Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Colorado retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Colorado retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Colorado caps retainage at 5% on both public and private jobs over the $150,000 line. On public contracts the entity must pay at least 95% of the calculated value of completed work, and it makes final settlement within 60 days after the work is completed and finally accepted (C.R.S. §24-91-103). On private contracts of $150,000 or more, no owner, GC or sub may withhold more than 5% of the price of the work completed, and the cap runs down to every subcontract and supply agreement regardless of its size (C.R.S. §§38-46-102, 38-46-103). From August 2026, on new private contracts, a GC or sub can post a retainage bond instead and the payer must release the cash (HB26-1311). Release timing stays in the contract.

## Retainage on private jobs

| Rule | Colorado law |
|---|---|
| Applies to | Contracts of $150,000 or more ([C.R.S. §§38-46-101 to 38-46-104 (enacted by HB21-1167; §38-46-101(2.5), (4.5) and §38-46-103(1)(b) added by HB26-1311, signed 2026-05-07)](https://leg.colorado.gov/laws/session-laws/HB26-1311/129/download)) |
| Retainage cap | 5% of each payment ([C.R.S. §§38-46-101 to 38-46-104 (enacted by HB21-1167; §38-46-101(2.5), (4.5) and §38-46-103(1)(b) added by HB26-1311, signed 2026-05-07)](https://leg.colorado.gov/laws/session-laws/HB26-1311/129/download)) |
| Release deadline | Not set by statute; the contract controls timing of payment including final payment (§38-46-103(2)). The 5% cap on the price of work completed applies to private contracts of $150,000 or more between a private property owner and a contractor, and to every subcontract and supply agreement under such a contract regardless of the subcontract's own price ([C.R.S. §§38-46-101 to 38-46-104 (enacted by HB21-1167; §38-46-101(2.5), (4.5) and §38-46-103(1)(b) added by HB26-1311, signed 2026-05-07)](https://leg.colorado.gov/laws/session-laws/HB26-1311/129/download)) |
| Interest on late retainage | Not set by statute |
| Escrow or bond instead of retainage | Retainage bond in lieu of retainage (HB26-1311, 2026 Colo. Sess. Laws ch. 129, adding C.R.S. §38-46-103(1)(b)): a contractor or sub may tender a surety bond from a Colorado-licensed insurer for up to 5% of the money earned; the owner, contractor or sub must accept a conforming bond and release the retainage it covers. The owner or contractor may require an A.M. Best rating no higher than 'A-'. If the owner accepts a bond from the GC, the GC must accept a like bond from any sub. Not for property owned by a public entity or public-private partnerships. Applies to contracts created on or after the act's effective date (August 12, 2026 if the 2026 session adjourned on May 13, 2026, as the act states). ([C.R.S. §§38-46-101 to 38-46-104 (enacted by HB21-1167; §38-46-101(2.5), (4.5) and §38-46-103(1)(b) added by HB26-1311, signed 2026-05-07)](https://leg.colorado.gov/laws/session-laws/HB26-1311/129/download)) |

## Retainage on public jobs

| Rule | Colorado law |
|---|---|
| Retainage cap | 5% on contracts over $150,000 ([C.R.S. §§24-91-102, 24-91-103, 24-91-104, 24-91-105; §38-26-107](https://colorado.public.law/statutes/crs_24-91-103)) |
| Release deadline | 60 days The public entity pays at least 95% of the calculated value of completed work; the withheld percentage may be held until the contract is completed satisfactorily and finally accepted, and final settlement is made within 60 days after that. The entity may release retainage early on written request when a phase is satisfactory, with surety consent ([C.R.S. §§24-91-102, 24-91-103, 24-91-104, 24-91-105; §38-26-107](https://colorado.public.law/statutes/crs_24-91-103)) |
| Prime passes the sub's share within | 7 days of receiving it ([C.R.S. §§24-91-102, 24-91-103, 24-91-104, 24-91-105; §38-26-107](https://colorado.public.law/statutes/crs_24-91-103)) |
| Interest on late retainage | A prime that fails to pay a sub on time owes the higher of the contract rate or 15% per annum; the statute does not change a contract's retention provisions ([C.R.S. §§24-91-102, 24-91-103, 24-91-104, 24-91-105; §38-26-107](https://colorado.public.law/statutes/crs_24-91-103)) |
| Retainage bond in lieu | Allowed ([C.R.S. §§24-91-102, 24-91-103, 24-91-104, 24-91-105; §38-26-107](https://colorado.public.law/statutes/crs_24-91-103)) |
| Applies to local governments | Yes ([C.R.S. §§24-91-102, 24-91-103, 24-91-104, 24-91-105; §38-26-107](https://colorado.public.law/statutes/crs_24-91-103)) |

## When the GC says it hasn't been paid in Colorado

Colorado's private retainage article expressly preserves pay-if-paid: a provision requiring the contractor to actually receive payment from the owner before it owes a subcontractor or supplier is a condition precedent the statute does not override (C.R.S. §38-46-103(2)(d)). The same article preserves satisfactory-performance conditions and backcharges. On public jobs, the sub's 7-day clock starts when the prime receives payment (C.R.S. §24-91-103(2)), and a prime is relieved of the 7-day and interest duty until the sub gives the list of its suppliers, sub-subs and laborers. A public-job sub can claim against the payment bond and file a verified statement with the public entity before final settlement (C.R.S. §38-26-107).

## After the deadline: what a sub can do in Colorado

A Colorado sub on a public job whose payment is late (1) confirms the prime was paid and the 7 calendar days have run, and that the sub gave its list of suppliers with the pay request; (2) demands payment plus interest at the higher of contract rate or 15% per annum from the due date; (3) files a verified statement of the amount due and unpaid with the public entity before final settlement, which makes the entity withhold funds until the claim is paid or the claimant sues within 90 days after the published final-settlement date (C.R.S. §38-26-107); (4) sues on the bond. On a private job, there is no statutory clock; the sub reads the subcontract and its payment conditions precedent.

## Colorado quirks to know

Colorado's 5% private cap (HB21-1167, C.R.S. title 38, art. 46) covers contracts with a private property owner and excludes a single contract for one single-family dwelling or one multifamily dwelling of up to four units, and any contract with a public entity. The cap attaches to the subcontract regardless of price, so a $20,000 subcontract under a $2M prime is still capped at 5%. A recipient must provide an executed lien waiver for amounts actually paid if the contract requires one (§38-46-104). HB26-1311 (signed May 7, 2026) adds a mandatory-acceptance retainage bond on private contracts created on or after its effective date, with flow-down to subs on a like bond. Public-works retention can be released by depositing acceptable securities on contracts above $150,000 (C.R.S. §24-91-105). In a take-over by the public entity, the retained percentage is due 30 days from final acceptance (C.R.S. §24-91-104).

## Worked example: retainage on a $480,000 subcontract in Colorado

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Public job: owner releases by | August 14, 2026 ([C.R.S. §§24-91-102, 24-91-103, 24-91-104, 24-91-105; §38-26-107](https://colorado.public.law/statutes/crs_24-91-103)) |
| GC pays the sub's share by | August 21, 2026 ([C.R.S. §§24-91-102, 24-91-103, 24-91-104, 24-91-105; §38-26-107](https://colorado.public.law/statutes/crs_24-91-103)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Both the private and public rules cap retainage at 5% of the work completed on a $480,000 contract (over the $150,000 threshold) = $24,000; a 10% contract term is cut to 5% by C.R.S. §38-46-103(1). Public job: if the work is completed and finally accepted on 2026-06-15, final settlement is due within 60 days: 2026-08-14 (C.R.S. §24-91-103(1)(b)), and the prime must pay each sub its share within 7 days of receipt. If the prime passes $24,000 of retainage to its subs 14 days late, interest at the 15% per annum floor (or the contract rate if higher) is $24,000 x 15% x 14/365 = $138.08. Private job: the statute sets no release date, so the date comes from the contract. On a private contract signed after HB26-1311 takes effect, the GC could post a $24,000 retainage bond instead and receive the cash.

## Colorado retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/colorado/#calculator. The statutory figures it starts from:

- **Private job:** no statutory deadline; no fixed statutory interest rate.
- **Public job:** 60 days (The public entity pays at least 95% of the calculated value of completed work; the withheld percentage may be held until the contract is completed satisfactorily and finally accepted, and final settlement is made within 60 days after that. The entity may release retainage early on written request when a phase is satisfactory, with surety consent); then 7 days for the GC to pay the sub; interest: A prime that fails to pay a sub on time owes the higher of the contract rate or 15% per annum; the statute does not change a contract's retention provisions.

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Colorado retainage law: questions

### Is there a retainage cap on private construction in Colorado?

Yes, on contracts of $150,000 or more: no more than 5% of the price of the work completed, and the cap flows down to every subcontract and supply agreement under such a contract (C.R.S. §§38-46-102, 38-46-103). Single-family and small multifamily (up to four units) single contracts and public contracts are excluded.

### When must a Colorado owner release retainage on a private job?

Colorado's statute does not set a date. C.R.S. §38-46-103(2) leaves payment timing, including final payment, to the contract. On public jobs, final settlement is due within 60 days after the work is completed and finally accepted (C.R.S. §24-91-103(1)(b)).

### What is the public-works retainage limit in Colorado?

The public entity must pay at least 95% of the calculated value of completed work on contracts over $150,000, so retainage is capped at 5% (C.R.S. §24-91-103(1)(a)). The contractor can substitute acceptable securities for withheld sums (C.R.S. §24-91-105).

### Can a Colorado contractor post a bond instead of having retainage withheld on a private job?

Yes, on private contracts created on or after HB26-1311's effective date (August 12, 2026 if the session adjourned May 13, 2026). A contractor or sub may tender a retainage bond for up to 5% of the money earned; a conforming bond must be accepted and the retainage it covers released. The payer may require an A.M. Best rating no higher than 'A-' (C.R.S. §38-46-103(1)(b)). It does not apply to publicly owned property.

## Sources

- [C.R.S. §§38-46-101 to 38-46-104 (enacted by HB21-1167; §38-46-101(2.5), (4.5) and §38-46-103(1)(b) added by HB26-1311, signed 2026-05-07)](https://leg.colorado.gov/laws/session-laws/HB26-1311/129/download)
- [C.R.S. §§24-91-102, 24-91-103, 24-91-104, 24-91-105; §38-26-107](https://colorado.public.law/statutes/crs_24-91-103) (mirror; the official site did not load)

Sources marked "mirror" were read from the linked copy on October 13, 2026 because the state's official code site did not load for us. Check the official code before relying on those figures.

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Colorado prompt payment law](https://fynex.ai/construction/prompt-payment/colorado/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- Colorado
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)