Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Illinois retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Illinois retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Illinois caps private retainage at 10% before the job is half complete and 5% after, under the Contractor Prompt Payment Act (815 ILCS 603/20, P.A. 101-432, effective August 20, 2019): up to 10% of any payment made before 50% completion, a reduction to no more than 5% held at the 50% mark, and no more than 5% of any later payment. On bonded public works, local governments follow the same 10%-then-5% limits since January 1, 2024, and so do primes and subs toward their own subs (30 ILCS 550/1). The State joins on June 1, 2027. A request for release of retainage is a payment application, so it follows the 25-day deemed-approval and 15-day payment cycle, and the GC passes each sub's share down within 15 days.

## Retainage on private jobs

| Rule | Illinois law |
|---|---|
| Retainage cap | 10% of each payment ([815 ILCS 603/20 (added by P.A. 101-432, eff. Aug. 20, 2019); 603/5(a), 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K20)) |
| How the cap applies | Up to 10% of any payment made before the contract is 50% complete; when the contract is 50% complete retainage held is reduced so no more than 5% is held, and no more than 5% of any later payment may be held ([815 ILCS 603/20 (added by P.A. 101-432, eff. Aug. 20, 2019); 603/5(a), 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K20)) |
| Release deadline | 40 days A request for release of retainage is a 'payment application' under the Act: deemed approved 25 days after the owner receives it unless the owner states reasons, then paid within 15 days of approval; the GC then pays subs within 15 calendar days of receiving the retainage monies ([815 ILCS 603/20 (added by P.A. 101-432, eff. Aug. 20, 2019); 603/5(a), 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K20)) |
| GC passes the sub's share within | 15 days of receiving it ([815 ILCS 603/20 (added by P.A. 101-432, eff. Aug. 20, 2019); 603/5(a), 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K20)) |
| Interest on late retainage | 10% per annum on any payment not made in time, including retainage release ([815 ILCS 603/20 (added by P.A. 101-432, eff. Aug. 20, 2019); 603/5(a), 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K20)) |

## Retainage on public jobs

| Rule | Illinois law |
|---|---|
| Retainage cap | 10% (Local governmental units (and their contractors toward subs), bonded public works: up to 10% of any payment before 50% completion. Bond required on public work costing over $150,000 until Jan. 1, 2029 (over $50,000 after; IDOT and the Tollway over $500,000); a local unit may require a bond on smaller contracts by ordinance.); 5% (Reduced so no more than 5% is held at 50% completion; no more than 5% of later payments.) ([Public Construction Bond Act, 30 ILCS 550/1 (as amended by P.A. 102-968, eff. Jan. 1, 2023, and P.A. 103-570, eff. Jan. 1, 2024; further amended by P.A. 104-0168, eff. June 1, 2027)](https://www.ilga.gov/Legislation/PublicActs/View/104-0168)) |
| Release deadline | No statutory release date was read. Local governmental units must cut retainage to 5% at 50% completion (30 ILCS 550/1, as amended by P.A. 103-570, eff. Jan. 1, 2024). The contractor and its subs may not withhold from their subs more than 10% before 50% completion and must reduce to 5% at 50%. From June 1, 2027 (P.A. 104-0168, HB 1224), the same 10%/5% limit applies to the State (except IDOT), and on State contracts entered into on or after that date a State agency may retain only when it finds unsatisfactory progress, case by case, and a contractor may retain from a sub only to the extent the agency retained on that sub's work (not the Tollway) ([Public Construction Bond Act, 30 ILCS 550/1 (as amended by P.A. 102-968, eff. Jan. 1, 2023, and P.A. 103-570, eff. Jan. 1, 2024; further amended by P.A. 104-0168, eff. June 1, 2027)](https://www.ilga.gov/Legislation/PublicActs/View/104-0168)) |
| Prime passes the sub's share within | 15 days of receiving it ([Public Construction Bond Act, 30 ILCS 550/1 (as amended by P.A. 102-968, eff. Jan. 1, 2023, and P.A. 103-570, eff. Jan. 1, 2024; further amended by P.A. 104-0168, eff. June 1, 2027)](https://www.ilga.gov/Legislation/PublicActs/View/104-0168)) |
| Interest on late retainage | Contractor pays sub-tier 2% per month on late pass-through (15 days after receipt); public-entity late payment interest 1% per month (local and state) ([Public Construction Bond Act, 30 ILCS 550/1 (as amended by P.A. 102-968, eff. Jan. 1, 2023, and P.A. 103-570, eff. Jan. 1, 2024; further amended by P.A. 104-0168, eff. June 1, 2027)](https://www.ilga.gov/Legislation/PublicActs/View/104-0168)) |
| Applies to local governments | Yes ([Public Construction Bond Act, 30 ILCS 550/1 (as amended by P.A. 102-968, eff. Jan. 1, 2023, and P.A. 103-570, eff. Jan. 1, 2024; further amended by P.A. 104-0168, eff. June 1, 2027)](https://www.ilga.gov/Legislation/PublicActs/View/104-0168)) |

## When the GC says it hasn't been paid in Illinois

Illinois' private-job clock starts when the GC receives payment from the owner: the GC must pay its sub within 15 calendar days of receipt of each periodic payment, final payment or retainage monies, for work the owner, the owner's agent or the GC has accepted (815 ILCS 603/10(2)). On public work, when the contractor receives less than the full payment, it must disburse the funds received pro rata among itself, subs and suppliers, and the sub-tier statute applies throughout the chain (50 ILCS 505/9; 30 ILCS 540/7). A State-contract sub with an unpaid claim can file a written notice with the State agency, which then convenes an administrative-law-judge hearing within 15 days. The Contractor Prompt Payment Act does not bar contract language conditioning a sub's pay on owner payment; that is a case-law question.

## After the deadline: what a sub can do in Illinois

An Illinois sub with a late payment (1) confirms its pay app or retainage request was submitted under the contract and is a 'payment application', and counts 25 days to deemed approval plus 15 days to pay; (2) sends written notice of the missed payment; after 7 calendar days' written notice the sub may suspend performance without breach (815 ILCS 603/15(b)); (3) demands 10% per annum interest from the due date; (4) on a public job, claims the 2% per month pass-through interest and, on State contracts, files a written notice with the State agency for an ALJ hearing (30 ILCS 540/7); (5) files a mechanic's lien or bond claim on separate deadlines.

## Illinois quirks to know

Illinois uses a deemed-approval device: silence by the owner for 25 days approves the pay app, and the 15-day payment clock starts on that approval. A sub's 15-day clock includes retainage monies. The private act excludes public-funds contracts and residential projects of 12 or fewer units in a single building. Public retainage limits apply where the Public Construction Bond Act requires a bond: work costing over $150,000 until January 1, 2029 (over $500,000 for IDOT and the Tollway), then over $50,000. From June 1, 2027 (P.A. 104-0168, HB 1224) the 10%/5% limit extends to the State except IDOT, and State agencies may retain on new contracts only for unsatisfactory progress, case by case, with sub retainage limited to what the agency held on that sub's work.

## Worked example: retainage on a $480,000 subcontract in Illinois

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Private job: owner releases by | July 25, 2026 ([815 ILCS 603/20 (added by P.A. 101-432, eff. Aug. 20, 2019); 603/5(a), 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K20)) |
| GC pays the sub's share by | August 9, 2026 ([815 ILCS 603/20 (added by P.A. 101-432, eff. Aug. 20, 2019); 603/5(a), 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K20)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Private commercial job. Retainage may be 10% of payments before 50% completion and 5% after, so the most that can be held at completion is 5% x $480,000 = $24,000 (10% of the first $240,000 = $24,000, reduced to $12,000 at the 50% mark, plus 5% of the second $240,000 = $12,000). The contractor's request for release of retainage on 2026-06-15 is deemed approved 25 days later, 2026-07-10, and payment is due 15 days after approval: 2026-07-25 (815 ILCS 603/10(1)). If the owner pays on 2026-09-25, 62 days late, interest at 10% per annum is $24,000 x 10% x 62/365 = $407.67 (603/15(a)). The GC then has 15 calendar days after receipt to pay each sub's share (603/10(2)).

## Illinois retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/illinois/#calculator. The statutory figures it starts from:

- **Private job:** 40 days (A request for release of retainage is a 'payment application' under the Act: deemed approved 25 days after the owner receives it unless the owner states reasons, then paid within 15 days of approval; the GC then pays subs within 15 calendar days of receiving the retainage monies); then 15 days for the GC to pay the sub; interest: 10% per annum on any payment not made in time, including retainage release.
- **Public job:** no statutory deadline; then 15 days for the GC to pay the sub; interest: Contractor pays sub-tier 2% per month on late pass-through (15 days after receipt); public-entity late payment interest 1% per month (local and state).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Illinois retainage law: questions

### What is the retainage cap on a private Illinois construction contract?

10% of any payment made before the contract is 50% complete; at 50% retainage is reduced so no more than 5% is held, and no more than 5% of later payments may be withheld (815 ILCS 603/20, from P.A. 101-0432). Residential projects of 12 or fewer units and public-funds contracts are excluded.

### Does Illinois cap retainage on local government projects?

Yes, on contracts that require a bond under the Public Construction Bond Act: no more than 10% of any payment before 50% completion, reduced to 5% at 50% and 5% of later payments, since January 1, 2024 (30 ILCS 550/1, P.A. 103-570). Primes and subs face the same 10%/5% limit toward their own subs. State-agency limits under P.A. 104-0168 take effect June 1, 2027.

## Sources

- [815 ILCS 603/20 (added by P.A. 101-432, eff. Aug. 20, 2019); 603/5(a), 603/10, 603/15](https://www.ilga.gov/legislation/ilcs/fulltext.asp?DocName=081506030K20) (mirror; the official site did not load)
- [Public Construction Bond Act, 30 ILCS 550/1 (as amended by P.A. 102-968, eff. Jan. 1, 2023, and P.A. 103-570, eff. Jan. 1, 2024; further amended by P.A. 104-0168, eff. June 1, 2027)](https://www.ilga.gov/Legislation/PublicActs/View/104-0168) (mirror; the official site did not load)

Sources marked "mirror" were read from the linked copy on October 13, 2026 because the state's official code site did not load for us. Check the official code before relying on those figures.

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Illinois prompt payment law](https://fynex.ai/construction/prompt-payment/illinois/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- Illinois
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- [Kansas](https://fynex.ai/construction/retainage/kansas/)
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)