title: "Hawaii Retainage Law (2026): Cap, Release Deadline & Interest"
description: "Hawaii retainage: no statute on private jobs, the subcontract governs; public jobs cap 5%, release within 30 days. Statute, release dates and a calculator."
url: "/construction/retainage/hawaii/"
updated: "2026-10-14"
---

Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Hawaii retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Hawaii retainage law: cap, release deadline and interest

_Law as of October 14, 2026. This page explains the law; it is not legal advice._

Hawaii regulates retainage only on public contracts. The procurement officer may withhold no more than 5% of the amount due the contractor, and once the contract is 50% complete with satisfactory progress, no further sum may be withheld (Haw. Rev. Stat. §103-32.1(c)). A prime cannot hold a bonded sub's retainage at a higher percentage than its own, and on final payment the sub's full retainage is due within 10 days after the prime receives the money (§103-10.5(b)). Late retainage carries a 1.5% per month penalty. On private jobs there is no cap, release date or interest rule for retainage; the contract controls.

## Retainage on private jobs

**No statute.** No Hawaii statute caps, times or regulates private-job retainage in the sections read (HRS chapter 444 and §103-32.1 apply to licensed contractors and public contracts). The contract controls the percentage and release date. On a private job the only payment statute is HRS §444-25, which times the GC's payment to a sub (10 days after the sub's invoice and the owner's payment) and carries 1.5% per month interest.

## Retainage on public jobs

| Rule | Hawaii law |
|---|---|
| Retainage cap | 5% of each payment ([Haw. Rev. Stat. §§103-32.1, 103-32.2, 103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-32.1.html)) |
| Release deadline | 30 days Public contract retainage held by the procurement officer is capped at 5% of the amount due, with no further sum withheld after 50% completion if progress is satisfactory; on final payment to the contractor, full payment to subs including retainage is due within 10 days after the contractor receives the money, if there is no bona fide dispute; a sub with a bond or acceptable collateral can have its retainage released on proof of completion and 90 days without a claim ([Haw. Rev. Stat. §§103-32.1, 103-32.2, 103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-32.1.html)) |
| Prime passes the sub's share within | 10 days of receiving it ([Haw. Rev. Stat. §§103-32.1, 103-32.2, 103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-32.1.html)) |
| Interest on late retainage | Penalty of 1.5% per month on retainage the responsible party fails to pay on time; state or county interest at WSJ prime plus 2% after 30 days (HRS §103-10) ([Haw. Rev. Stat. §§103-32.1, 103-32.2, 103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-32.1.html)) |
| Retainage bond in lieu | Allowed ([Haw. Rev. Stat. §§103-32.1, 103-32.2, 103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-32.1.html)) |
| Applies to local governments | Yes ([Haw. Rev. Stat. §§103-32.1, 103-32.2, 103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-32.1.html)) |

## When the GC says it hasn't been paid in Hawaii

Hawaii's private-job statute starts the GC's 10 days at the later of the sub's invoice or the GC's receipt of the owner's payment, so a GC need not pay a sub before it is paid for that work (HRS §444-25). If the bid solicitation states that payment is contingent on funds held in escrow or trust, interest does not start until the tenth day after the sub's invoice and receipt of those funds. On public jobs a dispute between a contractor and a sub of any tier is not a dispute to which the State or a county is a party, and no right of action lies against them (HRS §103-32.1(b)). The statutes read do not address pay-if-paid clauses directly.

## After the deadline: what a sub can do in Hawaii

A Hawaii sub with a late payment on a private job (1) checks that it sent an invoice with the supporting documents the subcontract requires, and that the GC has been paid for the sub's work, which together start the 10-day clock; (2) confirms there is no bona fide dispute and no escrow-or-trust contingency stated in the bid solicitation; (3) demands payment plus interest at 1.5% per month from the due date; (4) pursues the claim under the subcontract, and its lien and bond rights on separate deadlines. On a public job, a sub whose retainage is not released within 10 days of the prime's receipt can invoke the 1.5% per month penalty under HRS §103-10.5 and the contractor-licensing referral for repeat violations.

## Hawaii quirks to know

Hawaii's public-work rule for subs: a bonded sub's retainage cannot exceed the prime's percentage (§103-32.1(d)); parties may still agree to retain up to 10% of each progress payment from a sub without incurring late-payment interest (§103-32.1(e)(1)). A prime that violates the 10-day retainage rule three or more times within two years is referred to the contractor license board (§103-10.5(c)). The official capitol.hawaii.gov site blocks automated access, so this record was built from a mirror dated 2016, checked against archived copies of the official §§103-10.5 and 444-25 pages (February 2025), which match. Two bills of the 2025-2026 Legislature did not become law: H.B. 274 (a 30-day invoice rule with compounding interest for private subs) and S.B. 1587 (a public retainage rewrite).

## Worked example: retainage on a $480,000 subcontract in Hawaii

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Public job: owner releases by | July 15, 2026 ([Haw. Rev. Stat. §§103-32.1, 103-32.2, 103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-32.1.html)) |
| GC pays the sub's share by | July 25, 2026 ([Haw. Rev. Stat. §§103-32.1, 103-32.2, 103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-32.1.html)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Public job: retainage is capped at 5% and stops at 50% completion if progress is satisfactory, so the most the procurement officer holds is 5% x $240,000 = $12,000 (the first half of the $480,000 contract); a prime may hold no more than that percentage from a bonded sub. If the final statement is submitted on 2026-06-15, the State or county owes payment by 2026-07-15 (30 calendar days, HRS §103-10), after which interest runs at WSJ prime plus 2% (current prime not read). The prime then has 10 days after receipt to pay the sub's full retainage; a $12,000 payment 30 days late carries a 1.5% per month penalty = $180 (HRS §103-10.5). Private job: no retainage statute; a GC that is paid by the owner on 2026-06-15 for the sub's invoiced work owes the sub by 2026-06-25 and 1.5% per month interest after that (HRS §444-25).

## Hawaii retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/hawaii/#calculator. The statutory figures it starts from:

- **Private job:** no statutory deadline; no fixed statutory interest rate.
- **Public job:** 30 days (Public contract retainage held by the procurement officer is capped at 5% of the amount due, with no further sum withheld after 50% completion if progress is satisfactory; on final payment to the contractor, full payment to subs including retainage is due within 10 days after the contractor receives the money, if there is no bona fide dispute; a sub with a bond or acceptable collateral can have its retainage released on proof of completion and 90 days without a claim); then 10 days for the GC to pay the sub; interest: Penalty of 1.5% per month on retainage the responsible party fails to pay on time; state or county interest at WSJ prime plus 2% after 30 days (HRS §103-10).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Hawaii retainage law: questions

### Is there a retainage cap on private construction in Hawaii?

No private-job cap was found in the statutes read. HRS §103-32.1 caps retainage at 5% for public contracts only; on private jobs the contract sets the rate.

### What is the retainage limit on Hawaii public works?

5% of the amount due the contractor, with no additional retainage once the contract is 50% complete and progress is satisfactory (Haw. Rev. Stat. §103-32.1(c)). A prime cannot hold a bonded sub's retainage at a higher percentage than the prime's own (§103-32.1(d)).

### When is sub retainage due on a Hawaii public project?

Within 10 days after the prime receives the final payment from the procurement officer, if there is no bona fide dispute over the sub's performance (HRS §103-10.5(b)). A 1.5% per month penalty applies if the money is not paid on time.

## Sources

- [Haw. Rev. Stat. §§103-32.1, 103-32.2, 103-10, 103-10.5](https://law.onecle.com/hawaii/title-9/103-32.1.html) (mirror; the official site did not load)

Sources marked "mirror" were read from the linked copy on October 14, 2026 because the state's official code site did not load for us. Check the official code before relying on those figures.

Statutes as read on October 14, 2026. This page explains the law; it is not legal advice.

## Related

- [Hawaii prompt payment law](https://fynex.ai/construction/prompt-payment/hawaii/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- Hawaii
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)