1182(B), (C), (F)). Public-works retention reverts to 10% if the owner finds progress unsatisfactory after 50% completion (§34-221(C)(3)). Forum clauses moving disputes out of state are void (§32-1186).

Worked example: retainage on a $480,000 subcontract in Arizona

Subcontract$480,000
Retainage held10% = $48,000
CompletionJune 15, 2026
Private job: owner releases byJuly 6, 2026A.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)
GC pays the sub's share byJuly 13, 2026A.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)
Interest if paid 30 days lateNo statutory rate; the contract governs

Private job; Arizona sets no cap, so assume the contract holds 10% = $48,000. The contractor bills for retention release on substantial completion, 2026-06-15; the billing is deemed approved 14 days later (2026-06-29) and payment is due 7 days after that (2026-07-06) under A.R.S. §32-1182(H)-(I). If the owner pays on 2026-10-06, three months late, interest at 1.5% per month is 3 x 1.5% x $48,000 = $2,160, plus fees for the winner. The GC then has 7 days after receiving the money to pay the sub (§32-1183(B)). On a local public job with the same 10% retention, the balance would be due within 60 days after completion or notice of completion: 2026-08-14.

Run a payment like this in the split calculator

Arizona retainage law: questions

Is there a retainage cap on private construction in Arizona?

No percentage cap. The owner may withhold 'a reasonable amount for retention' from progress payments (A.R.S. §32-1182(D)). A GC or sub cannot withhold more from a sub than the owner holds for that sub's work (§32-1183(D)).

When must an Arizona owner release retention on a private job?

Within 7 days after the retention billing is certified and approved; the billing is deemed approved 14 days after the owner receives it unless the owner issues a written statement of reasons (A.R.S. §32-1182(H), (I)). The owner may hold back up to 150% of its direct cost to fix incomplete work.

What is the retention rate on Arizona local public works?

10% of each estimate until the contract is 50% complete; after that, no more than 5% of later payments, and half of the amount retained is returned at 50% on request if progress is satisfactory (A.R.S. §34-221(C)(2)-(3)). The balance is due within 60 days after completion.

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.