Delaware leaves private retainage to the contract: no cap, no release date, no interest rule. The only statutory touch is that an owner or GC may hold a specified percentage of each progress payment without owing the late-payment penalty, if it sends written notice of why payment is withheld within 7 days of the due date (6 Del. C. §3506(a)(3), (d)). On state public works the agency holds 5% of the value of completed work, may release 60% of it on completion, and must pay the balance within 60 days after completion or filing of notice of completion, or give a written finding for the delay (29 Del. C. §6962(d)(5); §6516(f)(3)).

Also in Delaware: prompt payment law

Delaware retainage release date and interest calculator

Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from Delaware law; change them if your contract or the statute's trigger differs.

Job type

Clock starts: Agency may release 60% of the retainage on completion; the balance is held until reports are received, listed-trade subs are paid, and final payment is authorized. Retainage is paid within 60 days after completion or filing notice of completion (or within 30 days of a required federal final approval); a longer hold needs a written finding within 10 days

Statute: Contractor may require interest up to 2% above the Federal Reserve prime rate on final payment delayed more than 60 days after the final submission; sub-tier interest up to the same rate after 21 days

Owner releases by
August 14, 2026
GC pays the sub's share by
September 4, 2026
Days late
30
Interest owed
—
Total now owed
$24,000.00

No fixed statutory rate: enter the rate from the statute or your contract.

Statute: 29 Del. C. §6962(d)(5); §6516(f)(3)-(4), (7)

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Retainage on private jobs

No statute. Delaware does not cap or time private-job retainage. Title 6, ch. 35 only says an owner may retain a specified percentage of each progress payment (and a contractor from subs) without incurring the late-payment interest penalty, if it gives written notice of why payment is withheld within 7 days of the date payment was due. The percentage, the release trigger and the release date are set by the contract. Delaware has no lien-fund reserve. Money received by a contractor on a building job is held in trust for subs and suppliers (6 Del. C. §§3502-3504).

Retainage on public jobs

RuleDelaware law
Retainage cap5% of each payment29 Del. C. §6962(d)(5); §6516(f)(3)-(4), (7)
Release deadline60 days Agency may release 60% of the retainage on completion; the balance is held until reports are received, listed-trade subs are paid, and final payment is authorized. Retainage is paid within 60 days after completion or filing notice of completion (or within 30 days of a required federal final approval); a longer hold needs a written finding within 10 days29 Del. C. §6962(d)(5); §6516(f)(3)-(4), (7)
Prime passes the sub's share within21 days of receiving it29 Del. C. §6962(d)(5); §6516(f)(3)-(4), (7)
Interest on late retainageContractor may require interest up to 2% above the Federal Reserve prime rate on final payment delayed more than 60 days after the final submission; sub-tier interest up to the same rate after 21 days29 Del. C. §6962(d)(5); §6516(f)(3)-(4), (7)
Retainage bond in lieuAllowed29 Del. C. §6962(d)(5); §6516(f)(3)-(4), (7)

When the GC says it hasn't been paid in Delaware

Delaware voids pay-if-paid on private jobs. A contract term stating that a contractor assumes the risk of the owner's nonpayment, or that makes a bond claimant's payment subject to owner payment, is against public policy and unenforceable (6 Del. C. §3507(e)(1), (3)). Money a contractor receives is held in trust and must first pay every person who furnished labor or material, and failure to pay within 30 days of receipt is prima facie evidence of misuse (§§3502-3504), a crime with a fine up to $1,000 or up to 3 years in prison (§3505). Section 3507 does not apply to Delaware public works, where §6516(f)(7) sets a 21-day sub-tier clock.

After the deadline: what a sub can do in Delaware

A Delaware sub with a late payment (1) checks its invoice was disputed or not within 7 days: an invoice with no written dispute in 7 days is deemed accepted (§3508(b)); (2) demands payment and the contract interest penalty at the legal rate; (3) pursues arbitration or suit under §3509, where the tribunal awards damages equal to the wrongfully withheld amount and fees to the substantially prevailing party (arbitration) or the court may award fees if the payment was withheld without good-faith reasonable cause (§3506(e)); (4) on a public job, claims interest from day 22 after the prime's receipt of payment (29 Del. C. §6516(f)(7)). Lien and bond rights run on separate deadlines.

Delaware quirks to know

Delaware's private prompt-pay chapter is also a construction trust-fund statute: money received by a contractor on a building job is a trust fund (6 Del. C. §3502). The payment sections exclude residential projects of 6 or fewer units under simultaneous construction and any single-unit alteration or repair. The 15-day GC-to-sub default applies only where no term is set, while §3506(b) requires a contract clause allowing up to 30 days; parties can opt out of §3508 dispute and §3509 fee rules by contract between GC and sub. Payment to a sub bars later claims against the GC and its surety by the sub's own suppliers (§3506(f)). State public works extend the sub-tier clock to 21 days.

Worked example: retainage on a $480,000 subcontract in Delaware

Subcontract$480,000
Retainage held5% = $24,000
CompletionJune 15, 2026
Public job: owner releases byAugust 14, 202629 Del. C. §6962(d)(5); §6516(f)(3)-(4), (7)
GC pays the sub's share bySeptember 4, 202629 Del. C. §6962(d)(5); §6516(f)(3)-(4), (7)
Interest if paid 30 days lateNo statutory rate; the contract governs

State public works: 5% retainage = $24,000. On completion 2026-06-15 the agency may release 60% ($14,400); the remaining $9,600 is paid within 60 days after completion or notice of completion, by 2026-08-14 (29 Del. C. §6516(f)(3)), unless the agency makes a written finding within 10 days. A sub then has 21 days after the prime receives the money. Interest up to 2% above the Federal Reserve prime rate (current prime not read) can be billed from day 61 after final submission. Private job: Delaware sets no cap or release date; if the contract is silent on payment, a final invoice delivered 2026-06-15 for a billing period ending 2026-06-30 is due 30 days after the later of period end or delivery: 2026-07-30 (§3507(c)), with the GC then owing subs within 15 days of receipt.

Run a payment like this in the split calculator

Delaware retainage law: questions

Is there a retainage cap on private construction in Delaware?

No. Delaware's private construction payment chapter (6 Del. C. ch. 35) allows an owner or contractor to retain a specified percentage of each progress payment but sets no maximum, no release date and no interest rate for retainage (§3506(a)(3), (d)). The contract controls.

What is the retainage rate on Delaware state public works?

5% of the value of work completed, set in the bid documents. The agency may release 60% on completion and must pay the balance within 60 days after completion or filing of notice of completion, unless it makes a written finding for a longer hold (29 Del. C. §6962(d)(5); §6516(f)(3)).