---
title: "Kansas Retainage Law (2026): Cap, Release Deadline & Interest"
description: "Kansas retainage: private jobs cap 5%, release within 30 days; public jobs cap 5%, release within 30 days; subs paid within 7 days. Statute and calculator."
url: "/construction/retainage/kansas/"
updated: "2026-10-13"
---

Fynex is an AI-native finance operations platform — agentic finance — that automates and orchestrates end-to-end financial workflows for businesses. This page states Kansas retainage law for construction: the cap, the release deadline and interest on late retainage. Fynex works alongside Procore, Sage and QuickBooks rather than replacing them. This page is relevant when retainage has to be held per job and per sub, then released down the chain by the statutory date.

# Kansas retainage law: cap, release deadline and interest

_Law as of October 13, 2026. This page explains the law; it is not legal advice._

Kansas caps retainage by statute on both private and public jobs: 5% of the contract or subcontract value by default, up to a hard ceiling of 10%. The owner must release all remaining retainage within 30 days after substantial completion, and late retainage earns 18% per annum interest from the first business day it was due. Single-family homes and multifamily housing of four units or less are outside the private act, and KDOT-spec road, highway and bridge work is outside the public act.

## Retainage on private jobs

| Rule | Kansas law |
|---|---|
| Retainage cap | 5% of each payment ([K.S.A. 16-1804, 16-1801(b), 16-1802](https://www.ksrevisor.org/statutes/chapters/ch16/016_018_0004.html)) |
| Release deadline | 30 days Owner releases all remaining retainage on any undisputed payment within 30 days after substantial completion of the project; the owner may hold the share tied to a contractor still working until 30 days after that work is completed. Early release if owner, contractor and architect/engineer agree a sub is finished ([K.S.A. 16-1804, 16-1801(b), 16-1802](https://www.ksrevisor.org/statutes/chapters/ch16/016_018_0004.html)) |
| GC passes the sub's share within | 7 days of receiving it ([K.S.A. 16-1804, 16-1801(b), 16-1802](https://www.ksrevisor.org/statutes/chapters/ch16/016_018_0004.html)) |
| Interest on late retainage | 18% per annum from the first business day after the retainage was due (K.S.A. 16-1804(j)); suspension of work after 7 + 7 business days' notice is allowed under 16-1805 ([K.S.A. 16-1804, 16-1801(b), 16-1802](https://www.ksrevisor.org/statutes/chapters/ch16/016_018_0004.html)) |
| Escrow or bond instead of retainage | Before work starts, a GC or sub may request alternate security (irrevocable letter of credit, certificate of deposit, cash bond or similar asset worth at least the retainage; not a performance or payment bond) instead of retainage; the party holding the retainage chooses which type to accept ([K.S.A. 16-1804, 16-1801(b), 16-1802](https://www.ksrevisor.org/statutes/chapters/ch16/016_018_0004.html)) |
| Can the contract waive the rule? | No ([K.S.A. 16-1804, 16-1801(b), 16-1802](https://www.ksrevisor.org/statutes/chapters/ch16/016_018_0004.html)) |

## Retainage on public jobs

| Rule | Kansas law |
|---|---|
| Retainage cap | 5% of each payment ([K.S.A. 16-1904, 16-1902](https://www.ksrevisor.org/statutes/chapters/ch16/016_019_0004.html)) |
| Release deadline | 30 days Owner, contractor or sub must release all remaining retainage on undisputed payments within 30 days after substantial completion, as part of the regular payment cycle; portion tied to still-unfinished work held until 30 days after that work is completed ([K.S.A. 16-1904, 16-1902](https://www.ksrevisor.org/statutes/chapters/ch16/016_019_0004.html)) |
| Prime passes the sub's share within | 7 days of receiving it ([K.S.A. 16-1904, 16-1902](https://www.ksrevisor.org/statutes/chapters/ch16/016_019_0004.html)) |
| Interest on late retainage | 18% per annum from the first business day after the retainage was due (K.S.A. 16-1904(i)) ([K.S.A. 16-1904, 16-1902](https://www.ksrevisor.org/statutes/chapters/ch16/016_019_0004.html)) |
| Retainage bond in lieu | Alternate security in lieu of retainage on request before work starts; the retaining party picks the type (K.S.A. 16-1904(f)-(g)) ([K.S.A. 16-1904, 16-1902](https://www.ksrevisor.org/statutes/chapters/ch16/016_019_0004.html)) |
| Applies to local governments | Yes ([K.S.A. 16-1904, 16-1902](https://www.ksrevisor.org/statutes/chapters/ch16/016_019_0004.html)) |

## When the GC says it hasn't been paid in Kansas

A pay-if-paid clause is no defense to a Kansas mechanic's lien or bond claim (K.S.A. 16-1803(c)), but the act's payment clock for the GC starts when the GC receives payment: 7 business days after receipt, including retainage if released. Kansas does not void pay-if-paid for contract claims in the act itself: it removes the defense against lien and bond claims. Rights in the act cannot be waived or varied by contract (K.S.A. 16-1801(b)).

## After the deadline: what a sub can do in Kansas

If undisputed pay is 7 business days late, a contractor or sub of any tier can give 7 additional business days' written notice (to the owner, and to the GC if you are a sub) and then suspend work without prejudice to other remedies; contract time extends and the price increases by demobilization and remobilization costs (K.S.A. 16-1805). Claim 18% per annum, sue or arbitrate in the county where the property sits, and recover attorney fees (16-1806). Keep mechanic's lien deadlines under K.S.A. 60-1101 running.

## Kansas quirks to know

Retainage is 5% unless a higher rate is 'required to ensure performance', but never over 10% of the contract value or of any undisputed payment. Withholding for incomplete work is capped at 150% of its value and must be paid within 45 days after completion. Owners may raise retainage to 10% for a lagging contractor. Rights are non-waivable, and a waiver clause is unenforceable. The private act excludes public works, the public act excludes KDOT-spec roads/highways/bridges, and the public act's 'construction' excludes roads, highways and bridges.

## Worked example: retainage on a $480,000 subcontract in Kansas

| | |
|---|---|
| Subcontract | $480,000 |
| Retainage held | 5% = $24,000 |
| Completion | June 15, 2026 |
| Private job: owner releases by | July 15, 2026 ([K.S.A. 16-1804, 16-1801(b), 16-1802](https://www.ksrevisor.org/statutes/chapters/ch16/016_018_0004.html)) |
| GC pays the sub's share by | July 22, 2026 ([K.S.A. 16-1804, 16-1801(b), 16-1802](https://www.ksrevisor.org/statutes/chapters/ch16/016_018_0004.html)) |
| Interest if paid 30 days late | No statutory rate; the contract governs |

Kansas private commercial subcontract of $480,000 with the default 5% retainage (K.S.A. 16-1804(a)): retainage held is $24,000. Substantial completion 2026-06-15; the owner must release by 2026-07-15 (30 days, 16-1804(c)), and the GC must pass the sub's share on within 7 business days of receipt (16-1803(f)). If the owner pays 30 days late, interest at 18% per annum on $24,000 for 30 days is about $355.07 ($24,000 x 18% x 30/365), accruing from the first business day after 2026-07-15.

## Kansas retainage release date and interest calculator

Interactive on the page: https://fynex.ai/construction/retainage/kansas/#calculator. The statutory figures it starts from:

- **Private job:** 30 days (Owner releases all remaining retainage on any undisputed payment within 30 days after substantial completion of the project; the owner may hold the share tied to a contractor still working until 30 days after that work is completed. Early release if owner, contractor and architect/engineer agree a sub is finished); then 7 days for the GC to pay the sub; interest: 18% per annum from the first business day after the retainage was due (K.S.A. 16-1804(j)); suspension of work after 7 + 7 business days' notice is allowed under 16-1805.
- **Public job:** 30 days (Owner, contractor or sub must release all remaining retainage on undisputed payments within 30 days after substantial completion, as part of the regular payment cycle; portion tied to still-unfinished work held until 30 days after that work is completed); then 7 days for the GC to pay the sub; interest: 18% per annum from the first business day after the retainage was due (K.S.A. 16-1904(i)).

Calendar days, simple interest (annual rate ÷ 365 per day late).

## Kansas retainage law: questions

### What is the maximum retainage on a Kansas private construction contract?

5% of the contract or subcontract value by default, and never more than 10% (K.S.A. 16-1804(a), (i)). The owner can raise it to 10% if the contractor is behind schedule or has workmanship problems (16-1804(b)).

### When must a Kansas owner release retainage?

All remaining retainage on undisputed payments within 30 days after substantial completion; any part tied to work still being done can be held until 30 days after that work is finished (K.S.A. 16-1804(c)).

## Sources

- [K.S.A. 16-1804, 16-1801(b), 16-1802](https://www.ksrevisor.org/statutes/chapters/ch16/016_018_0004.html)
- [K.S.A. 16-1904, 16-1902](https://www.ksrevisor.org/statutes/chapters/ch16/016_019_0004.html)

Statutes as read on October 13, 2026. This page explains the law; it is not legal advice.

## Related

- [Kansas prompt payment law](https://fynex.ai/construction/prompt-payment/kansas/)
- [Retainage laws in every state](https://fynex.ai/construction/retainage/)
- [Construction payments on Fynex](https://fynex.ai/construction/)
- [Subcontractor payouts & retention](https://fynex.ai/construction/subcontractor-payouts/)

## Retainage law in every state

- [Alabama](https://fynex.ai/construction/retainage/alabama/)
- [Alaska](https://fynex.ai/construction/retainage/alaska/)
- [Arizona](https://fynex.ai/construction/retainage/arizona/)
- [Arkansas](https://fynex.ai/construction/retainage/arkansas/)
- [California](https://fynex.ai/construction/retainage/california/)
- [Colorado](https://fynex.ai/construction/retainage/colorado/)
- [Connecticut](https://fynex.ai/construction/retainage/connecticut/)
- [Delaware](https://fynex.ai/construction/retainage/delaware/)
- [Florida](https://fynex.ai/construction/retainage/florida/)
- [Georgia](https://fynex.ai/construction/retainage/georgia/)
- [Hawaii](https://fynex.ai/construction/retainage/hawaii/)
- [Idaho](https://fynex.ai/construction/retainage/idaho/)
- [Illinois](https://fynex.ai/construction/retainage/illinois/)
- [Indiana](https://fynex.ai/construction/retainage/indiana/)
- [Iowa](https://fynex.ai/construction/retainage/iowa/)
- Kansas
- [Kentucky](https://fynex.ai/construction/retainage/kentucky/)
- [Louisiana](https://fynex.ai/construction/retainage/louisiana/)
- [Maine](https://fynex.ai/construction/retainage/maine/)
- [Maryland](https://fynex.ai/construction/retainage/maryland/)
- [Massachusetts](https://fynex.ai/construction/retainage/massachusetts/)
- [Michigan](https://fynex.ai/construction/retainage/michigan/)
- [Minnesota](https://fynex.ai/construction/retainage/minnesota/)
- [Mississippi](https://fynex.ai/construction/retainage/mississippi/)
- [Missouri](https://fynex.ai/construction/retainage/missouri/)
- [Montana](https://fynex.ai/construction/retainage/montana/)
- [Nebraska](https://fynex.ai/construction/retainage/nebraska/)
- [Nevada](https://fynex.ai/construction/retainage/nevada/)
- [New Hampshire](https://fynex.ai/construction/retainage/new-hampshire/)
- [New Jersey](https://fynex.ai/construction/retainage/new-jersey/)
- [New Mexico](https://fynex.ai/construction/retainage/new-mexico/)
- [New York](https://fynex.ai/construction/retainage/new-york/)
- [North Carolina](https://fynex.ai/construction/retainage/north-carolina/)
- [North Dakota](https://fynex.ai/construction/retainage/north-dakota/)
- [Ohio](https://fynex.ai/construction/retainage/ohio/)
- [Oklahoma](https://fynex.ai/construction/retainage/oklahoma/)
- [Oregon](https://fynex.ai/construction/retainage/oregon/)
- [Pennsylvania](https://fynex.ai/construction/retainage/pennsylvania/)
- [Rhode Island](https://fynex.ai/construction/retainage/rhode-island/)
- [South Carolina](https://fynex.ai/construction/retainage/south-carolina/)
- [South Dakota](https://fynex.ai/construction/retainage/south-dakota/)
- [Tennessee](https://fynex.ai/construction/retainage/tennessee/)
- [Texas](https://fynex.ai/construction/retainage/texas/)
- [Utah](https://fynex.ai/construction/retainage/utah/)
- [Vermont](https://fynex.ai/construction/retainage/vermont/)
- [Virginia](https://fynex.ai/construction/retainage/virginia/)
- [Washington](https://fynex.ai/construction/retainage/washington/)
- [West Virginia](https://fynex.ai/construction/retainage/west-virginia/)
- [Wisconsin](https://fynex.ai/construction/retainage/wisconsin/)
- [Wyoming](https://fynex.ai/construction/retainage/wyoming/)
