Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Florida retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Florida retainage law: cap, release deadline and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

Florida caps retainage only on public jobs. A state or local public entity may withhold at most 5% of each progress payment on contracts over $200,000, and must pay the balance plus retainage within 20 business days after the punchlist is developed, less 150% of the cost to finish listed items (Fla. Stat. §§255.078, 255.077, 218.735). On private jobs there is no cap and no required reserve: the owner and GC may agree to hold back any portion until substantial completion, and §715.12(7) then requires the owner to release the balance within 14 days after the certificate of substantial completion, certificate of occupancy, or possession, once the punchlist is done. Late retainage bears the §55.03 judgment rate plus 12% a year.

## Retainage on private jobs

| Rule | Florida law |
|---|---|
| Retainage cap | No statutory cap; the contract sets the rate |
| Release deadline | 14 days Owner may hold back part of each progress payment until substantial completion; balance including retainage is due within 14 days after the architect or engineer certifies substantial completion, a certificate of occupancy issues, or the owner takes possession, and the contractor has finished the owner's punchlist ([Fla. Stat. §715.12(7)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0700-0799/0715/Sections/0715.12.html)) |
| Interest on late retainage | Section 55.03 judgment rate plus 12% per annum on retainage held past the due date; for lower tiers, retainage bears interest 14 days after it is due under the sub-level contract and the pay-when-paid conditions are met ([Fla. Stat. §715.12(7)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0700-0799/0715/Sections/0715.12.html)) |
| Escrow or bond instead of retainage | Obligee may withdraw retained amounts by depositing US Treasury obligations, State of Florida bonds or notes, or insured certificates of deposit with the obligor (s. 715.12(7)(c)); the obligor must remit income on the securities within 30 days ([Fla. Stat. §715.12(7)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0700-0799/0715/Sections/0715.12.html)) |

Florida sets no cap on private-job retainage and no statutory lien-fund reserve; the contract sets the percentage. Section 715.12(7) controls only when retainage is released and what interest runs once it is late.

## Retainage on public jobs

| Rule | Florida law |
|---|---|
| Retainage cap | 5% on contracts over $200,000 ([Fla. Stat. §§255.078, 255.077 (state/public entities); §218.735(7)-(8) (local governmental entities)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0200-0299/0255/Sections/0255.078.html)) |
| Release deadline | 20 days Contract must provide a punchlist within 30 days after substantial completion (projects under $10M) or 30-45 days ($10M and over); the public entity then pays the balance including retainage, less 150% of the cost to complete listed items, within 20 business days after the list is developed and a proper invoice is received ([Fla. Stat. §§255.078, 255.077 (state/public entities); §218.735(7)-(8) (local governmental entities)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0200-0299/0255/Sections/0255.078.html)) |
| Prime passes the sub's share within | 10 days of receiving it ([Fla. Stat. §§255.078, 255.077 (state/public entities); §218.735(7)-(8) (local governmental entities)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0200-0299/0255/Sections/0255.078.html)) |
| Interest on late retainage | 2% per month on payments not made within the statutory limits (state: s. 255.073(4); local: s. 218.735(9), or the contract rate if greater) ([Fla. Stat. §§255.078, 255.077 (state/public entities); §218.735(7)-(8) (local governmental entities)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0200-0299/0255/Sections/0255.078.html)) |
| Applies to local governments | Yes ([Fla. Stat. §§255.078, 255.077 (state/public entities); §218.735(7)-(8) (local governmental entities)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0200-0299/0255/Sections/0255.078.html)) |

## When the GC says it hasn't been paid in Florida

Florida writes pay-when-paid into the statute for private jobs. A GC or sub is obliged to pay the next tier only once it has been paid by the person above it for the work in the sub's request (§715.12(4)(b)). The statute does not void a contract clause making payment conditional on the owner paying; it controls the timing and the interest once the money arrives. If the GC has been paid and still withholds, the 12% over the judgment rate starts to run on the 14th day after payment was due. An obligor cannot withhold payment for unrelated labor, services, or materials just because it disputes a different item (§715.12(6)(e)). On public jobs, §255.073(3) starts the sub's 10-day clock when the prime receives payment from the agency.

## After the deadline: what a sub can do in Florida

For a private pay app that is late, a Florida sub (1) confirms its written request for payment and required waivers were delivered, because those are conditions in §715.12(4); (2) checks whether the GC returned the request within 14 days with written reasons (§715.12(5)(b)); if not, interest runs; (3) sends a written demand for the unpaid amount and statutory interest; (4) serves its notice to owner and records a claim of lien within the Chapter 713 deadlines, which are separate from this statute. §715.12 creates no separate cause of action except to collect the interest (§715.12(6)(b)) and no attorney's fee right. On a public job, send a written demand citing §255.073 or §218.735 and the 2% per month rate.

## Florida quirks to know

Section 715.12 applies only to written contracts that carry construction lien rights under Chapter 713 Part I. The rate is the §55.03 judgment rate (reset quarterly by the CFO) plus 12%, not a fixed percentage, so interest calculators need a rate input. On public jobs the 5% cap does not apply to contracts of $200,000 or less, or to federally funded work with contrary federal requirements (§255.078(5)-(6)). Retainage cannot be held to secure insurance premiums under a wrap-up program, and warranty items cannot delay the final retainage release (§255.077(7)-(8)). Private retainage can be swapped for deposited Treasury securities, State of Florida bonds, or insured CDs (§715.12(7)(c)). On local-government contracts from July 1, 2025, a conforming change-order quote not approved or denied in writing within 35 days is deemed approved at the quoted price (§218.755).

## Worked example: retainage on a $480,000 subcontract in Florida

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 10% = $48,000 |
| Completion | June 15, 2026 |
| Private job: owner releases by | June 29, 2026 ([Fla. Stat. §715.12(7)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0700-0799/0715/Sections/0715.12.html)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Private job, 10% retainage = $48,000 (no cap applies). Assume the architect certifies substantial completion on 2026-06-15 and no punchlist is delivered within the contract period. Under §715.12(7)(a) interest begins 14 days after the certificate: 2026-06-29. Interest is the §55.03 rate plus 12% a year on $48,000; the 12% add-on alone is $48,000 x 12% x 30/365 = $473.42 for each 30 days late, before adding the quarterly §55.03 rate (not read). On a public job the cap would be 5% = $24,000 (contract over $200,000), the entity would owe the balance 20 business days after the punchlist is made, and late sums bear 2% per month, or $480 per month on $24,000.

## Florida retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/florida/#calculator. The statutory figures it starts from:

- **Private job:** 14 days (Owner may hold back part of each progress payment until substantial completion; balance including retainage is due within 14 days after the architect or engineer certifies substantial completion, a certificate of occupancy issues, or the owner takes possession, and the contractor has finished the owner's punchlist); interest: Section 55.03 judgment rate plus 12% per annum on retainage held past the due date; for lower tiers, retainage bears interest 14 days after it is due under the sub-level contract and the pay-when-paid conditions are met.
- **Public job:** 20 days (Contract must provide a punchlist within 30 days after substantial completion (projects under $10M) or 30-45 days ($10M and over); the public entity then pays the balance including retainage, less 150% of the cost to complete listed items, within 20 business days after the list is developed and a proper invoice is received); then 10 days for the GC to pay the sub; interest: 2% per month on payments not made within the statutory limits (state: s. 255.073(4); local: s. 218.735(9), or the contract rate if greater).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Florida retainage law: questions

### Is there a cap on retainage on a private construction job in Florida?

No. Section 715.12(7) lets the owner and contractor agree to withhold a portion of each progress payment until substantial completion but sets no maximum percentage. Public entities are capped at 5% under §255.078 and §218.735(8).

### How long does an owner have to release retainage on a private Florida project?

Within 14 days after the architect or engineer certifies substantial completion, a certificate of occupancy issues, or the owner takes possession, and the contractor has substantially completed the owner's punchlist (Fla. Stat. §715.12(7)(a)). The contract may set a shorter time.

### How long does a Florida public entity have to release retainage after substantial completion?

The contract must set up a punchlist within 30 calendar days after substantial completion for projects under $10 million, then the entity pays the balance, including retainage, less 150% of the cost to complete listed items, within 20 business days of the list and a proper invoice (Fla. Stat. §255.077(1), (4)).

## Sources

- [Fla. Stat. §715.12(7)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0700-0799/0715/Sections/0715.12.html)
- [Fla. Stat. §§255.078, 255.077 (state/public entities); §218.735(7)-(8) (local governmental entities)](https://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0200-0299/0255/Sections/0255.078.html)

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [Florida prompt payment law](https://fynex.ai/construction/prompt-payment/florida/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- Florida
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)