Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Arkansas retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Arkansas retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Arkansas regulates retainage only on public work. Where a public agency (the state, a political subdivision, or a nonprofit using public funds) requires the prime to furnish a performance and payment bond, the prime is paid 95% of earned progress payments and the agency may hold 5%; the agency may stop holding at 50% completion if the work is satisfactory, and must pay everything it withheld within 30 days after the contract is completed (Ark. Code §22-9-604). A sub the prime requires to be bonded gets the same 95%/5% split, and once it completes 50% of its subcontract the prime, on its approval, retains nothing further. No retainage may be held on required stored materials. There is no statute for private jobs; the contract sets the percentage and the release date.

## Retainage on private jobs

**No statute.** Arkansas's retainage statute (Ark. Code §22-9-601 et seq.) governs only construction contracts between a public agency and a prime contractor, and the subcontracts under them. No cap, release deadline or interest rule for private-job retainage was found; the contract governs, and §22-9-604's 5% and 30-day rules do not apply to private owners. No lien-fund reserve exists.

## Retainage on public jobs

| Rule | Arkansas law |
|---|---|
| Retainage cap | 5% of each payment ([Ark. Code §22-9-604 (text as rewritten by Act 866 of 2015, the last amendment); §§22-9-601 to 22-9-603 (definitions, scope, non-waiver; mirror text only)](https://arkleg.state.ar.us/Acts/FTPDocument?path=%2FACTS%2F2015R%2FPublic%2F&file=866.pdf&ddBienniumSession=2015%2F2015R)) |
| Release deadline | 30 days Where the prime is required to furnish a performance and payment bond, it is paid 95% of earned progress payments and the agency retains 5%. All sums withheld by the public agency are paid to the contractor within 30 days after the construction contract has been completed. The agency may forgo retainage once the contract is 50% complete, if the work is satisfactory and the design professional and agency agree (it may also keep withholding throughout). Phased jobs with partial occupancy release retainage within 30 days in proportion to the completed part. No retainage on stored materials or equipment the contract requires the contractor to buy. ([Ark. Code §22-9-604 (text as rewritten by Act 866 of 2015, the last amendment); §§22-9-601 to 22-9-603 (definitions, scope, non-waiver; mirror text only)](https://arkleg.state.ar.us/Acts/FTPDocument?path=%2FACTS%2F2015R%2FPublic%2F&file=866.pdf&ddBienniumSession=2015%2F2015R)) |
| Interest on late retainage | Not set by statute |
| Applies to local governments | Yes ([Ark. Code §22-9-604 (text as rewritten by Act 866 of 2015, the last amendment); §§22-9-601 to 22-9-603 (definitions, scope, non-waiver; mirror text only)](https://arkleg.state.ar.us/Acts/FTPDocument?path=%2FACTS%2F2015R%2FPublic%2F&file=866.pdf&ddBienniumSession=2015%2F2015R)) |

## When the GC says it hasn't been paid in Arkansas

Arkansas statutes do not regulate when a GC must pay its subs, so the subcontract and the pay-if-paid or pay-when-paid language in it decide. Secondary summaries say Arkansas courts enforce a pay-if-paid clause when it is clear and unambiguous, but this was not checked against case law here. A sub on a public job can sue on the payment bond, and on a private job its statutory tool is the mechanic's lien; neither is covered by the payment sections read.

## After the deadline: what a sub can do in Arkansas

An Arkansas sub with unpaid money first reads its subcontract for the payment trigger, because the state sets none. On a public job a sub (1) confirms the agency has paid the prime (agencies have 5 working days per processing party on state projects, or 90 days on a completion claim); (2) checks the retainage deadline of 30 days after completion under §22-9-604(c) for the prime's own recovery; (3) demands payment and any contractual interest from the prime; and (4) preserves payment-bond and lien rights on separate deadlines not covered here.

## Arkansas quirks to know

Arkansas is a minimal-statute state: only public-agency contracts carry retainage and payment-timing rules, and the parties cannot waive the retainage subchapter by agreement (Ark. Code §22-9-603). The retainage subchapter excludes State Highway Commission road and highway contracts (§22-9-602). 'Public agency' includes nonprofit corporations that receive public funds, so a grant-funded nonprofit's construction project can fall under the 5% rule. The subcontract-level 5% limit applies only to a sub the prime requires to furnish a performance and payment bond (§22-9-604(b)).

## Worked example: retainage on a $480,000 subcontract in Arkansas

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Public job: owner releases by | July 15, 2026 ([Ark. Code §22-9-604 (text as rewritten by Act 866 of 2015, the last amendment); §§22-9-601 to 22-9-603 (definitions, scope, non-waiver; mirror text only)](https://arkleg.state.ar.us/Acts/FTPDocument?path=%2FACTS%2F2015R%2FPublic%2F&file=866.pdf&ddBienniumSession=2015%2F2015R)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Public job under Ark. Code §22-9-604: the agency may hold 5% = $24,000 (it pays 95% of each progress payment). If the project is complete on 2026-06-15, all sums withheld are due to the contractor within 30 days, by 2026-07-15 (§22-9-604(c)). A completion claim not paid within 90 days of presentation (2026-09-13 if presented 2026-06-15) bears 10% per annum, $24,000 x 10% / 365 = about $6.58 a day after that date (§22-9-205). A bonded sub would see the same 5% limit, and the prime may stop retaining at 50% of the subcontract if it approves. On a private job none of these figures applies; the contract sets them.

## Arkansas retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/arkansas/#calculator. The statutory figures it starts from:

- **Private job:** no statutory deadline; no fixed statutory interest rate.
- **Public job:** 30 days (Where the prime is required to furnish a performance and payment bond, it is paid 95% of earned progress payments and the agency retains 5%. All sums withheld by the public agency are paid to the contractor within 30 days after the construction contract has been completed. The agency may forgo retainage once the contract is 50% complete, if the work is satisfactory and the design professional and agency agree (it may also keep withholding throughout). Phased jobs with partial occupancy release retainage within 30 days in proportion to the completed part. No retainage on stored materials or equipment the contract requires the contractor to buy.); no fixed statutory interest rate.

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Arkansas retainage law: questions

### Does Arkansas cap retainage on private construction?

No statute was found that does. Ark. Code §22-9-604's 5% retainage rule applies only to contracts between a public agency and a prime contractor and the bonded subcontracts under them. On private jobs the contract sets the percentage.

### What is the retainage cap on Arkansas public works?

5% of earned progress payments (the contractor receives 95%), under Ark. Code §22-9-604(a). The agency may stop withholding at 50% completion if work is satisfactory and the design professional and agency approve.

### How long does an Arkansas public agency have to release retainage?

Within 30 days after the construction contract has been completed (Ark. Code §22-9-604(c)). On phased projects with partial occupancy, retainage is partially released within 30 days in direct proportion to the completed part (§22-9-604(a)(2)).

## Sources

- [Ark. Code §22-9-604 (text as rewritten by Act 866 of 2015, the last amendment); §§22-9-601 to 22-9-603 (definitions, scope, non-waiver; mirror text only)](https://arkleg.state.ar.us/Acts/FTPDocument?path=%2FACTS%2F2015R%2FPublic%2F&file=866.pdf&ddBienniumSession=2015%2F2015R)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Arkansas prompt payment law](https://fynex.ai/construction/prompt-payment/arkansas/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- Arkansas
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)