Construction · Retainage law

Kansas retainage law: cap, release deadline and interest

Kansas caps retainage by statute on both private and public jobs: 5% of the contract or subcontract value by default, up to a hard ceiling of 10%. The owner must release all remaining retainage within 30 days after substantial completion, and late retainage earns 18% per annum interest from the first business day it was due. Single-family homes and multifamily housing of four units or less are outside the private act, and KDOT-spec road, highway and bridge work is outside the public act.

Also in Kansas: prompt payment law

Kansas retainage release date and interest calculator

Enter the completion date and the retainage held. The release and pass-through days and the interest rate are pre-filled from Kansas law; change them if your contract or the statute's trigger differs.

Job type

Clock starts: Owner releases all remaining retainage on any undisputed payment within 30 days after substantial completion of the project; the owner may hold the share tied to a contractor still working until 30 days after that work is completed. Early release if owner, contractor and architect/engineer agree a sub is finished

Statute: 18% per annum from the first business day after the retainage was due (K.S.A. 16-1804(j)); suspension of work after 7 + 7 business days' notice is allowed under 16-1805

Owner releases by
July 15, 2026
GC pays the sub's share by
July 22, 2026
Days late
30
Interest owed
—
Total now owed
$24,000.00

No fixed statutory rate: enter the rate from the statute or your contract.

Statute: K.S.A. 16-1804, 16-1801(b), 16-1802

Calendar days and simple interest (annual rate ÷ 365 per day late). If the statute counts business days or your contract sets a shorter clock, edit the days. A guide to the statute, not legal advice.

Retainage on private jobs

RuleKansas law
Retainage cap5% of each paymentK.S.A. 16-1804, 16-1801(b), 16-1802
Release deadline30 days Owner releases all remaining retainage on any undisputed payment within 30 days after substantial completion of the project; the owner may hold the share tied to a contractor still working until 30 days after that work is completed. Early release if owner, contractor and architect/engineer agree a sub is finishedK.S.A. 16-1804, 16-1801(b), 16-1802
GC passes the sub's share within7 days of receiving itK.S.A. 16-1804, 16-1801(b), 16-1802
Interest on late retainage18% per annum from the first business day after the retainage was due (K.S.A. 16-1804(j)); suspension of work after 7 + 7 business days' notice is allowed under 16-1805K.S.A. 16-1804, 16-1801(b), 16-1802
Escrow or bond instead of retainageBefore work starts, a GC or sub may request alternate security (irrevocable letter of credit, certificate of deposit, cash bond or similar asset worth at least the retainage; not a performance or payment bond) instead of retainage; the party holding the retainage chooses which type to acceptK.S.A. 16-1804, 16-1801(b), 16-1802
Can the contract waive the rule?NoK.S.A. 16-1804, 16-1801(b), 16-1802

Retainage on public jobs

RuleKansas law
Retainage cap5% of each paymentK.S.A. 16-1904, 16-1902
Release deadline30 days Owner, contractor or sub must release all remaining retainage on undisputed payments within 30 days after substantial completion, as part of the regular payment cycle; portion tied to still-unfinished work held until 30 days after that work is completedK.S.A. 16-1904, 16-1902
Prime passes the sub's share within7 days of receiving itK.S.A. 16-1904, 16-1902
Interest on late retainage18% per annum from the first business day after the retainage was due (K.S.A. 16-1904(i))K.S.A. 16-1904, 16-1902
Retainage bond in lieuAlternate security in lieu of retainage on request before work starts; the retaining party picks the type (K.S.A. 16-1904(f)-(g))K.S.A. 16-1904, 16-1902
Applies to local governmentsYesK.S.A. 16-1904, 16-1902

When the GC says it hasn't been paid in Kansas

A pay-if-paid clause is no defense to a Kansas mechanic's lien or bond claim (K.S.A. 16-1803(c)), but the act's payment clock for the GC starts when the GC receives payment: 7 business days after receipt, including retainage if released. Kansas does not void pay-if-paid for contract claims in the act itself: it removes the defense against lien and bond claims. Rights in the act cannot be waived or varied by contract (K.S.A. 16-1801(b)).

After the deadline: what a sub can do in Kansas

If undisputed pay is 7 business days late, a contractor or sub of any tier can give 7 additional business days' written notice (to the owner, and to the GC if you are a sub) and then suspend work without prejudice to other remedies; contract time extends and the price increases by demobilization and remobilization costs (K.S.A. 16-1805). Claim 18% per annum, sue or arbitrate in the county where the property sits, and recover attorney fees (16-1806). Keep mechanic's lien deadlines under K.S.A. 60-1101 running.

Kansas quirks to know

Retainage is 5% unless a higher rate is 'required to ensure performance', but never over 10% of the contract value or of any undisputed payment. Withholding for incomplete work is capped at 150% of its value and must be paid within 45 days after completion. Owners may raise retainage to 10% for a lagging contractor. Rights are non-waivable, and a waiver clause is unenforceable. The private act excludes public works, the public act excludes KDOT-spec roads/highways/bridges, and the public act's 'construction' excludes roads, highways and bridges.

Worked example: retainage on a $480,000 subcontract in Kansas

Subcontract$480,000
Retainage held5% = $24,000
CompletionJune 15, 2026
Private job: owner releases byJuly 15, 2026K.S.A. 16-1804, 16-1801(b), 16-1802
GC pays the sub's share byJuly 22, 2026K.S.A. 16-1804, 16-1801(b), 16-1802
Interest if paid 30 days lateNo statutory rate; the contract governs

Kansas private commercial subcontract of $480,000 with the default 5% retainage (K.S.A. 16-1804(a)): retainage held is $24,000. Substantial completion 2026-06-15; the owner must release by 2026-07-15 (30 days, 16-1804(c)), and the GC must pass the sub's share on within 7 business days of receipt (16-1803(f)). If the owner pays 30 days late, interest at 18% per annum on $24,000 for 30 days is about $355.07 ($24,000 x 18% x 30/365), accruing from the first business day after 2026-07-15.

Run a payment like this in the split calculator

Kansas retainage law: questions

What is the maximum retainage on a Kansas private construction contract?

5% of the contract or subcontract value by default, and never more than 10% (K.S.A. 16-1804(a), (i)). The owner can raise it to 10% if the contractor is behind schedule or has workmanship problems (16-1804(b)).

When must a Kansas owner release retainage?

All remaining retainage on undisputed payments within 30 days after substantial completion; any part tied to work still being done can be held until 30 days after that work is finished (K.S.A. 16-1804(c)).

Sources

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

Book a demo