---
title: "Arizona Retainage Law (2026): Cap, Release Deadline & Interest"
description: "Arizona retainage: no private cap, but release within 21 days; public jobs cap 5–10%, release within 60 days. Statute, release dates and a calculator."
url: "/construction/retainage/arizona/"
updated: "2026-10-13"
---

Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Arizona retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Arizona retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Arizona's private-job retainage rule is about timing and fairness, not a cap. An owner may withhold a reasonable amount for retention and must release it within 7 days after the retention billing is certified and approved, which happens automatically 14 days after the owner receives it unless the owner issues a written statement of reasons (A.R.S. §§32-1182(D), (H), (I)). The owner may hold back up to 150% of its direct cost to fix incomplete work. No GC or sub may hold more retention from a sub than the owner holds for that sub's work (§32-1183(D)). On local public works, retention is 10% until the contract is 50% complete, then at most 5%, with the remainder due within 60 days after completion (A.R.S. §34-221).

## Retainage on private jobs

| Rule | Arizona law |
|---|---|
| Retainage cap | No statutory cap; the contract sets the rate |
| Release deadline | 21 days On substantial completion the contractor submits a billing for release of retention; it is deemed certified and approved 14 days after the owner receives it, and the owner must pay within 7 days after that (unless the contract extends the clock with the statutory legend). The owner may hold back up to 150% of its reasonable direct cost to fix incomplete work ([A.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)](https://www.azleg.gov/ars/32/01182.htm)) |
| GC passes the sub's share within | 7 days of receiving it ([A.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)](https://www.azleg.gov/ars/32/01182.htm)) |
| Interest on late retainage | 1.5% per month or fraction of a month on retention not released on time; 150% withholding limit for incomplete or disputed work; a GC or sub may not hold more retention from a sub than the owner holds for that sub's work ([A.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)](https://www.azleg.gov/ars/32/01182.htm)) |

The statute allows an owner to withhold 'a reasonable amount for retention' and sets no percentage cap; the contract sets the rate. Retention is defined as a portion of a progress payment withheld under the contract to ensure performance.

## Retainage on public jobs

| Rule | Arizona law |
|---|---|
| Retainage cap | 10% (Until the contract is 50% complete); 5% (On payments after 50% completion, if satisfactory progress; 10% reinstated if not) ([A.R.S. §34-221(C)(2)-(6), (G)-(K)](https://www.azleg.gov/ars/34/00221.htm)) |
| Release deadline | 60 days At 50% completion, half of the retained amount is paid on request if progress is satisfactory; the remaining retention is paid within 60 days after completion or filing of the notice of completion (a longer hold needs a written finding of reasons) ([A.R.S. §34-221(C)(2)-(6), (G)-(K)](https://www.azleg.gov/ars/34/00221.htm)) |
| Prime passes the sub's share within | 7 days of receiving it ([A.R.S. §34-221(C)(2)-(6), (G)-(K)](https://www.azleg.gov/ars/34/00221.htm)) |
| Interest on late retainage | 1% per month or fraction of a month on late payments to the contractor (A.R.S. §34-221(J)); sub-tier interest at 1% per month starting on the eighth day after receipt (A.R.S. §34-221(K)) ([A.R.S. §34-221(C)(2)-(6), (G)-(K)](https://www.azleg.gov/ars/34/00221.htm)) |
| Retainage bond in lieu | Allowed ([A.R.S. §34-221(C)(2)-(6), (G)-(K)](https://www.azleg.gov/ars/34/00221.htm)) |
| Applies to local governments | Yes ([A.R.S. §34-221(C)(2)-(6), (G)-(K)](https://www.azleg.gov/ars/34/00221.htm)) |

## When the GC says it hasn't been paid in Arizona

Arizona says performance entitles a contractor, sub or supplier to payment from the party it contracts with (A.R.S. §32-1183(A)). The 7-day clock runs from the GC's receipt of payment, but if the owner declines to approve part of a billing for defective work, the GC must still pay each sub whose work was not the cause within 21 days after the owner's payment would have been due (§32-1183(G)). The GC must send the sub the owner's written refusal within 7 days (§32-1183(F)). A clause barring a sub from suspending performance or terminating after nonpayment is void (§32-1186(A)(2)); the subcontractor may stop work for nonpayment under §32-1185.

## After the deadline: what a sub can do in Arizona

An Arizona sub whose pay app or retention is past the 7-day mark (1) confirms it sent a billing and a conditional lien waiver (required before the GC's duty arises); (2) checks whether the GC sent a written statement of reasons within 14 days (§32-1183(E)); (3) demands payment plus 1.5% per month, running from the eighth day; (4) may file a complaint with the Registrar of Contractors, which requires a surety bond or cash deposit of $500 or half the amount due, whichever is less (§32-1183(I)); (5) may suspend performance or terminate under §32-1185 after notice, and (6) sues or arbitrates, where the winner recovers fees under §32-1183(J). Lien and bond rights run on separate deadlines.

## Arizona quirks to know

Arizona's prompt-pay act does not apply to the state or its political subdivisions (A.R.S. §32-1187); public jobs follow A.R.S. §34-221, which applies to counties, cities and towns, districts and similar local bodies (A.R.S. §34-101). Owner-occupant dwellings are carved out of the owner-pay rules unless the contractor puts a prescribed notice on the front page of each billing (§32-1188). Contract terms can extend the 14-day approval and 7-day payment periods, but only with a conspicuous 'Notice of Extended Payment Provision' legend on every page of the plans (§32-1182(B), (C), (F)). Public-works retention reverts to 10% if the owner finds progress unsatisfactory after 50% completion (§34-221(C)(3)). Forum clauses moving disputes out of state are void (§32-1186).

## Worked example: retainage on a $480,000 subcontract in Arizona

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 10% = $48,000 |
| Completion | June 15, 2026 |
| Private job: owner releases by | July 6, 2026 ([A.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)](https://www.azleg.gov/ars/32/01182.htm)) |
| GC pays the sub's share by | July 13, 2026 ([A.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)](https://www.azleg.gov/ars/32/01182.htm)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Private job; Arizona sets no cap, so assume the contract holds 10% = $48,000. The contractor bills for retention release on substantial completion, 2026-06-15; the billing is deemed approved 14 days later (2026-06-29) and payment is due 7 days after that (2026-07-06) under A.R.S. §32-1182(H)-(I). If the owner pays on 2026-10-06, three months late, interest at 1.5% per month is 3 x 1.5% x $48,000 = $2,160, plus fees for the winner. The GC then has 7 days after receiving the money to pay the sub (§32-1183(B)). On a local public job with the same 10% retention, the balance would be due within 60 days after completion or notice of completion: 2026-08-14.

## Arizona retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/arizona/#calculator. The statutory figures it starts from:

- **Private job:** 21 days (On substantial completion the contractor submits a billing for release of retention; it is deemed certified and approved 14 days after the owner receives it, and the owner must pay within 7 days after that (unless the contract extends the clock with the statutory legend). The owner may hold back up to 150% of its reasonable direct cost to fix incomplete work); then 7 days for the GC to pay the sub; interest: 1.5% per month or fraction of a month on retention not released on time; 150% withholding limit for incomplete or disputed work; a GC or sub may not hold more retention from a sub than the owner holds for that sub's work.
- **Public job:** 60 days (At 50% completion, half of the retained amount is paid on request if progress is satisfactory; the remaining retention is paid within 60 days after completion or filing of the notice of completion (a longer hold needs a written finding of reasons)); then 7 days for the GC to pay the sub; interest: 1% per month or fraction of a month on late payments to the contractor (A.R.S. §34-221(J)); sub-tier interest at 1% per month starting on the eighth day after receipt (A.R.S. §34-221(K)).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Arizona retainage law: questions

### Is there a retainage cap on private construction in Arizona?

No percentage cap. The owner may withhold 'a reasonable amount for retention' from progress payments (A.R.S. §32-1182(D)). A GC or sub cannot withhold more from a sub than the owner holds for that sub's work (§32-1183(D)).

### When must an Arizona owner release retention on a private job?

Within 7 days after the retention billing is certified and approved; the billing is deemed approved 14 days after the owner receives it unless the owner issues a written statement of reasons (A.R.S. §32-1182(H), (I)). The owner may hold back up to 150% of its direct cost to fix incomplete work.

### What is the retention rate on Arizona local public works?

10% of each estimate until the contract is 50% complete; after that, no more than 5% of later payments, and half of the amount retained is returned at 50% on request if progress is satisfactory (A.R.S. §34-221(C)(2)-(3)). The balance is due within 60 days after completion.

## Sources

- [A.R.S. §§32-1182(D), (H), (I), (Q); 32-1183(B), (D), (H)](https://www.azleg.gov/ars/32/01182.htm)
- [A.R.S. §34-221(C)(2)-(6), (G)-(K)](https://www.azleg.gov/ars/34/00221.htm)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Arizona prompt payment law](https://fynex.ai/construction/prompt-payment/arizona/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- Arizona
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)
